Policy's Limitation Period for Seeking Replacement Costs Not Enforced Where Unreasonable
March 12, 2014 —
Tred R. Eyerly – Insurance Law HawaiiThe New York Court of Appeals determined that a two year period for obtaining replacement costs for damage to property was unenforceable where the property could not be reasonably replaced in two years. Executive Plaza, LLC v. Peerless Ins. Co., 2014 WL 551251 (N.Y. Ct. App. Feb. 13, 2014).
Plaintiff's office building was severely damaged in a fire on February 23, 2007. It cost more than a million dollars to restore the building to its previous condition. Plaintiff had $1 million in coverage from Peerless. The policy provided that replacement costs for any loss would be paid after the damaged property was repaired. The insured was required to make the repairs as soon as possible. Further, the policy provided that any legal action against the insurer had to be brought within two years of the loss.
Peerless paid the "actual cash value" of the destroyed building pursuant to the policy in the amount of $757,812.50. Peerless informed the plaintiff that it would have to provide documentation of the completion of repairs to collect the full replacement value, another $242,187.50.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Summary Findings of the Fourth National Climate Assessment
January 02, 2019 —
Anthony B. Cavender - Gravel2GavelOn November 23, the latest National Climate Assessment, Fourth National Climate Assessment (NCA4), was released by the U.S. Global Research Program, as required by the Clean Air Act. The Assessment, comprising three volumes and 1600 pages, contains some rather bleak findings which the Report usefully summarizes. Here’s a description of these findings.
1.
Communities. The report states that “climate change creates new risks and exacerbates existing vulnerabilities in communities across the United States.” In particular, “more frequent and intense extreme weather and climate-related events” will continue to damage infrastructure , ecosystems and social systems. However, “global action” to significantly cut greenhouse gas emissions can substantially reduce these risks.
Read the court decisionRead the full story...Reprinted courtesy of
Anthony B. Cavender, PillsburyMr. Cavender may be contacted at
anthony.cavender@pillsburylaw.com
A Court-Side Seat: Recent Legal Developments at Supreme and Federal Appeals Courts
December 18, 2022 —
Anthony B. Cavender - Gravel2GavelThis is a review of initial Supreme Court and Federal Appeals Courts oral arguments and other matters in October 2022.
Oral Arguments at the Supreme Court
Michael Sackett, et ux., v. Environmental Protection Agency
The Supreme Court’s 2022 term began on October 3, 2022, with this important oral argument. For many years, the petitioner has encountered EPA opposition to the construction of a home on his property located near a lake in Idaho. The agency insists that the land is subject to federal regulatory jurisdiction, in that a Clean Water Act permit will be needed before work can proceed. Several courts have already weighed in on this issue; whether the land in question is considered a regulated “wetlands” pursuant to the “significant nexus” test developed by the Court in the Rapanos case decided in 2006. The oral argument was fairly long and spirited. The justices appear to believe that the “significant nexus” is unworkable because in many instances it provides little or no guidance to landowners as to whether their property may be subject to federal jurisdiction, and thus subject to civil and even criminal penalties. Justice Kavanaugh remarked that “this case is going to be important for wetlands throughout the country and we have to get it right.” Later, Justice Gorsuch lamented the fact that implementing a test for federal jurisdiction under the Clean Water Act test is so difficult to apply: “If the federal government doesn’t know [if a property is adjacent to navigable water and is regulated,] “does a reasonable landowner have any idea.” The issue is very difficult to resolve, and the Congress has indicated that is has no interest in entering this regulatory thicket.
Read the court decisionRead the full story...Reprinted courtesy of
Anthony B. Cavender, PillsburyMr. Cavender may be contacted at
anthony.cavender@pillsburylaw.com
Judgment for Insured Upheld After Insurer Rejects Claim for Hurricane Damage
April 15, 2015 —
Tred R. Eyerly – Insurance Law HawaiiThe Texas Court of Appeals affirmed a trial court's judgment as modified against Lloyds for improperly denying a claim for damage caused by Hurricane Ike. Nat'l Lloyds Ins. Co. v. Lewis, 2015 Tex. App. LEXIS 1573 (Tex. Ct. App. Feb. 19, 2015).
Lewis sued Lloyds, alleging that, although her home and personal property were seriously damaged by Hurricane Ike, her claim was denied. At trial, Lloyds testified that the damage to Lewis' home had been previously caused by Hurricane Rita and Lloyds had already paid for repair of the roof. Nevertheless, Lewis had not used the payment for roof repairs. Lewis admitted that she used some of the payment after Hurricane Rita to purchase a generator and for evacuation expenses, but the majority of the payment was used for roof repairs.
Lewis' expert engineer testified that the damage to Lewis' home was caused by wind and water intrusion through a hole caused by a tree limb that fell during Hurricane Ike. The expert further opined that the cost to mitigate the damage to the home and bring it up to livable standard was $156,155. Further, the home was a constructive total loss.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Will They Blow It Up?
March 28, 2012 —
CDJ STAFFThe issues concerning the Harmon Towers building in Las Vegas continue to make their way through the courts. As we noted in a previous piece, Cook County building officials stated that the building could be a hazard if Las Vegas were struck by an earthquake. The question of whether the building will continue to stand is just one of the issues in front of a judge.
MGM Resorts International argued at a March 13 hearing for permission to implode the Harmon hotel building. They claim that more than 1,700 defects have been discovered in the building and that the building is a public safety hazard. Arguing against demolition, Perini Building Company, the general contractor for the hotel, and its subcontractors are claiming that imploding the building would destroy evidence and prejudice juries in the ongoing construction defect claims. They claim that MGM Resorts wishes to abandon the building due to the economic slowdown. Perini Corp, the contractor for the project, claims that the building can be fixed. Perini claims that MGM’s position in the construction trial would be improved if the building is demolished.
After Judge Elizabeth Gonzalez heard the four days of testimony on the Harmon Towers building and whether it should be demolished, she scheduled more testimony, with two days in April and an entire week in July. Judge Gonzalez will be deciding whether the building will be torn down, imploded, or left in place.
Read the full story…
Read the full story…
Read the court decisionRead the full story...Reprinted courtesy of
COVID-19 Response: Recent Executive Orders Present Opportunities for Businesses Seeking Regulatory and Enforcement Relief and Expedited Project Development
June 15, 2020 —
Karen C. Bennett, Jane C. Luxton & Amanda L. Tharpe - Lewis BrisboisWashington, D.C. (June 8, 2020) - Two recent Executive Orders (EO) aimed at promoting economic recovery from the COVID-19 crisis offer regulatory and enforcement relief and encourage agencies to expedite infrastructure project approvals. The May 19, 2020 EO 13924, “Regulatory Relief to Support Economic Recovery,” directs agencies to determine whether previous regulatory reforms would promote economic recovery if made permanent and encourages compliance assistance through exercising enforcement discretion, including declining enforcement. And the June 4, 2020 EO 13927, “Accelerating the Nation’s Economic Recovery from the COVID-19 Emergency by Expediting Infrastructure Investments and Other Activities,” aims to speed up the permitting process for infrastructure projects to strengthen the national economy. As businesses look to move forward and recover from the COVID-19 pandemic, they should closely review these EOs for opportunities to take advantage of streamlined treatment and faster project approvals.
EO 13294 supplements the Administration’s efforts to address the economic crisis brought on by the COVID-19 pandemic by encouraging federal agencies to rescind, modify, waive, or provide exemptions from federal regulations that may inhibit economic recovery and to provide guidance to businesses, particularly small businesses, on what is required of them under federal law for reopening. Specifically, the EO directs agency heads to identify regulatory standards that may inhibit economic recovery and consider rescinding or waiving those regulations, exempting regulated entities from compliance, exercising enforcement discretion, or extending regulatory compliance and enforcement deadlines. It also allows for compliance assistance through accelerated regulatory procedures to receive a pre-enforcement ruling and directs agencies to assess previous regulatory reforms to determine whether making them permanent would promote economic recovery. Since taking office, the Trump Administration has made regulatory reform a cornerstone of its agenda. This Executive Order is a continuation of the aggressive steps taken by the Administration to reduce the regulatory burden faced by American businesses that many argue increases operating costs, inhibits job creation, and stifles economic growth.
Reprinted courtesy of Lewis Brisbois attorneys
Karen C. Bennett,
Jane C. Luxton and
Amanda L. Tharpe
Ms. Bennett may be contacted at Karen.Bennett@lewisbrisbois.com
Ms. Luxton may be contacted at Jane.Luxton@lewisbrisbois.com
Ms. Tharpe may be contacted at Amanda.Tharpe@lewisbrisbois.com
Read the court decisionRead the full story...Reprinted courtesy of
Contractual Impartiality Requires an Appraiser to be Unbiased, Disinterested, and Unswayed by Personal Interest
June 01, 2020 —
Frank Ingham - Colorado Construction Litigation BlogOn June 24, 2019, the Colorado Supreme Court held that when a contract or insurance policy requires an “impartial” appraisal, the appraiser for a party cannot be an advocate for that party.[1] In this situation, the appraiser must be unbiased, disinterested, without prejudice, and unswayed by personal interest. Id.
Owners Insurance Company (“Owners”) issued a policy to the Dakota Station II Condominium Association, Inc. (“Association”) that represents a 49-building multifamily residential property in Jefferson County, Colorado. Concerning loss conditions, the policy includes an appraisal provision requiring that, in the event of property appraisal, “each party will select a competent and impartial appraiser.” The parties would then select an umpire or have one appointed by the court. Any agreement as to the values reached by two of the three would bind them all.
On May 24, 2012, the Association made a storm-damage roofing claim to Owners for $1.33 million. The parties could not agree on the amount of the loss and the Association invoked the policy’s appraisal process. The Association retained Scott Benglen as its contingent-fee cap appraiser. Mr. Benglen retained Laura Haber as a policy and damage expert, who appraised the roof loss at $2.55 million and the total replacement at $4.3 million.[2] Owners’ appraiser, Mark Burns, submitted the loss at $1.86 million with the replacement cost award of $2.3 million. The umpire, Honorable James Miller, adopted Owners’ estimates in four of the six categories, awarding just over $3 million to the Association. Id.
Read the court decisionRead the full story...Reprinted courtesy of
Frank Ingham, Higgins, Hopkins, McLain & RoswellMr. Ingham may be contacted at
ingham@hhmrlaw.com
Wisconsin Court Applies the Economic Loss Doctrine to Bar Negligence Claims for Purely Economic Losses
August 17, 2020 —
Rahul Gogineni - The Subrogation StrategistIn Mech. Inc. v. Venture Elec. Contrs., Inc., No. 2018AP2380, 2020 Wisc. App. LEXIS 170, the Court of Appeals of Wisconsin, District Two, considered whether a party may bring a negligence claim for purely economic damages. In upholding the lower court, the appellate court found that a party is barred by the Economic Loss Doctrine from bringing a negligence claim for purely economic damages.
Both parties involved in this action were subcontractors on a building project at the Great Lakes Research Facility for the University of Wisconsin-Milwaukee. As a result of Venture Electrical Contractors, Inc. (Venture) not paying for requested work, Mechanical, Inc. (Mechanical) sued Venture for $11,961.31. Venture, in turn, countersued in negligence for $1.1 million for costs incurred due to delays and untimely performance. Mechanical sought dismissal of the negligence claim based upon the Economic Loss Doctrine. Finding that the Economic Loss Doctrine applies to purely economic losses, the trial court dismissed Venture’s negligence claim. Venture appealed to the Court of Appeals of Wisconsin.
Read the court decisionRead the full story...Reprinted courtesy of
Rahul Gogineni, White and Williams LLPMr. Gogineni may be contacted at