Design-Assist, an Ambiguous Term Causing Conflict in the Construction Industry[1]
December 02, 2019 —
John P. Ahlers - Ahlers Cressman & Sleight PLLC“Design-Assist” is one of the recent cost-saving trends being touted for construction projects and, in particular, construction projects utilizing alternative procurement methods. If an internet search for the term, “design-assist” is made, the result will be numerous construction industry articles and white papers lauding “design-assist” as a recent cost-saving trend in construction procurement. From a legal perspective, however, the term “design-assist” is notably absent from court opinions and most state licensing laws. With the exception of the ConsensusDocs, few standard form contracts even include the term “design-assist” in their text.
The ConsensusDocs agreement provides examples of the Constructor’s obligations to perform “assisting activities” (the term “design-assist” is not used) and states that, notwithstanding the performance of such “assisting activities” by the Constructor, the responsibility of the design remains with the Designer unless otherwise stated in the Contract:
- Article 4.5 DESIGN PROFESSIONAL’S RESPONSIBIITIES The Designer shall furnish or provide all design and engineering services necessary to design the Project in accordance with the Owner’s objectives … the Designer shall draw upon the assistance of Constructor and others in developing the design, but the Designer shall retain overall responsibility for all design decisions….
- Article 4.6 CONSTRUCTOR’S RESPONSIBILITIES [T]he Constructor shall assist the Designer in the development of the Project Plan and Project Design but shall not provide professional services which constitute the practice of architecture or engineering unless the Constructor needs to provide such services in order to carry out its responsibilities … or unless specifically called for by the Contract Documents.
Read the court decisionRead the full story...Reprinted courtesy of
John P. Ahlers, Ahlers Cressman & Sleight PLLCMr. Ahlers may be contacted at
john.ahlers@acslawyers.com
Bidders Shortlisted as Oroville Dam Work Schedule is Set
April 13, 2017 —
JT Long - Engineering News-RecordIn a race to fix the damaged Oroville Dam’s main spillway by November, the California Dept. of Water Resources, the operator of the country’s tallest dam, is going to bid with a 65%-complete design that breaks recovery efforts into three parts, with an ultimate goal of doubling the main spillway’s release capacity to 270,000 cu ft per second.
Read the court decisionRead the full story...Reprinted courtesy of
JT Long, ENRENR may be contacted at
ENR.com@bnpmedia.com
Blackstone Said to Sell Boston Buildings for $2.1 Billion
May 21, 2014 —
Hui-yong Yu – BloombergBlackstone Group LP (BX) agreed to sell five office properties in Boston to a venture led by Toronto-based Oxford Properties Group for about $2.1 billion, according to two people with knowledge of the transaction.
The buildings total almost 3.3 million square feet (306,000 square meters) and are mostly in downtown Boston, said the people, who asked not to be named because the sale is private. The sale is Blackstone’s largest of U.S. office properties since the real estate market crash.
Oxford plans to purchase 100 High St. and 125 Summer St., and team with JPMorgan Chase & Co. (JPM)’s asset-management unit to buy three other properties: 60 State St., 225 Franklin St. and One Memorial Drive in nearby Cambridge, the people said. Blackstone also is selling its roughly half-stake in Boston’s Rowes Wharf to part-owner Morgan Stanley (MS) for about $200 million, according to one of the people.
Read the court decisionRead the full story...Reprinted courtesy of
Hui-yong Yu, BloombergHui-yong Yu may be contacted at
hyu@bloomberg.net
Homebuilder Confidence Takes a Beating
October 21, 2013 —
CDJ STAFFHomebuilder confidence dropped to fifty-five percent in October, the lowest percentage seen in the last four months. The score had been rising on the strength of renewed home sales. The current slump is attributed to increases in interest rates, which have made home purchases more expensive for prospective buyers, and the uncertainty of the budget struggle in Washington.
John Stumpf, the chairman and CEO of Wells Fargo said that “home price appreciation remains strong and affordability remains excellent.” Mr. Strum has “guarded optimism” over the effects of the budget struggle.
Read the court decisionRead the full story...Reprinted courtesy of
Death, Taxes and Attorneys’ Fees in Construction Disputes
July 18, 2022 —
Garret Murai - California Construction Law BlogAccording to Benjamin Franklin there are two certainties in this world:
Death and taxes. Let me humbly add a third if you’re ever involved in non-contingency civil litigation: Attorneys’ fees.
As such, when it comes to legal disputes, sophisticated parties know that it’s not just about winning but the cost of winning. While winning is never certain – remember Poor Richard’s proverb above – what is certain is that it will most likely cost you to find out whether you’ve won or lost. That’s why the ability to recover (or at least threaten the recovery of attorneys’ fees – that’s a separate discussion altogether) in litigation and arbitration is so important.
A few facts:
- According to the National Center for State Courts (NCSC) in their 2013 report, Measuring the Cost of Civil Litigation: Findings From a Survey of Trial Lawyers, the median cost of litigation (i.e., attorneys’ fees) for contract disputes, of which most construction disputes would fall under, was $90,575 from case initiation through post-trial disposition.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
Lessons from the Sept. 19 Mexico Earthquake
October 19, 2017 —
Nadine M. Post - Engineering News-RecordOn the 32nd anniversary of the magnitude-8.1 earthquake that devastated Mexico City on Sept. 19, 1985, 41 U.S. seismic experts were in a workshop near Los Angeles, polishing a new tool to identify “killer” buildings: non-ductile concrete structures that often perform poorly in quakes. Suddenly, the attendees started getting pager alerts from the U.S. Geological Survey: A magnitude-7.1 quake had struck about 120 kilometers from Mexico City.
Read the court decisionRead the full story...Reprinted courtesy of
Nadine M. Post, ENRMs. Post may be contacted at
postn@enr.com
Judge Gives Cintra Bid Protest of $9B Md. P3 Project Award New Life
March 21, 2022 —
Jim Parsons - Engineering News-RecordThe Maryland Dept. of Transportation will have to reconsider a protest lodged by the losing bidder for the initial phase of its $9-billion Express Lanes project, according to a Feb. 17 state circuit court judge's ruing. The decision likely stalls the state's ambitious plan to add capacity along portions of the I-495/Beltway and I-270 west of Washington, DC, using a progressive public-partnership.
Reprinted courtesy of
Jim Parsons, Engineering News-Record
ENR may be contacted at enr@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Wait! Don’t Sign Yet: Reviewing Contract Protections During the COVID Pandemic
April 13, 2020 —
Danielle S. Ward - Balestreri Potocki & HolmesAs the circumstances of the COVID pandemic change day by day, and we all rush to keep business moving where and when we can, companies should consider hitting the “pause button” before renewing or executing any new contracts. Developing contracts often takes considerable time and expense, and companies are not in the habit of reworking them often. A change in law may prompt a company to revisit their contract terms, but otherwise business is often carried out with a standard form contract for a period of years. With the COVID pandemic affecting nearly every business and industry, life is not business as usual, and companies should make sure their contracts consider what previously seemed like an unforeseeable event.
Force Majeure clauses are included in many contracts to excuse contract performance when made impossible by some unforeseen circumstance. These clauses typically fall under two categories: general and specific. General force majeure clauses excuse performance if performance is prevented by circumstances outside the parties’ control. By contrast, specific force majeure clauses detail the exhaustive list of circumstances (acts of god, extreme weather, war, riot, terrorism, embargoes) which would excuse contract performance. Force majeure clauses are typically interpreted narrowly. If your contract has a specific clause and pandemic or virus is not one of the listed circumstances it may not apply. Whether a particular existing contract covers the ongoing COVID pandemic will vary depending on the language of the contract.
Force majeure clauses previously made headlines when the great economic recession hit in 2008. A number of courts held that simple economic hardship was not enough to invoke force majeure. The inability to pay or lack of desire to pay for the contracted goods or services did not qualify as force majeure. In California, impossibility turns on the nature of the contractual performance, and not in the inability of the obligor to do it. (Kennedy v. Reece (1964) 225 Cal. App. 2d 717, 725.) In other words, the task is objectively impossible not merely impossible or more burdensome to the specific contracting party.
California has codified “force majeure” protection where the parties haven’t included any language or the circumstances in the clause don’t apply to the situation at hand. Civil Code section 1511 excuses performance when “prevented or delayed by an irresistible, superhuman cause, or by the act of public enemies of this state or of the United States, unless the parties have expressly agreed to the contrary.” (Civ. Code § 1511.) What qualifies as a “superhuman cause”? In California, the test is whether under the particular circumstances there was such an insuperable interference occurring without the party's intervention as could not have been prevented by the exercise of prudence, diligence and care. (Pacific Vegetable Oil Corp. v. C. S. T., Ltd. (1946) 29 Cal.2d 228, 238.)
If you find yourself in an existing contract without a force majeure clause, or the statute does not apply, you may consider the doctrine of frustration of purpose. This doctrine is applied narrowly where performance remains possible, but the fundamental reason the parties entered into the contract has been severely or substantially frustrated by an unanticipated supervening circumstance, thus destroying substantially the value of the contract. (Cutter Laboratories, Inc. v. Twining (1963) 221 Cal. App. 2d 302, 314-15.) In other words, performance is still possible but valueless. Note this defense is not likely to apply where the contract has simply become less profitable for one party.
Now that COVID is no longer an unforeseeable event, but rather a current and grave reality, a party executing a contract today without adequate protections may have a difficult time proving unforeseeability. Scientists are not sure whether warm weather will suppress the spread of the virus, as it does with the seasonal flu, but to the extent we get a reprieve during the summer we may see a resurgence of cases this Fall or Winter. Companies should take care in reviewing force majeure clauses, and other clauses tied to timely performance such as delay and liquidated damages before renewing or executing new contracts.
Your contract scenario may vary from the summary provided above. Please contact legal counsel before making any decisions. During this critical time, BPH’s attorneys can be reached via email to answer your questions.