Another Colorado District Court Refuses to Apply HB 10-1394 Retroactively
October 28, 2011 —
In Martinez v. Mike Wells Construction Company, 09CV227, Teller County District Court Judge Edward S. Colt refused to apply C.R.S. § 13-20-808 retroactively to provide coverage for the underlying construction defect allegations. According to the recitation of facts in Judge Colt’s March 2011 order, Martinez contracted with Mike Wells Construction to serve as the general contractor for the construction of a home. At that time, Mike Wells Construction was insured through ProBuilders Specialty Insurance Company, RRG. Disputes arose between Martinez and Mike Wells Construction, resulting in Martinez ordering it off of the project in mid-November 2007 and terminating its right to work there by letter dated November 28, 2007.
Mike Wells, the owner of the corporation, subsequently died. Martinez sued Mike Wells Construction in July 2009 for breach of contract and various claims relating to alleged defecting workmanship. Martinez provided notice of the suit to the special administrator of the probate estate. No answer having been filed, the court entered a default judgment against Mike Wells Construction and Martinez sought to garnish Mike Wells Construction’s ProBuilders insurance policy.
Read the full story...
Reprinted courtesy of Higgins, Hopkins, McLain & Roswell, LLC. Mr. McClain can be contacted at mclain@hhmrlaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Alert: AAA Construction Industry Rules Update
June 07, 2021 —
Christopher G. Hill - Construction Law MusingsThe American Arbitration Association has made some needed updates to their Construction Industry Arbitration and Mediation Rules, effective July 1, 2015. Among the changes listed at their website are:
- A mediation step for all cases with claims of $100,000 or more (subject to the ability of any party to opt out).
- Consolidation and joinder time frames and filing requirements to streamline these increasingly involved issues in construction arbitrations.
- New preliminary hearing rules to provide more structure and organization to get the arbitration process on the right track from the beginning.
- Information exchange measures to give arbitrators a greater degree of control to limit the exchange of information, including electronic documents.
- Availability of emergency measures of protection in contracts that have been entered into on or after July 1, 2015.
- Enforcement power of the arbitrator to issue orders to parties that refuse to comply with the Rules or the arbitrator’s orders.
- Permissibility of dispositive motions to dispose of all or part of a claim or to narrow the issue in a claim.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
The Partial Building Collapse of the 12-Story Florida Condo
June 28, 2021 —
Beverley BevenFlorez – CDJ StaffOn Thursday, the Champlain Towers South Condo building in Surfside, Florida suffered a partial collapse. As of Monday morning, the official death toll stood at 10 with 151 persons unaccounted for, according to the Miami Herald.
NPR uncovered minutes from a November 15th, 2018 Chaplain Tower South Condominium Association board meeting where the inspector made assurances that “the building was ‘in very good shape.’” However, “an
engineering report from five weeks earlier” alleged “that failed waterproofing in a concrete structural slab needed to be replaced ‘in the near future.’” Daniella Levine Cava, the Miami-Dade County mayor, told reporters that “officials ‘knew nothing’ about the report.”
The New York Times on Sunday reported that experts looking at video footage of the incident believe that the cause is centered on a location “in the lowest part of the condominium complex — possibly in or below the underground parking garage — where an initial failure could have set off a structural avalanche.” The cause of the incident remains unclear, however. This “progressive collapse” could have been caused by a number of different factors “including design flaws or the less robust construction allowed under the building codes of four decades ago.”
A witness, according to the New York Times, saw a hole appear near the pool: “Michael Stratton said his wife, Cassie Stratton, who is missing, was on the phone with him and was looking out through the window of her fourth-floor unit when, she told him, the hole appeared. After that, the call cut off.”
Possible reasons for the “initial failure at the bottom of the building could include a problem with the deep, reinforced concrete pilings on which the building sits — perhaps set off by an unknown void or a sinkhole below — which then compromised the lower columns. Or the steel reinforcing the columns in the parking garage or first few floors could have been so corroded that they somehow gave way on their own. Or the building itself could have been poorly designed, built with substandard concrete or steel — or simply with insufficient steel at critical points.”
"It will take many months to complete the analysis necessary to understand the cause or causes of the collapse,” Eric Ruzicka, a partner at the international law firm Dorsey & Whitney and a commercial litigator who specializes in the area of construction and real estate litigation, stated in a media release. “Often, information that comes out early can be very misleading or misunderstood unless the full context of the information is known.”
Ruzicka explained that Florida’s statues of limitations and repose may be relevant. “These statutes will likely eliminate the liability of those involved in the original development, design and construction of the building. Rather, victims and their families' recovery will be limited to those involved in the building's maintenance and those assessing the condition of the building over the past four years.”
Miami and Sunny Isles Beach have announced they will audit older structures in their communities “ahead of the mandatory 40-year recertification,” the Miami Herald reported.
Read the full story (Miami Herald)...
Read the full story (NPR)...
Read the full story (NY Times)...
Read the court decisionRead the full story...Reprinted courtesy of
Washington Supreme Court Upholds King County Ordinance Requiring Utility Providers to Pay for Access to County’s Right-of-Way and Signals Approval for Other Counties to Follow Suit
March 02, 2020 —
Kristina Southwell - Ahlers Cressman & Sleight PLLCOn December 5, 2019, the Washington State Supreme Court released its opinion in King County v. King County Water Districts, et al.,[1] upholding King County’s Ordinance 18403, which requires utility companies who are franchise grantees to pay “franchise compensation” for their use of the County rights-of-way. Generally, utility companies must apply for and obtain from the County a franchise permitting it to do necessary work in the County rights-of-way. [2] Previously, King County only charged an administrative fee associated with issuing such a franchise. But with the new franchise compensation charges, King County estimates that it will raise approximately $10 million dollars per year for its general fund.
Ordinance 18403 passed in November 2016 and was the first of its kind in the state. The ordinance created a rule, set forth in RCW 6.27.080, requiring electric, gas, water, and sewer utilities who are granted a franchise by King County to pay “franchise compensation” in exchange for the right to use the County’s rights-of-way. The rule provides that franchise compensation is in the nature of an annual rent payment to the County for using the County roads. King County decides an initial estimate of the charge by considering various factors such as the value of the land used, the size of the area that will be used, and the density of the households served. But utility companies can negotiate with the County over the final amount of franchise compensation.
Read the court decisionRead the full story...Reprinted courtesy of
Kristina Southwell, Ahlers Cressman & Sleight PLLCMs. Southwell may be contacted at
kristina.southwell@acslawyers.com
2022 Project of the Year: Linking Los Angeles
May 01, 2023 —
Aileen Cho - Engineering News-RecordThe 2023 Oscar awards featured a Best Actor and Best Supporting Actor who reinvented themselves and came back for a second act. The tunnel-boring machine Angeli is the LA performer who did much the same, but entirely underground.
Reprinted courtesy of
Aileen Cho, Engineering News-Record
Ms. Cho may be contacted at choa@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Toddler Crashes through Window, Falls to his Death
January 24, 2014 —
Beverley BevenFlorez-CDJ STAFFTwo-year old Alijah Glenn fell 17 stories to his death after crashing through “a floor-to-ceiling window” at the Crystal Tower apartments in East Cleveland, Ohio, on January 13th, according to The Plain Dealer. Solandra Wallace, East Cleveland’s building and housing manager, told The Plain Dealer that “the city inspects the building whenever a complaint is filed and does not have regular inspections.” The apartment complex “was built in 1966 and would have to adhere to that era's building code standards,” according to the article.
The Plain Dealer reports that three complaints have been filed at the Crystal Tower since 2010. A resident complained in 2012 that “her apartment was falling apart, causing water damage and emitting a foul odor,” however, by the time an inspector arrived the ceiling was being fixed. In 2011, an “unspecified roof leak” turned out to be “condensation from a hot pipe.” An elevator was reported inoperable in 2010, however the claim was deemed “invalid” since the elevator worked when inspectors arrived.
The Cuyahoga County Medical Examiner ruled Glenn’s death accidental.
Read the court decisionRead the full story...Reprinted courtesy of
Everybody Is Going to End Up Paying for Texas' Climate Crisis
March 29, 2021 —
David R Baker & Mark Chediak - BloombergFallout from last month’s deadly deep freeze in Texas has quietly spread to people living hundreds of miles away. Minnesota utilities have warned that monthly heating bills could spike by $400, after the crisis jacked up natural gas prices across the country. Xcel Energy’s Colorado customers could face a $7.50 per month surcharge for the next two years.
This is a subtle demonstration of the way Americans already share the collective financial burden of climate change, even if we don’t realize it. The national bill for global warming is here, and it’s rising.
Perhaps it’s easier to see this dynamic playing out beyond February’s Texas cold snap. That disaster left dozens dead, stranded millions in dark homes, and sent a shockwave of higher gas prices across the nation. But since there remains scientific uncertainty over the role of global warming, let’s examine two other calamities for which the climate link is clearer: wildfires and tropical storms.
Read the court decisionRead the full story...Reprinted courtesy of
David R Baker & Mark Chediak, Bloomberg
Untangling Unique Legal Issues in Modern Modular Construction
September 09, 2024 —
Chad Theriot & Brad Sands - Construction ExecutiveModular construction has grown significantly over the last few years and shows no signs of slowing down. This construction method is a departure from traditional approaches where all construction activity occurs onsite. Modular construction involves building standardized project components—usually in an offsite, controlled environment—which are then transported and assembled at the project site. Offsite construction generally allows for better quality control and economic efficiency, as it can utilize an assembly-line process. Modular fabrication can also centralize skilled labor in regions with lower labor costs.
Establishing each party's expectations upfront is always important, but even more so in modular construction since much of the construction activity is performed away from the ultimate project site. This requires extensive coordination among designers, fabricators, installers and owners to ensure construction, testing and quality progresses accordingly. Every field change and design clash could have an exponential impact on the modular fabrication efficiencies given the assembly-line approach and remote nature of modular work.
Reprinted courtesy of
Chad Theriot & Brad Sands, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.