Triggering Duty to Advance Costs Same Standard as Duty to Defend
April 11, 2018 —
Tred R. Eyerly - Insurance Law HawaiiInterpreting Hawaii law, the federal district court held that the standard for triggering the duty to defend is the same as the standard for the duty to advance costs under a D&O policy.
Maui Land & Pineapple Co. v. Liberty Ins. Underwriters, 2018 U.S. Dist. LEXIS 56949 (D. Haw. April 3, 2018).
The underlying plaintiffs sued 22 defendants, including Maui Land Pineapple (MLP) and Ryan L. Churchill, concerning a residential development project known as The Ritz-Carlton Club & Residences. The underlying complaint alleged that MLP "directly or indirectly through wholly owned subsidiaries exerts control" over Kapalua Bay, LLC, the defendant in the underlying lawsuit. Kapalua Bay, LLC was created as a joint venture of which MLP held 51%. Churchill was a senior executive officer of MLP, President of Kapalua Bay, and an executive officer of Kapalua Realty, which participated in all aspects of the Project, such as financing, development, and construction.
In their second amended complaint, the underlying plaintiffs alleged nine Counts against the defendants, including breach of fiduciary duty. It was alleged that defendants were not transparent and kept owners in the dark regarding the status of the project. Several allegations named Churchill individually and described his alleged material misrepresentations to the underlying plaintiffs regarding the project's financing.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
In Florida, Component Parts of an Improvement to Real Property are Subject to the Statute of Repose for Products Liability Claims
December 02, 2015 —
Michael L. DeBona – White and Williams LLPIn Dominguez v. Hayward Industries, Inc., Certified Gunite Company d/b/a Custom Pools, and John M. Pieklo, — So.3d —-, 2015 WL 5438782 (3d DCA Sept. 16, 2015), the District Court of Appeal of Florida, Third District, discussed whether products liability claims related to a pool filter, a component part of a pool system, were subject to Florida’s twelve-year products liability statute of repose, section 95.031, Florida Statutes. The court held that a pool filter does not constitute an improvement to real property and, thus, the plaintiffs’ claims were subject to the statute of repose.
Background Facts
Ryan and Jessica Dominguez had a pool installed at their house; the delivery and installation of the pool and its filter were completed on December 20, 1999. Over twelve years later – on November 17, 2012 – the pool filter exploded, causing Mr. Dominguez a severe head injury. Mr. Dominguez and his wife brought a products liability action against, among others, the pool filter manufacturer and distributor, Hayward Industries, Inc., and the installer of the pool and intermediate distributor of the pool filter, Certified Gunite Company.
Read the court decisionRead the full story...Reprinted courtesy of
Michael L. DeBona, White and Williams LLPMr. DeBona may be contacted at
debonam@whiteandwilliams.com
Effective Zoning Reform Isn’t as Simple as It Seems
July 03, 2022 —
Yonah Freemark & Lydia Lo - BloombergThe Biden Administration’s Housing Supply Action Plan, unveiled last week, aims to help close America’s shortfall of almost 4 million housing units and subdue the nation’s skyrocketing home prices. At the top of its list of action items is a promise to provide federal grants as a reward to communities that alter land-use policies to promote density, an approach the administration is already piloting.
But identifying the land-use policies that most effectively add housing is harder than it seems. Mounting evidence indicates that one-off reforms such as eliminating single-family-only zoning aren’t adequate. To make meaningful progress in building homes, municipalities have to do more.
The Biden plan doesn’t detail how it will determine which types of policies will make a community eligible for these federal grants. But to meet the administration’s housing goals, we recommend it require that local governments seeking grants both show that their zoning changes are actually producing additional housing units, and also that their reforms include the full array of land-use policies that affect housing affordability.
Read the court decisionRead the full story...Reprinted courtesy of
Bloomberg
Do Not File a Miller Act Payment Bond Lawsuit After the One-Year Statute of Limitations
November 01, 2022 —
David Adelstein - Florida Construction Legal UpdatesUnder the Miller Act, a claim against a Miller Act payment bond must be commenced “no later than one year after the date on which the last of the labor was performed or material was supplied by the person bringing the action.” 40 U.S.C. s. 3133(b)(4). Stated another way, a claimant must file its lawsuit against the Miller Act payment bond within one year from its final furnishing on the project.
Filing a lawsuit too late, i.e., outside of the one-year statute of limitations, will be fatal to a Miller Act payment bond claim. This was the outcome in Diamond Services Corp. v. Travelers Casualty & Surety Company of America, 2022 WL 4990416 (5th Cir. 2022) where a claimant filed a Miller Act payment bond lawsuit four days late. That four days proved to be fatal to its Miller Act payment bond claim and lawsuit. Do not let this happen to you!
In Diamond Services Corp., the claimant submitted a claim to the Miller Act payment bond surety. The surety issued a claim form to the claimant that requested additional information. The claimant returned the surety’s claim form. The surety denied the claim a year and a couple of days after the claimant’s final furnishing. The claimant immediately filed its payment bond lawsuit four days after the year expired. The claimant argued that the surety should be equitably estopped from asserting the statute of limitations in light of the surety’s letter requesting additional information. (The claimant was basically arguing that the statute of limitations should be equitably tolled.) The trial court dismissed the Miller Act payment bond claim finding it was barred by the one-year statute of limitations and that equitable estoppel did not apply.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Comparing Contracts: A Review of the AIA 201 and ConsensusDocs - Part II
March 28, 2018 —
Michael Sams and Amanda Cox – Construction Executive, A publication of Associated Builders and Contractors. All Rights Reserved.Part II of this three-part series compares and analyzes important contract sections in the AIA 201 (2007 and 2017 versions) and ConsensusDocs (2014 and 2017 versions), including Schedule/Time, Consequential Damages/LDs, Claims and Disputes/ADR.
Part I covered Financial Assurances, Design Risk, Project Management and Contract Administration. Part III will cover Insurance and Indemnification and Payment.
SCHEDULE/TIME
Relevant Sections:
- 2007 & 2017 A201: Section 3.10.1
- 2014 & 2017 ConsensusDocs: Section 6.2
AIA:
- Section 3.10.1 of the 2007 A201 requires that the Contractor promptly after being awarded the Contract, prepare and submit a construction schedule providing for Work to be completed within the time limits required in the Contract Documents.
- This schedule shall be revised at appropriate intervals.
- The 2017 edition breaks down the schedule to contain date of commencement, interim milestone dates, date of substantial completion, apportionment of Work by trade or building system, and the time required for completion of each portion of the Work.
- Under section 3.10.2 of the 2007 and 2017 versions, if the Contractor fails to provide a submittal schedule, the Contractor is not entitled to any additional compensation or a time extension based on the Owner’s or the Architect’s slow processing of submittals, regardless of how long they take.
ConsensusDocs 200:
- The 2017 Contract replaces the term Contract Time and instead requires a “Schedule of the Work…formatted in detailed precedence-style critical path method that (a) provides a graphic representation of all activities and events, including float values that will affect the critical path of the Work and (b) identifies dates that are critical to ensure timely and orderly completion of the Work.”
- The Constructor must submit an initial schedule to the Owner only before, “first application for payment” and thereafter on a monthly basis. (Section 6.2.1).
- The Owner is allowed to change the sequences provided in the schedule as long as it does not “unreasonably interfere with the Work.” (Section 6.2.2).
Reprinted courtesy of
Michael Sams , Kenney & Sams and
Amanda Cox, Kenney & Sams
Read the court decisionRead the full story...Reprinted courtesy of
Indemnity Provision Provides Relief to Contractor; Additional Insured Provision Does Not
January 06, 2016 —
Tred R. Eyerly – Insurance Law HawaiiThe court found that the contractor was entitled to relief under the contractual indemnity provision, but not the policy's additional insured clause. Chatelain v. Fluor Daniel Constr. Co., 2015 La. App. LEXIS 2257 (Ct. App. La. Nov. 10, 2015).
Following Hurricanes Katrina and Rita, FEMA retained Fluor Enterprises, Inc. as a contractor to transport and install FEMA trailers. Fluor entered a Blanket Ordering Agreement (BOA) with Bobby Reavis Contracting, Inc. to transport and install the trailers. The BOA provided Reavis would defend and indemnify Fluor from all liability arising from the subcontractor's work. Reavis also agreed to name Fluor as an additional insured under its CGL policy.
Reavis installed a FEMA trailer for Connie Chatelain. Ms. Chatelain was injured when she fell exiting her FEMA trailer. She sued Fluor and Reavis. Fluor tendered the suit to Reavis and Reavis' insurer, Guilford Insurance Company. The tender was rejected and Fluor filed a third-party action demanding indemnification, reimbursement of all legal expenses and damages for insurer misconduct.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
68 Lewis Brisbois Attorneys Recognized in 5th Edition of Best Lawyers: Ones to Watch in America
September 23, 2024 —
Lewis Brisbois Newsroom(August 15, 2024) – 68 Lewis Brisbois attorneys across 26 offices have been named to the 5th edition of “Best Lawyers: Ones to Watch in America.” Congratulations to the following attorneys on this recognition!
You can see the list of Lewis Brisbois attorneys named to Best Lawyers' 30th edition of The Best Lawyers in America here.
Reprinted courtesy of
Lewis Brisbois
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
The Importance of Providing Notice to a Surety
October 21, 2015 —
Craig Martin – Construction Contractor AdvisorA recent case out of Missouri emphasizes the importance of providing notice to a surety when a bonded subcontractor is in default. When the question of whether a surety will be obligated under the bond is in the balance, notice is crucial.
In CMS v. Safeco Insurance Company, Safeco provided a performance bond to a subcontractor for the benefit of CMS. The bond specifically provided:
“PRINCIPAL DEFAULT. Whenever the Principal [Subcontractor] shall be, and is declared by the Obligee [CMS] to be in default under the Subcontract, with the Obligee having performed its obligations in the Subcontract, the Surety [Safeco] may promptly remedy the default, or shall promptly:
4.1 COMPLETE SUBCONTRACT. . . .
4.2 OBTAIN NEW CONTRACTORS. . . .
4.3 PAY OBLIGEE. . . .
4.4 DENY LIABILITY. . .”
Read the court decisionRead the full story...Reprinted courtesy of
Craig Martin, Lamson, Dugan and Murray, LLPMr. Martin may be contacted at