Experts: Best Bet in $300M Osage Nation Wind Farm Dispute Is Negotiation
March 11, 2024 —
Daniel Tyson - Engineering News-RecordNearly two months after a federal judge ruled that renewables developer Enel Green Power North America must deconstruct 84 land-based wind turbines because it did not secure mineral rights on Osage Nation land in northern Oklahoma, two energy sector attorneys say the unit of an Italy-based company must negotiate with the tribe.
Reprinted courtesy of
Daniel Tyson, Engineering News-Record
Mr. Tyson may be contacted at tysond@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Construction Defects through the Years
July 31, 2013 —
CDJ STAFFBuilder has an article on the some building changes over the years that have led to construction defect problems. Is insulation evil? Well, that what some thought in the 1930s. Early attempts at insulating walls trapped moisture causing paint to peel. Then in the 1960s, the rise of aluminum wire lead to an even more serious problem: house fires.
And it continues. The plastic piping that was though to last forever when it was installed in the late 70s turned out to have about a decade of life. It’s a short forever. Eventually, polybutylene plumbing was forbidden by building codes.
The article has a series of building innovations that seemed like great ideas at the time, but were later found to be problematic.
Read the court decisionRead the full story...Reprinted courtesy of
The ABCs of PFAS: What You Need to Know About Liabilities for the “Forever Chemical”
February 22, 2021 —
Robert F. Walsh, Gregory S. Capps & R. Victoria Fuller - Complex Insurance Coverage ReporterThis article is based on a presentation the authors made at White and Williams LLP’s Virtual Coverage College® on October 22, 2020. Every year, hundreds of insurance professionals come to Philadelphia—this year via our online platform—to participate in a full day of lectures and interactive presentations by White and Williams lawyers and guest panelists about the latest issues and challenges involved in claim handling and insurance litigation. Visit coveragecollege.com for more information and stay tuned for Coverage College® 2021.
Perfluoroalkyl and polyfluoroalkyl substances, commonly referred to as PFAS or PFOS, have been a key ingredient in numerous industrial and consumer products for decades. These man-made chemicals are prevalent and are also known for their longevity in the environment. More recently, PFAS have been the focus of thousands of lawsuits alleging personal injury and property damage. Some insurers have already questioned whether PFAS could rival asbestos in scope and bottom-line impacts. It is a legacy that confronts manufacturers and other defendants and insurers today.
This article provides a primer on PFAS, including the current regulatory framework and litigation landscape. We also identify some key emerging coverage issues insurers should be aware of when dealing with PFAS claims under liability and first-party property policies.
Reprinted courtesy of
Robert F. Walsh, White and Williams LLP and
Gregory S. Capps, White and Williams LLP
Mr. Walsh may be contacted at walshr@whiteandwilliams.com
Mr. Capps may be contacted at cappsg@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of
It’s Time to Change the Way You Think About Case Complexity
August 07, 2018 —
Ben Patrick - Gordon & Rees Construction Law BlogThere are few things that lawyers love more than telling war stories. Partially, that’s because many lawyers either only or primarily have friends who are lawyers, and war stories are a way for lawyers to relate to each other—your barber doesn’t understand the pain of reading through 5 paragraphs of irrelevant objections posed to each of 75 interrogatories, but your fellow lawyers will. One common feature of war stories is a note regarding how much was at issue in the case. “I was handling this $25 million claim once….” Lawyers include the dollar figure in dispute as a shorthand for the complexity of the case they’re talking about. “Oh, we’ll be in depositions for a month solid, this is a $10 million case!”
I don’t know where I picked up this habit, but I know exactly how I learned to rethink it. A friend of mine, as in-house counsel, was handling a case worth over a billion dollars. When he told me about it, my jaw dropped. One of the first things I asked him was, how do you manage a case that big? And he told me about the several law firms he had engaged, all the people working on it. But then he said: it’s not really a complicated case. There were only 4-5 real factual questions, and a similar number of legal ones. It’s just that every factual question had a very high price tag associated with it. The high price tag doesn’t make the factual question any more complex, or any harder to litigate. For example, your builders’ risk policy either has coverage for flood damage or it doesn’t. If it does, then it doesn’t matter whether the flood washed the whole building away or just some materials from the laydown area—coverage is coverage, irrespective of quantum.
Read the court decisionRead the full story...Reprinted courtesy of
Ben Patrick, Gordon & Rees Scully MansukhaniMr. Patrick may be contacted at
jpatrick@grsm.com
The Clock is Ticking: Construction Delays and Liquidated Damages
September 18, 2023 —
Tiffany Harrod - ConsensusDocsWith the on-going shortage of construction workers in the industry and other factors ranging from weather to procurement problems, the threat of project delay is real. When a contract contains a liquidated damages clause for assessing project delays, real financial consequences for contractors can result. Courts have long allowed parties to apportion contractual risks as they deem appropriate especially in the commercial context where the parties are considered to be sophisticated even if their bargaining power is not equal. Liquidated damage provisions such as those for delay that are found in construction contracts are not unusual but they must be crafted in such a way as to be enforceable and not violate public policy.
A liquidated damage clause in a construction contract is a customary way for the parties to deal with the possibility of delay in the completion of a project and the potential losses flowing from the delay.[
1] In their most basic form, the party in breach, which is more often than not the contractor, is obligated to pay the non-breaching party, usually the project owner, some fixed sum of money for the period that exceeds the designated completion date that was agreed upon in advance and memorialized in the contract. (It is after all no secret that these provisions are primarily for the owner’s benefit.) The non-breaching party is then compensated for losses associated with the delay without the time and expense of having to prove in either a civil suit or an arbitration proceeding what the actual damages are. This option is particularly attractive to project owners because the liquidated damages assessment can simply be withheld from payments owed to the contractor once the agreed-upon completion date has been passed.
Read the court decisionRead the full story...Reprinted courtesy of
Tiffany Harrod, Peckar & AbramsonMs. Harrod may be contacted at
tharrod@pecklaw.com
California’s Right To Repair Act Is The Sole Remedy For Damages For Construction Defects In New Residential Construction
March 14, 2018 —
Mark Johnson – Real Estate Litigation Blog The California Supreme Court ruled in
McMillin Albany LLC et al. v. The Superior Court of Kern County, (1/18/2018) 4 cal. 5th 241, that California’s Right to Repair Act, California Civil Code sections 895 et seq. (“Act”) is the sole remedy for construction defect claims for economic loss and property damages regarding new residential construction. The Act establishes a pre-litigation dispute resolution process that must be followed before filing a construction defect action for new residential construction purchased after January 1, 2003. The Act provides a builder with the right to attempt to repair construction defects before litigation is filed.
The
McMillin ruling resolved a split among two court of appeal decisions regarding the scope of the Act:
Liberty Mutual Insurance Company v. Brookfield Crystal Cove LLC (2013) 219 Cal.App.4th 98 and
Burch v. Superior Court [(2014) 223 Cal.App.4th 1411. Those cases held that the Act is not the exclusive remedy for construction defect lawsuits that allege property damage arising from new residential construction. Therefore owners of new residential construction where construction defects had caused property damage were not required to proceed under the Act and instead could proceed with common law claims.
McMillilin removes that option.
Read the court decisionRead the full story...Reprinted courtesy of
Mark Johnson, Snell & WilmerMr. Johnson may be contacted at
majohnson@swlaw.com
More Money Down Adds to U.S. First-Time Buyer Blues: Economy
August 20, 2014 —
Michelle Jamrisko and Alexis Leondis – BloombergThe challenges facing prospective buyers of the least expensive homes in the U.S. are getting harder to overcome.
Already beset by stagnant wages, growing student debt and competition from investors who are snapping up listings, those looking to purchase moderately priced houses must also provide more cash up front. The median down payment for the cheapest 25 percent of properties sold in 2013 was $9,480 compared with $6,037 in 2007, the last year of the previous economic expansion, according to data from 25 of the largest metro areas compiled by brokerage firm Redfin Corp.
The higher bar is a symptom of still-tight credit that is crowding out first-time buyers even as interest rates remain near historical lows. Younger adults, who would normally be making initial forays into real estate, are among those most affected, weakening the foundations of the housing market and limiting its contribution to economic growth.
Ms. Jamrisko may be contacted at mjamrisko@bloomberg.net; Ms. Leondis may be contacted at aleondis@bloomberg.net
Read the court decisionRead the full story...Reprinted courtesy of
Michelle Jamrisko and Alexis Leondis, Bloomberg
Flooded Courtroom May be Due to Construction Defect
September 01, 2011 —
CDJ STAFFThe General Services Administration wouldn’t pin it on a construction defect, but a spokesperson said that a pipe that was misaligned during installation was the likely cause of a flood in the Thomas F. Eagleton US Courthouse on August 23. According to the St. Louis Dispatch, the burst pipe caused a 17-story waterfall in the courthouse, soaking ceilings and floors, and drenching the building’s contents.
The building was dedicated eleven years ago. During the nearly ten years before the building was complete, there were construction disputes and soil contamination issues.
Read the full story…