Should I Pull the Pin? Contractor and Subcontractor Termination for Cause
January 26, 2017 —
Patrick McNamara - Porter Law GroupAny owner or general contractor who has a few projects under his or her belt has likely had this thought: “My contractor (or subcontractor) is not performing the way I expected; should I replace him?” The other side of the termination coin is: “This project is not going the way I expected; should I get out?”
While there may be an emotional high that immediately comes from terminating a contractor or subcontractor (or leaving a project, in mid-stream), there are many factors to be weighed, before making that decision.
Project Delay. Replacing a contractor or subcontractor that has already begun performance always results in delays to the project. Assessing the work in place, interviewing replacement contractors, and negotiating the terms of the new relationship can easily consume weeks, if not months of project time.
Read the court decisionRead the full story...Reprinted courtesy of
Patrick McNamara, Porter Law GroupMr. McNamara may be contacted at
pmcnamara@porterlaw.com
When Are General Conditions and General Requirements Covered by Builder's Risk
December 18, 2022 —
Michael V. Pepe & Grace V. Hebbel - Saxe Doernberger & VitaGeneral conditions and general requirements are terms of art in the construction industry that describe the indirect costs necessary to complete a construction project. After physical loss or damage to a project, the following question often arises: Are “general conditions” and “general requirements” covered under a builder’s risk policy?
General Conditions vs. General Requirements
General conditions are usually described as the cost of managing a construction project. Examples include salaries for personnel like project managers, supervisors, engineers, field office staff, as well as the cost of field trailers, office equipment and supplies, and anything necessary to support the staff.
General requirements are the non-management indirect costs of executing the project, including items such as pre-development costs, permits, security, dumpsters, fences, temporary lighting, worker amenities, and clean-up costs.
Reprinted courtesy of
Michael V. Pepe, Saxe Doernberger & Vita and
Grace V. Hebbel, Saxe Doernberger & Vita
Mr. Pepe may be contacted at MPepe@sdvlaw.com
Ms. Hebbel may be contacted at GHebbel@sdvlaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Revel Closing Shows Gambling Is No Sure Thing for Renewal
September 03, 2014 —
Christopher Palmeri – BloombergThe Revel Casino Hotel was envisioned as a playground for Wall Streeters who hated flying to Las Vegas. Instead, it’s become a money pit for the banks and money managers who spearheaded the New Jersey project, and the losses will keep coming even after closing today.
The Atlantic City resort, built at a cost of $2.4 billion, ceased operations after two bankruptcies and a 10-month search for a buyer. Barring a sale, the new owners may be Wells Fargo & Co. and JPMorgan Chase & Co., which provided $125 million in court-approved funding. Previous backers also included Capital Group Cos., the third-largest manager of U.S. mutual funds, and Morgan Stanley, the original investor.
The resort fell prey to poor timing, bad design and a misreading of the local market. The Revel saga shows what can go wrong when bankers stray from what they know, according to Charles Geisst, a professor of finance at Manhattan College in New York and author of the book “Wall Street: A History.”
Read the court decisionRead the full story...Reprinted courtesy of
Christopher Palmeri, BloombergMr. Palmeri may be contacted at
cpalmeri1@bloomberg.net
Following California Law, Federal Court Adopts Horizontal Allocation For Asbestos Coverage
May 19, 2014 —
Tred R. Eyerly – Insurance Law HawaiiFollowing California law, the federal district court adopted horizontal allocation to settle a dispute among carriers for an insured sued for selling asbestos products. New England Fire Ins. Corp. v. Ferguson Enterprises, Inc., Civil No. 3:12cv948 (D. Conn. April 8, 2014) [ruling here]
The insured was a California-based corporation that sold plumbing supply products that contained asbestos. The insured was named in numerous asbestos-related lawsuits that were filed largely in California.
The insured had primary and excess coverage for bodily injury claims. New England Fire Insurance issued an excess policy to the insured. The policy provided the insurer would be liable for the ultimate new loss in excess of the insureds underlying limit, which was defined as the amount equal to the limits of the underlying insurance, plus the applicable limits of any other underlying insurance collectible by the insured.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
California Supreme Court Holds “Notice-Prejudice” Rule is “Fundamental Public Policy” of California, May Override Choice of Law Provisions in Policies
November 12, 2019 —
Anthony L. Miscioscia & Timothy A. Carroll - White and Williams LLPOn August 29, 2019, in Pitzer College v. Indian Harbor Insurance Company, 2019 Cal. LEXIS 6240, the California Supreme Court held that, in the insurance context, the common law “notice-prejudice” rule is a “fundamental public policy” of the State of California for purposes of choice of law analysis. Thus, even though the policy in Pitzer had a choice of law provision requiring application of New York law – which does not require an insurer to prove prejudice for late notice of claims under policies delivered outside of New York – that provision can be overridden by California’s public policy of requiring insurers to prove prejudice after late notice of a claim. The Supreme Court in Pitzer also held that the notice-prejudice rule “generally applies to consent provisions in the context of first party liability policy coverage,” but not to consent provisions in the third-party liability policy context.
The Pitzer case arose from a discovery of polluted soil at Pitzer College during a dormitory construction project. Facing pressure to finish the project by the start of the next school term, Pitzer officials took steps to remediate the polluted soil at a cost of $2 million. When Pitzer notified its insurer of the remediation, and made a claim for the attendant costs, the insurer “denied coverage based on Pitzer’s failure to give notice as soon as practicable and its failure to obtain [the insurer’s] consent before commencing the remediation process.” The Supreme Court observed that Pitzer did not inform its insurer of the remediation until “three months after it completed remediation and six months after it discovered the darkened soils.” In response to the denial of coverage, Pitzer sued the insurer in California state court, the insurer removed the action to federal court and the insurer moved for summary judgment “claiming that it had no obligation to indemnify Pitzer for remediation costs because Pitzer had violated the Policy’s notice and consent provisions.”
Reprinted courtesy of
Timothy Carroll, White and Williams and
Anthony Miscioscia, White and Williams
Mr. Carroll may be contacted at carrollt@whiteandwilliams.com
Mr. Miscioscia may be contacted at misciosciaa@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of
New Jersey Federal Court Examines And Applies The “j.(5)” Ongoing Operations Exclusion
October 07, 2019 —
Anthony L. Miscioscia and Timothy A. Carroll - White and Williams LLPIn PJR Construction of N.J. v. Valley Forge Insurance Company, 2019 U.S. Dist. LEXIS 127973 (D.N.J. July 31, 2019) (PJR Construction), a New Jersey federal court held that the “j.(5)” “Ongoing Operations Exclusion” applied to bar coverage for property damage to property on which a construction company allegedly performed faulty work. The court’s opinion follows prior New Jersey state court precedent, including Ohio Casualty Insurance Company v. Island Pool & Spa, Inc., 12 A.3d 719 (N.J. Super. Ct. App. Div. 2011) (Island Pool), but also provides additional guidance on the elements which can make the Ongoing Operations Exclusion applicable to exclude coverage.
In PJR Construction, a commercial property owner engaged a construction company to build a 26,000 square foot swim club and related 3,000 square foot pavilion building in New Jersey. After about 75% of the work was completed, the property owner fired the construction company and denied it access to the property. The owner later sued the construction company in New Jersey state court alleging “shoddy workmanship” in, among other things, sealants, flashing, water resistant barriers, masonry and the handicap ramps. The construction company sought coverage from its CGL insurer, which denied coverage based on, among other things, the j.(5) Ongoing Operations Exclusion. After the denial of coverage, the company sued the insurer in New Jersey federal court seeking a declaration of coverage.
Reprinted courtesy of
Anthony L. Miscioscia, White and Williams LLP and
Timothy A. Carroll, White and Williams LLP
Mr. Miscioscia may be contacted at misciosciaa@whiteandwilliams.com
Mr. Carroll may be contacted at carrollt@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of
What Counts as Adequate Opportunity to Cure?
June 13, 2022 —
Christopher G. Hill - Construction Law Musingsqimono @ PixabayHere at Musings, we like to discuss (likely more than readers would like) the fact that in Virginia, the contract is king and its terms will be looked at carefully by the courts. One of those provisions that will be looked at carefully is the so-called “cure period.” The “cure period” is the time that a subcontractor has to fix any non-compliant construction after receiving notice of any deviation from the contract documents that must be fixed.
In United States ex rel Allan Myers VA, Inc. v. Ocean Construction Services, Inc. the federal court for the Eastern District of Virginia examined what it means to grant a proper opportunity to cure. The Ocean Construction Services case arises from a contractual dispute between Allan Myers VA Inc. and Ocean Construction Services Inc., or OCS, involving renovation work performed in sections of Arlington National Cemetery. Presently before the court is Myers’ motion for partial summary judgment, arguing that the undisputed facts demonstrate that it was not provided with a three-day cure period, a contractual prerequisite to OCS terminating the subcontract for default.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
You Are Your Brother’s Keeper. Direct Contractors in California Now Responsible for Wage Obligations of Subcontractors
January 31, 2018 —
Garret Murai – California Construction Law BlogIf there’s one law from the 2017 Legislative Session that’s garnered a lot of attention in the construction press, it’s
AB 1701. Under AB 1701, beginning January 1, 2018, for contracts entered into on or after January 1, 2018, direct contractors may be found liable for unpaid wages, fringe or other benefit payments or contributions, including interest, but excluding penalties or liquidated damages, owed by a subcontractor of any tier to their workers. Here’s what you need to know about AB 1701.
What code section did AB 1701 amend?
AB 1701 added a a new section 218.7 to the Labor Code.
To whom does AB 1701 apply?
AB 1701 applies to direct contractors only. A direct contractor is defined as a “contractor that has a direct contractual relationship with an owner.”
On what types of projects does AB 1701 apply?
AB 1701 applies to private works projects only.
When does AB 1701 take effect?
AB 1701 took effect on January 1, 2018 and applies to all contracts entered into on or after January 1, 2018.
Read the court decisionRead the full story...Reprinted courtesy of
Garret, Murai, Wendel, Rosen, Black, Dean, LLPMr. Murai may be contacted at
gmurai@wendel.com