Ninth Circuit Rules Supreme Court’s Two-Part Test of Implied Certification under the False Claims Act Mandatory
May 13, 2019 —
Meredith Thielbahr - Gordon & Rees Construction Law BlogFor those contractors in the government arena, read on.
The False Claims Act (“FCA”) was enacted to deter knowingly fraudulent actions by contractors which resulted in a loss of property to the Government. Intent to defraud with resulting financial hardship was required. Contrary to popular misconception, the statute was not designed to punish all false submissions to the Government simply because those submissions, or claims, are later found to be false. The statute’s inclusion of the requisite element of knowledge is consistent with this notion:
- A defendant must submit a claim for payment to the Government;
- the claim must be false or fraudulent;
- the defendant must have known the claim was fraudulent when it was submitted (also known as scienter); and
- the claim must have caused the Government to pay out money.
See 31 U.S.C. § 3729(a).
Despite these explicit elements (in addition to common law elements of fraud), over the last two decades, contractors have seen ever-expanding theories of FCA recovery presented by qui tam plaintiffs and the Government. For example, under the FCA, the false “claim” evolved over time: the claim no longer needs to be an express false claim (i.e. the truthfulness of the claim is a direct condition of payment); the claim can be “implied” misrepresentation or “half-truth”.
Read the court decisionRead the full story...Reprinted courtesy of
Meredith Thielbahr, Gordon & Rees Scully MansukhaniMs. Thielbahr may be contacted at
mthielbahr@grsm.com
The “Your Work” Exclusion—Is there a Trend against Coverage?
September 10, 2014 —
Craig Martin – Construction Contractor AdvisorTwo more courts have weighed in on the “your work” exclusion in commercial general liability (CGL) policies, finding that contractors did not have coverage for work performed improperly. These cases highlight that whether you have coverage for poor workmanship will depend on the state’s law applied. It now appears that if you are in South Carolina or Massachusetts, you will not have coverage.
The South Carolina case, Precision Walls, Inc. v. Liberty Mutual Fire Insurance Company, involved a subcontractor hired to tape insulation. After taping the insulation, a brick veneer was installed on the exterior. During the brick installation, the mason reported that the tape was losing its adhesion and the subcontractor was instructed to repair the problem. In order to access the tape, portions of the brick veneer had to be removed and re-installed. The subcontractor then sought coverage for the costs associated with repairing the tape.
The insurer denied coverage and the subcontractor sued its insurer. The court ruled in favor of the insurer, finding that the defective tape was “your work” because it was “material furnished in connection” with the subcontractor’s work. The policy specifically excluded from coverage damage to property caused by “your work”. Thus, there was no coverage for the subcontractor.
Read the court decisionRead the full story...Reprinted courtesy of
Craig Martin, Lamson, Dugan and Murray, LLPMr. Martin may be contacted at
cmartin@ldmlaw.com
Real Estate & Construction News Roundup (12/4/24) – Highest Rate of Office Conversions, Lending Caps for Fannie Mae and Freddie Mac and Affordability Challenges for Homebuyers
December 23, 2024 —
Pillsbury's Construction & Real Estate Law Team - Gravel2Gavel Construction & Real Estate Law BlogIn our latest roundup, infrastructure-related ballot initiatives, U.S. Green Building Council’s success stories, support for sustainable building, and more!
- 2024 is expected to see the highest rate of office conversions since CBRE began tracking them in 2016. (Nish Amarnath, SmartCities Dive)
- The Federal Housing Finance Agency has established lending caps of $73 billion each for Fannie Mae and Freddie Mac, allowing them to purchase a total of up to $146 billion in multifamily loans in 2025. (Leslie Shaver, Multifamily Dive)
- A number of infrastructure-related initiatives with the potential to impact facilities managers were on the ballot during the 2024 U.S. presidential election. (Joe Burns, Construction Dive)
Read the court decisionRead the full story...Reprinted courtesy of
Pillsbury's Construction & Real Estate Law Team
Rulemaking to Modernize, Expand DOI’s “Type A” Natural Resource Damage Assessment Rules Expected Fall 2023
December 23, 2023 —
Amanda G. Halter, Jillian Marullo & Ashleigh Myers - Gravel2Gavel Construction & Real Estate Law BlogThe U.S. Department of the Interior (DOI) anticipates proposing a new rule that would revise its “Type A” Natural Resource Damage Assessment (NRDA) regulations under the Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) in Fall 2023. The proposed rule would modernize DOI’s rarely used simplified Type A procedures for assessing damages for natural resource injuries tailored at sites involving minor releases of hazardous substances, with a smaller scale and scope of natural resource injury occurring in either coastal and marine areas or Great Lakes environments (the “Type A Rule”). (See 88 Fed. Reg. 3373; see 43 C.F.R. Pt. 11 Subpt. D.) The Type A Rule was last updated in 1997.
DOI previewed the proposal in January 2023 in its Office of Restoration and Damage Assessment’s (ORDA)
Advanced Notice of Proposed Rulemaking (ANPR). In the ANPR, the ORDA surmised that the Type A Rule was rarely used in part because of its restricted scope, but also because “the model equation for each Type A environment is the functional part of the rule itself—with no provisions to reflect evolving toxicology, ecology, technology, or other scientific understanding without a formal amendment to the Type A Rule each time a parameter is modified.” Calling the existing rule “inefficient and inflexible,” the ORDA stated that its proposal to reformulate the rule “as a procedural structure” would “modernize the Type A process and develop a more flexible and enduring rule than what is provided by the two existing static models” (88 Fed. Reg. 3373).
Reprinted courtesy of
Amanda G. Halter, Pillsbury,
Jillian Marullo, Pillsbury and
Ashleigh Myers, Pillsbury
Ms. Halter may be contacted at amanda.halter@pillsburylaw.com
Ms. Marullo may be contacted at jillian.marullo@pillsburylaw.com
Ms. Myers may be contacted at ashleigh.myers@pillsburylaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Use Your Instincts when Negotiating a Construction Contract
August 07, 2018 —
Christopher G. Hill - Construction Law MusingsI have often discussed the more “mechanical” aspects of contract negotiation and drafting here at Construction Law Musings. However, there is another, less objective (possibly) and more “feel” oriented aspect to construction contracting that can have as big an impact on your construction project. What am I talking about? Your instinct as a construction professional when looking the other party in the eye and getting a feel for the company or individual with whom you are contracting.
Why is this so important? Firstly, and this is a truism, no matter how well drafted your construction contract is (and it should be well drafted and reviewed by an experienced construction attorney), if the other party wishes to “play games” and not honor the terms of that contract, you could still very well end up in litigation with the attendant frustration and expense. Having a great looking, well thought out and at least reasonably “fair” construction contract may make the litigation process somewhat less painful but it does not completely avoid the risk of litigation. If the other party or parties to the contract decide not to pay you or perform as they promised, you are left to enforce whatever contract you have in place.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
The Fourth Circuit Applies a Consequential Damages Exclusionary Clause and the Economic Loss Doctrine to Bar Claims by a Subrogating Insurer Seeking to Recover Over $19 Million in Damages
February 23, 2016 —
William L. Doerler – White and Williams LLPIn Severn Peanut Company, Inc. v. Industrial Fumigant Company, 807 F.3d 88 (4th Cir. (N.C.) 2015), the United States Court of Appeals for the Fourth Circuit (Fourth Circuit), applying North Carolina law, considered whether a consequential damages clause in a contract between the Severn Peanut Company, Inc. (Severn) and Industrial Fumigant Company (IFC) barred Severn and its subrogating insurer, Travelers Property Casualty Company of America (Travelers), from recovering over $19 million in damages that Severn suffered as the result of a fire and explosion at its Severn, North Carolina plant. The Fourth Circuit, rejecting Severn’s unconscionability and public policy arguments related to the consequential damages clause and finding that the economic loss doctrine barred Severn from pursuing negligence claims, affirmed the trial court’s judgment granting summary judgment in IFC’s favor.
As noted in the Severn decision, the facts showed that Severn and IFC signed a Pesticide Application Agreement (PAA) requiring IFC to use phosphine, a pesticide, to fumigate Severn’s peanut storage dome and to apply the pesticide “in a manner consistent with instructions . . . and precautions set forth in [its] labeling.” With respect to damages, the PAA specified that IFC’s charge for its services, $8,604 plus applicable sales tax, was “based solely upon the value of the services provided” and was not “related to the value of [Severn’s] premises or the contents therein.” In addition, the PAA specified that the $8,604 sum to which the parties agreed was not “sufficient to warrant IFC assuming any risk of incidental or consequential damages” to Severn’s “property, product, equipment, downtime, or loss of business.”
Read the court decisionRead the full story...Reprinted courtesy of
William L. Doerler, White and Williams LLPMr. Doerler may be contacted at
doerlerw@whiteandwilliams.com
Legislation Update: S-865 Public-Private Partnerships in New Jersey Passed by Both Houses-Awaiting Governor’s Signature
July 02, 2018 —
Steven M. Charney & Charles F. Kenny - Peckar & Abramson, P.C.New Jersey is finally close to being among the many states with broad authority to develop or improve public projects through a Public-Private Partnership (P3) delivery method. This contracting model has stimulated growth and improvements in other States and led to the delivery of projects that may not otherwise have happened. Senate Bill 865 (“S-865”), after undergoing some last-minute amendments in a frenzied legislature dealing with budget and other critical issues, has passed in both houses of the Legislature and is waiting for Governor Murphy’s signature, which is expected shortly. The law will be effective 180 days from formal enactment. The administrative framework is now in place to make Public-Private Partnerships a reality in New Jersey.
Reprinted courtesy of
Steven M. Charney, Peckar & Abramson, P.C. and
Charles F. Kenny, Peckar & Abramson, P.C.
Mr. Charney may be contacted at scharney@pecklaw.com
Mr. Kenny may be contacted at ckenny@pecklaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Burden to Prove Exception to Exclusion Falls on Insured
April 19, 2022 —
Tred R. Eyerly - Insurance Law HawaiiIn a dispute between two insurers, the Ninth Circuit relied upon Nevada law in finding that the burden of proving that an exception to the exclusion applies was on the insured. Zurich Am. Ins. Co. v. Ironshore Specialty Ins. Co., 2022 U.S. App. LEXIS 1626 (9th Cir. Jan. 20, 2022).
Ironshore insured seven subcontractors. The policy included an exclusion providing there was no coverage for any property damage for the subcontractors' for "work performed prior to the policy inception." An exception to the exclusion provided that the exclusion did not apply to property damage that was "sudden and accidental and takes place within the policy period."
The seven subcontractors were sued for work they had performed. Zurich defended and indemnified the subcontractors. Zurich then sued Ironshore seeking contribution and indemnification for defense and settlement costs. The parties stipulated that all construction work at issue had been completed before the inception of Ironshore's policy and that none of the complaints against the subcontractors alleged that sudden and accidental damage had occurred after the inception of Ironshore's policy.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at