Waiver of Subrogation Enforced, Denying Insurers Recovery Against Additional Insured in $500 Million Off-Shore Oil Rig Loss
September 30, 2019 —
Sergio F. Oehninger & Daniel Hentschel - Hunton Insurance Recovery BlogThe United States District Court for the Southern District of Texas recently rejected a claim by a group of insurance companies (“Underwriters”) against American Global Maritime Inc. for more than $500 million that the Underwriters paid the named insured under an Off-Shore Construction Risk insurance policy for losses resulting from the an alleged off-shore oil rig failure.
The action arose out of alleged construction defects related to Chevron’s “Big Foot” oil-drilling platform in the Gulf of Mexico. Chevron hired American Global to be the marine warranty surveyor responsible for reviewing and certifying the project’s specifications and materials. American Global issued the certificate of approval required for the project to proceed; however, during the attempted installation of the platform in 2015, it was alleged that parts from the structure fell to the sea floor. The Underwriters paid more than $500 million in connection with the incident under an Off-Shore Construction insurance policy they had issued to Chevron.
After paying the claim, the Underwriters filed a negligence action against American Global and other contractors involved in the project.
Reprinted courtesy of
Sergio F. Oehninger, Hunton Andrews & Kurth and
Daniel Hentschel , Hunton Andrews & Kurth
Mr. Oehninger may be contacted at soehninger@HuntonAK.com
Mr. Hentschel may be contacted at dhentschel@HuntonAK.com
Read the court decisionRead the full story...Reprinted courtesy of
When Customers Don’t Pay: What Can a Construction Business Do
June 06, 2022 —
Patrick Hogan – Handle.comLate payments are not unusual in construction. From general contractors to subs and material suppliers, every construction project participant has dealt with delayed payments as part of business. However, there’s the issue of clients who refuse to pay. Not late--just no payment. For businesses big and small, a client who refuses to pay can make a significant impact financially and operationally. Many construction transactions are made on trust, and when a client doesn’t pay, some contractors and suppliers may make poor decisions. Yet, to get out of a project going sideways--with payment in hand or lessons learned--you need to be smart and proceed with your business interest in mind.
Why is the customer not paying?
This is where it begins. You must first identify the reasons why a customer refuses to pay. Were they unsatisfied with the quality of work? Do they feel that what was delivered was not aligned with what’s contractually obligated? Do they feel like the work was rushed or the materials used inferior? Was the job finished later than agreed? All these are possibilities that need to be investigated.
If the customer has not volunteered any of this information, it’s best to personally visit the project or set a meeting with the customer to discuss issues in person. If the problems the customer has raised are valid, plan how to resolve them right away. Suppose, after the discussion, you’ve determined that the customer demands things beyond what’s contractually obligated, and you cannot resolve them without incurring unreasonable time and costs. In that case, you might have a delinquent customer in your hands.
Let the customer know your decision. If you’ve decided to proceed and fix the issues they’ve raised, send the invoice for the unpaid work immediately upon commencing the remedial work. Of course, there is no guarantee that addressing their concerns will result in swift payment, so exercise your best judgment. If you think you’ve exhausted all the cordial means to get them to pay as the contract requires, you might need to consider your legal options.
A legal option to recover payments: Filing a mechanics lien
State laws protect construction providers like contractors and material suppliers from non-payment through lien laws. Mechanics liens work by placing a hold on the property where the work or materials were provided as a security in case of non-payment. Mechanics liens can result in a sale of the property where the lien is attached, and the proceeds will be used to pay unpaid vendors.
When a client fails to pay after a good-faith pursuit to resolve the payment issue, filing a mechanics lien becomes the smartest next move. However, note that to file a mechanics lien, you must have fulfilled the requirements of lien laws specific to the state where the project is located. For many states, the main requirement is sending a preliminary or pre-lien notice to secure your right to file liens. It’s only good business practice to
file preliminary notices for every project you work on. It’s not an indication of distrust in the client’s ability to pay–and that is mentioned in the wording of many statutory statements included in preliminary notices. It’s just industry standard to file prelim notices.
Filing a mechanics lien includes a period where the client still has the opportunity to pay arrears before the lien is enforced. Suppose the client fails to pay in this period. You are now allowed to enforce the mechanics lien through a lawsuit. This is a complex process, but it presents itself as the last resort to recover payments. As long as all your documents are in check, you’ve filed the necessary notices in the time and manner required by law, and you’ve fulfilled your contractual obligations to the client, a ruling in your favor is the likely outcome.
Promoting timely payments
It’s in your best interest to promote timely payments from your customers. While construction contracts are primarily reliant on trust, there are many things you can do to encourage and facilitate timely payments from your clients. Here are some ideas:
- Use detailed contracts and progress billing
- Vet clients through background research, credit history, references, and public financial records
- Send regular on-time invoices
- Ensure your invoices are aligned with the formats used by your client’s payables department
- Provide multiple payment methods
- File the necessary preliminary notices throughout the project
In the case of construction payments, the adage prevention is better than cure applies. There are many reasons why payments get delayed or skipped, some malicious, some not. It’s in your best interest to ensure that you are doing everything from your end to promote timely payments and that you’re fully protected by rights granted to construction businesses by law.
About the Author:
Patrick Hogan is the CEO of
Handle.com, where they build software that helps contractors and material suppliers with lien management and payment compliance. The biggest names in construction use Handle on a daily basis to save time and money while improving efficiency.
Read the court decisionRead the full story...Reprinted courtesy of
Cable-Free Elevators Will Soar to New Heights, and Move Sideways
January 14, 2015 —
Belinda Lanks – BloombergI live in one of the few buildings in New York that still has a manual elevator. When I ask the operator on the morning shift how he's doing, his well-oiled response is "up and down." For the last 160 years, elevators have travelled a predictably vertical path. That will soon change when the German manufacturer ThyssenKrupp introduces the first fleet of cable-free cars that can also move sideways.
The system, dubbed MULTI, will allow multiple cabs to motor along a single, looping shaft. The cars move by magnetic levitation (the same technology behind some high-speed trains), rather than being pulled by the heavy steel ropes that limit how high skyscrapers can stretch. With MULTI, architects will be able to build spindly towers on small plots formerly deemed untenable for high-rises.
Read the court decisionRead the full story...Reprinted courtesy of
Belinda Lanks, BloombergMs. Lanks may be contacted at
blanks@bloomberg.net
Subcontractors Have Remedies, Even if “Pay-if-Paid” Provisions are Enforced
February 19, 2019 —
John P. Ahlers - Ahlers Cressman & Sleight PLLCIn a recent case in Kentucky[1], a sub-tier subcontractor sued the general contractor and owner for failure to pay for extra work. At the trial, the court held the subcontractor was entitled to recover under the theories of implied contracts and unjust enrichment, even though the subcontract contained a “pay-if-paid” clause. All parties appealed. In particular, the general contractor asserted that the pay-if-paid provision in the subcontract precluded recovery by the subcontractor. The issue was petitioned to the Supreme Court of Kentucky.
The question to be resolved by the Supreme Court of Kentucky was whether a pay-if-paid provision was enforceable as between a general contractor and subcontractor, and if so, whether the subcontractor could nevertheless pursue the owner directly for payment notwithstanding a lack of privity between the owner and subcontractor.
Read the court decisionRead the full story...Reprinted courtesy of
John P. Ahlers, Ahlers Cressman & Sleight PLLCMr. Ahlers may be contacted at
john.ahlers@acslawyers.com
Nerves of Steel Needed as Firms Face Volatile Prices, Broken Contracts and Price-Gouging
December 06, 2021 —
Richard Korman, Jonathan Barnes, & Greg Aragon - Engineering News-RecordWhen Elmhurst Group, a Pittsburgh-area developer, started collecting bids for a new mixed-use building last November, the price of the steel frame, roof and cladding panels for the $14-million project came in $382,000 higher than expected—a big enough disappointment to give Elmhurst pause. Overall material costs for the project were running more than $650,000 above what was originally calculated.
Reprinted courtesy of
Richard Korman, Engineering News-Record,
Jonathan Barnes, Engineering News-Record and
Greg Aragon, Engineering News-Record
Mr. Korman may be contacted at kormanr@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Address 'Your Work' Exposure Within CPrL Policies With Faulty Workmanship Coverage
December 29, 2020 —
Joseph Reynolds - Construction ExecutiveNew faulty workmanship coverage forms have emerged to potentially address the “your work” exposure found in most contractors professional liability (CPrL) policies. Once offered by only a single carrier, several insurers have recently entered the marketplace to cover the cost to repair or replace faulty work or the related material costs associated with the “self-performed work” of general and trade contractors.
Commonly serving as a separate insuring agreement and offered in carrier-specific CPrL policies, faulty workmanship coverage forms are designed to protect contractors from the “your work” claims triggered by project owners and other third parties. This includes the contractor’s workmanship as well as the equipment, parts and materials such as steel beams, epoxy activators and anchor bolts used to perform construction work.
Insureds should be aware that exclusions and strict conditions apply. For instance, faulty workmanship policies typically do not cover resulting bodily injury and property damage and some policies even exclude project delays and other business risks that can arise from the claims of unhappy customers. Another potentially confusing issue is the scope of coverage offered under a ‘faulty work’ endorsement. While some faulty workmanship enhancements are specifically-designed to cover “your work,” claims, others may only cover the products manufactured or fabricated by the insured and not the work they perform or install.
Reprinted courtesy of
Joseph Reynolds, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Mr. Reynolds may be contacted at
joseph.reynolds@rtspecialty.com
Supreme Court of Idaho Rules That Substantial Compliance With the Notice and Opportunity to Repair Act Suffices to Bring Suit
July 31, 2018 —
Lian Skaf - The Subrogation StrategistIn Davison v. Debest Plumbing, Inc., 416 P.3d 943 (Ida. 2018), the Supreme Court of Idaho addressed the issue of whether plaintiffs who provided actual notice of a defective condition, but not written notice as stated in the Notice and Opportunity to Repair Act (NORA), Idaho Code §§ 6-2501 to 6-2504, et. seq., substantially complied with the act and if the plaintiffs’ notice was sufficient to bring suit. Section 6-2503 of the NORA states that, “[p]rior to commencing an action against a construction professional for a construction defect, the claimant shall serve written notice of claim on the construction professional. The notice of claim shall state that the claimant asserts a construction defect claim against the construction professional and shall describe the claim in reasonable detail sufficient to determine the general nature of the defect.” Any action not complying with this requirement should be dismissed without prejudice. The court held that the defendant’s actual notice of the defect was sufficient to satisfy the objectives of the NORA and, thus, the plaintiffs’ action complied with the NORA.
In Davison, Scott and Anne Davison hired general contractor Gould Custom Builders (Gould) to remodel a vacation home in McCall, Idaho. Gould subcontracted out the plumbing work to Debest Plumbing (Debest). This work included installing a bathtub. When the Davisons arrived at their home for the first time on July 25, 2013, they noticed a leak from the subject bathtub. The Davisons contacted Gould and, the next morning, Gil Gould arrived with a Debest employee to inspect the home. In addition to inspecting the home, the Debest employee repaired the leak and helped Gould remove some water-damaged material.
Read the court decisionRead the full story...Reprinted courtesy of
Lian Skaf, White and Williams, LLPMr. Skaf may be contacted at
skafl@whiteandwilliams.com
Water Damage: Construction’s Often Unnoticed Threat
November 02, 2020 —
Yaron Dycian - Construction ExecutiveFire damage to commercial buildings might get headlines, but water damage, whether to projects under construction or completed buildings, delivers massive financial blows to owners, developers and contractors. The impact is massive, reaching many billions of dollars per year. One water leak on the 19th floor at a construction site of a high-end apartment building in New York City resulted in $30 million in property damage and millions in delayed delivery penalties.
Imagine this all-too-typical scenario: A 20-story building has thousands of pipe connections and many tens of thousands throughout the entire building. It only takes one of those joints failing, perhaps due to human oversight. Early on a Saturday morning when no one is onsite, one of the connections inside a wall begins to leak, slowly at first. In a couple hours the connection fails completely, sending a cascade of water into the building. The site is located next to a highway, so the security guards don’t hear the water flowing.
The leak goes undetected until crews come back onsite on Monday morning. By that point, lower levels of the building have been inundated with thousands of gallons of water that has destroyed construction material, carpeting and electrical switchgear. It’s flowed into the elevator pits and mechanical room.
Reprinted courtesy of
Yaron Dycian, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Mr. Dycian may be contacted at
yaron@wint.ai