Care, Custody or Control Exclusion Requires Complete and Exclusive Control by Insured Claiming Coverage
July 30, 2019 —
Christopher Kendrick & Valerie A. Moore – Haight Brown & Bonesteel LLPIn McMillin Homes Construction v. Natl. Fire & Marine Ins. Co. (No. D074219, filed 6/5/19) a California appeals court held that a “care, custody or control” exclusion did not bar coverage for defense of a general contractor as an additional insured under a subcontractor’s policy, because the exclusion requires exclusive control, but the facts and allegations posed a possibility of shared control with the subcontractor.
McMillin was the general contractor on a housing project and was added as an additional insured to the roofing subcontractor’s policy pursuant to the construction subcontract. The homeowners sued, including allegations of water intrusion from roof defects. McMillin tendered to the roofing subcontractor’s insurer, which denied a defense based on the CGL exclusion for damage to property within McMillin’s care, custody or control.
In the ensuing bad faith lawsuit, McMillin argued that the exclusion required complete or exclusive care, custody or control by the insured claiming coverage, which was not the case for McMillin. The insurer argued that the exclusion said nothing about complete or exclusive care, custody or control. Further, the intent to exclude coverage for damage to any and all property in McMillin’s care, custody or control, to whatever degree, was demonstrated by the fact that the additional insured endorsement in question was not an ISO CG2010 form, but a CG2009 form, which expressly adds a care, custody or control exclusion to the additional insured coverage not found in the CG2010 form. The argument was that the CG2009 form evidences an intent to conclusively eliminate coverage for property in the additional insured’s care, custody or control. In addition, the insurer argued that this result was also reinforced by its inclusion of an ISO CG2139 endorsement in the roofer’s policy, which eliminated that part of the “insured contract” language of the CGL form, defining an “insured contract” as “[t]hat part of any other contract or agreement pertaining to your business . . . under which you assume the tort liability of another party to pay for ‘bodily injury’ or ‘property damage’ to a third person or organization.” The insurer’s argument was that by having eliminated coverage for contractual indemnity or hold harmless agreements, it had “closed the loop” of eliminating additional insured coverage for construction defect claims.
Reprinted courtesy of
Christopher Kendrick, Haight Brown & Bonesteel LLP and
Valerie A. Moore, Haight Brown & Bonesteel LLP
Mr. Kendrick may be contacted at ckendrick@hbblaw.com
Ms. Moore may be contacted at vmoore@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Subcontract Requiring Arbitration Outside of Florida
August 07, 2018 —
David Adelstein - Florida Construction Legal UpdatesHave you entered into a subcontract that requires you to arbitrate disputes? If so, does the arbitration provision require you to arbitrate your dispute outside of Florida? If so, the case of Sachse Construction and Development Corp. v. Affirmed Drywall, Corp., 43 Fla. L. Weekly D1622e (Fla. 2d DCA 2018) applies and reinforces the notion: Read and consider what you sign!
In Sachse Construction, a drywall subcontractor entered into a subcontract for a construction project in Miami with an arbitration provision. The subcontract provided that it shall be construed in accordance with Michigan law and required that arbitration shall take pace in Michigan per the Construction Industry Rules of the American Arbitration Association.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com
Workplace Safety–the Unpreventable Employee Misconduct Defense
October 02, 2015 —
Craig Martin – Construction Contractor AdvisorI just attended an Associated Builders and Contractors meeting during which Lueder Construction discussed a fatality on one of its worksite. OSHA fully investigated the incident and did not issue a single citation. This is a testament to the safety plan and training Lueder had in place well before this incident. One defense to an OSHA citation is unpreventable employee misconduct. However, proving this defense requires substantial planning, well before an incident or investigation.
Unpreventable Employee Misconduct Defense
OSHA requires that an employer do everything reasonably within its power to ensure that its personnel do not violate safety standards. But if an employer lives up to that billing and an employee nonetheless fails to use proper equipment or otherwise ignores firmly established safety measures, it seems unfair to hold the employer liable. To address this dilemma, both the Occupational Safety & Health Review Commission and courts have recognized the availability of the unforeseeable employee misconduct defense.
Read the court decisionRead the full story...Reprinted courtesy of
Craig Martin, Lamson, Dugan and Murray, LLPMr. Martin may be contacted at
cmartin@ldmlaw.com
Sales of Existing U.S. Homes Unexpectedly Fell in January
February 22, 2018 —
Sho Chandra – BloombergSales of previously owned U.S. homes unexpectedly fell in January to a four-month low, indicating a shortage of available properties is increasingly hindering the real-estate industry, a National Association of Realtors report showed Wednesday.
Sales growth is limited by an acute shortage of inventory, which is pushing up home prices faster than wage growth. The group noted that property prices have jumped 41 percent over the past five years, while wages have gained 12 percent.
If the current pace of sales continues -- which NAR doesn’t anticipate -- purchases would be lower than in 2017. At the same time, steady hiring and elevated confidence to make large purchases, as well as tax cuts that are boosting Americans’ take-home pay, are expected to sustain demand for housing in much of the nation.
Read the court decisionRead the full story...Reprinted courtesy of
Sho Chandra, Bloomberg
Documenting Contract Changes in Construction
December 07, 2020 —
J.D. Holzheauser - Construction ExecutiveConstruction projects are almost inevitably subject to changes in the contract. A fundamental understanding of construction changes, how those changes are governed and what is necessary to ensure a complete change are of paramount importance to all parties involved in a construction project. This article is not a treatise on construction contract changes; rather, it provides advice on actions a contractor can take during construction that will help the contractor recover time or money when a contract’s schedule or scope of work needs to be changed.
Changes Defined
Changes to a construction project affect two broad spheres—timing and scope of work. Changes usually present themselves as either a change order or a change directive. Each may go by a different name depending on the contractual scheme in the project’s prime contract, but they essentially have the same characteristics.
The difference between a change order and a change directive is one of agreement. A change order (in the owner-prime contractor context) occurs when the contractor and the owner agree to a change in the timing or scope of work in the contract. Normally, the change order is a written agreement to change the contract and is executed by the contractor and owner.
Reprinted courtesy of
J.D. Holzheauser, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Mr. Holzheauser may be contacted at jdholzheauser@pecklaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Hawaii Bill Preserves Insurance Coverage in Lava Zones
May 20, 2015 —
Tred R. Eyerly – Insurance Law HawaiiThe Hawaii legislature passed a bill in its recently concluded session to protect homeowners and businesses affected by lava flows from losing coverage.
The Puna district on the Big Island was severely impacted by the Pu`u O`o lava flow as it crept closer to homes, businesses, schools and populated areas. Problems were created by the imposition of a moratorium on the sale of new policies in certain areas of the Puna district.
SB 589 grants relief to homeowners who have had continuous insurance in lava zone areas that are declared to be in a state of emergency. The bill (1) allows the homeowners to have their policies renewed, (2) permits continued coverage for homeowners who wish to sell their homes, (3) grants coverage for new buyers of an insured property, and (4) allows homeowners who have not previously had insurance to purchase coverage from the Hawaii Property Insurance Association.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Colorado Requires Builders to Accommodate High-Efficiency Devices in New Homes
December 14, 2020 —
David M. McLain – Colorado Construction LitigationStarting in 2009, the Colorado Legislature began adding requirements that builders offer certain options to accommodate high-efficiency devices. These requirements started with solar prewire options in 2009, then water-smart home options in 2010. In 2020, the Legislature added requirements for electric vehicle charging and heating systems. These sections apply to unoccupied homes serving as sales inventory or a model home or manufactured homes, as defined by Colorado law. While the Legislature has only required builders to include options to accommodate these devices, it may be just a matter of time until builders must install the prescribed devices themselves.
In 2009, the Legislature passed C.R.S. 38-35.7-106, which was amended this year by HB 20-1155. As it now reads, Colorado law requires every builder of single-family detached residences to offer to have the home’s electrical or plumbing system, or both, include:
- A residential photovoltaic solar generation system or a residential thermal system, or both;
- Upgrades of wiring or plumbing, or both, planned by the builder to accommodate future installation of such systems; and
- A chase or conduit, or both, constructed to allow ease of future installation of the necessary wiring or plumbing for such systems.
Read the court decisionRead the full story...Reprinted courtesy of
David McLain, Higgins, Hopkins, McLain & RoswellMr. McLain may be contacted at
mclain@hhmrlaw.com
Oregon Courthouse Reopening after Four Years Repairing Defects
April 01, 2014 —
Beverley BevenFlorez-CDJ STAFFThe Courthouse Square in Marion County, Oregon is due to reopen after four years and nearly $23 million of repair costs to fix structural defects, according to the Statesman Journal. The square includes a courthouse building and bus mall, and is jointly owned by the county and transit district.
Two years after the Courthouse Square had been built, cracks were observed “in the building’s walls” and “paving stones on the bus mall shifted and settled.” A construction defect suit was filed in 2006.
However, the situation worsened in July of 2010 when “engineers determined that the entire complex was dangerous,” according to the Statesman Journal. “Building safety officials gave Courthouse Square’s occupants 60 days to move out, forcing county and transit district operations into temporary leased space.”
Now that the structural repairs have been completed, Dave Clark, project manager with Structural Preservation Systems LLC (the company awarded the repair contract), stated that the building’s structure is now stronger than most buildings. “If there’s an earthquake, come to this building,” Clark said.
Read the court decisionRead the full story...Reprinted courtesy of