Reasonableness of Liquidated Damages Determined at Time of Contract (or, You Can’t Look Back Again)
October 05, 2020 —
Christopher G. Hill - Construction Law MusingsI’ve discussed the continuing litigation between White Oak Power Constructors v. Mitsubishi Hitachi Power Systems Americas, Inc. previously here at Construction Law Musings because the case was another reminder that your construction contract terms matter and will be interpreted strictly here in the Commonwealth of Virginia. The prior opinion in this case from the Eastern District of Virginia court the Court considered the applicability of a liquidated damages provision. In the latest opinion from the Court (PDF) the Court looked at when and how any liquidated damages would be calculated. In its June 22, 2020 opinion, the Court put the issue as follows:
White Oak’s motion for partial summary judgment presents a narrow issue: whether courts may consider the damages actually sustained by a party as a result of a contract breach when deciding if liquidated damages required by a contract “grossly exceed” a party’s actual damages.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Wharf Holdings to Sell Entire Sino-Ocean Stake for $284 Million
December 10, 2015 —
Bloomberg News – BloombergWharf Holdings Ltd., a Hong Kong-based real-estate developer, said it has agreed to sell its entire stake in Sino-Ocean Land Holdings Ltd. for HK$2.2 billion ($284 million) to an undisclosed buyer, three days after Anbang Insurance Group Co. purchased about a fifth of the Chinese builder’s shares.
Wharf will sell 445 million shares, or 5.93 percent of Sino-Ocean Land’s stake, for HK$5 each, the company said in a statement on its website on Thursday. It expects to complete the transaction next week.
Read the court decisionRead the full story...Reprinted courtesy of
Bloomberg News
Velazquez Framing, LLC v. Cascadia Homes, Inc. (Take 2) – Pre-lien Notice for Labor Unambiguously Not Required
May 13, 2024 —
Travis Colburn - Ahlers Cressman & SleightPre-lien Notice for Labor Unambiguously Not Required.
In January 2024, almost a year after Division 2 of the Washington Court of Appeals decided Velazquez Framing, LLC v. Cascadia Homes, Inc.,1 the Washington Supreme Court, sitting en banc, reversed and remanded the matter for further proceedings.2
The relevant background facts are that Cascadia Homes, Inc. (“Cascadia”), was a general contractor and also owned the property that was the subject matter of the underlying dispute. Cascadia wished to construct a new home on the property. Cascadia hired High End Construction, LLC (“High End”) – a framing subcontractor – to provide framing for the new home. High End, in turn, hired Velazquez Framing, LLC (“Velazquez”). Velazquez did not provide Cascadia – the owner – with notice of its statutory right to claim a lien.
Read the court decisionRead the full story...Reprinted courtesy of
Travis Colburn, Ahlers Cressman & SleightMr. Colburn may be contacted at
travis.colburn@acslawyers.com
Hawaii Supreme Court Finds Excess Can Sue Primary for Equitable Subrogation
October 21, 2015 —
Tred R. Eyerly – Insurance Law HawaiiIn responding to a certified question from the U.S. Distric Court, the Hawaii Supreme Court determined that an excess carrier can sue the primary carrier for failure to settle a claim in bad faith within primary limits. St. Paul Fire & Marine Ins. Co. v. Liberty Mut. Ins. Co., 2015 Haw. LEXIS 142 (Haw. June 29, 2015).
St. Paul, the excess carrier, and Liberty Mutual, the primary carrier, issued polices to Pleasant Travel Service, Inc. The primary policy covered up to $1 million.
Pleasant Travel was sued for damages resulting from an accidental death. St. Paul alleged that Liberty Mutual rejected multiple pretrial settlement offers within the $1 million primary policy limit. A trial resulted in a verdict of $4.1 million against Pleasant Travel. The action settled for a confidential amount in excess of the Liberty Mutual policy limit. St. Paul paid the amount in excess.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
One-Upmanship by Contractors In Prevailing Wage Decision Leads to a Bad Result for All . . . Perhaps
July 19, 2021 —
Garret Murai - California Construction Law BlogFights between contractors can be a bit like Mad magazine’s “Spy vs. Spy” with each side trying to out outwit and one-up one another. The next case, Division of Labor Standards Enforcement v. Built Pacific, Inc., Case No. D076601 (March 15, 2021), is a case in point.
The Built Pacific Case
Built Pacific, Inc. was a subcontractor to Austin Sundt Joint Venture on a public works project known as the San Diego Regional Airport Authority Project.
In 2015, following an investigation by the California Division of Labor Standards Enforcement (DLSE), the DLSE issued a Civil Wage Penalty Assessment of $119,319.76 based on Built Pacific’s failure to pay prevailing wages. The DLSE also named Austin Sundt in the Civil Wage Assessment pursuant to Labor Code 1743 which makes contractors and subcontractors jointly and severally liable for wage violations. As a result of the Civil Wage Assessment, Austin Sundt withheld approximately $70,000 in retention from Built Pacific.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
How New York City Plans to Soak Up the Rain
May 02, 2022 —
Linda Poon - BloombergWhen the remnants of Hurricane Ida pummeled New York City with more than 3 inches of rain in just one hour, the city struggled to soak it up. Instead, streets and subways flooded as storm drains were overwhelmed, basement apartments were inundated, and more than a dozen people died.
That September 2021 storm and the ones before it, including a cloudburst downpour during Tropical Storm Elsa in July, have forced New York to take a hard look at becoming a “spongier” city — one that combines nature-based green infrastructure like street-side rain gardens with gray infrastructure like storm drains to divert or absorb water and prevent catastrophic flooding.
“New York City is preparing for both chronic storm events — these cloudburst events that we see occurring more and more frequently — as well as extreme storm events like Ida,” says Jennifer Cherrier, a professor of earth and environmental sciences at Brooklyn College. On top of that, the city also faces mounting risks from storm surges, like during Hurricane Sandy in 2012.
Read the court decisionRead the full story...Reprinted courtesy of
Linda Poon, Bloomberg
Congratulations to BWB&O Partner John Toohey and His Fellow Panel Members on Their Inclusion in West Coast Casualty’s 2022 Program!
March 14, 2022 —
Dolores Montoya - Bremer Whyte Brown & O'Meara LLPBremer Whyte Brown & O’Meara is pleased to announce that Newport Beach Partner John Toohey was selected to speak during the West Coast Casualty Conference on Friday, May 13th at 12 PM PST., alongside panel members Al Clarke of Clarke Mediation, Inc., Brett Reuter of Arch Insurance Group, Inc., Kevin Stineman of Hannover Re Services, Inc. and Scott Rembold of Rembold Hirschman
To register for the West Coast Casualty Conference, please click
here!
Mr. Toohey and his fellow speakers will be discussing The Alternative-to-Alternative Dispute Resolution-Arbitration in Construction Matters and Beyond! Unfortunately, many construction projects end in dispute and the parties frequently find themselves in the middle of uncharted territory – arbitration! Join us as we explore the pitfalls, debunk the myths, and discuss the benefits of arbitration in construction disputes.
Read the court decisionRead the full story...Reprinted courtesy of
Dolores Montoya, Bremer Whyte Brown & O'Meara LLP
Sub-Limit Restricts Insured's Flood Damage Recovery
March 15, 2021 —
Tred R. Eyerly - Insurance Law HawaiiThe insured's recovery for flood damage was controlled by the policy's sub-limit. David S. Brown Enters. v. Affiliated FM Ins. Co., 2020 U.S. Dist. LEXIS 239208 (D. Md. Dec. 18, 2020).
Roughly 6.6 inches of rain fell in Ellicott City, Maryland, causing extensive flooding. During the storm, a water main broke on Main Street, in relatively close proximity to the insured's two properties on Main Street. The foundations of the two properties washed away.
The insured, David S. Brown Enterprises (DSB), had a business owners' policy with Affiliated with covered 204 named locations. The Main Street Properties were not listed, but the policy also provided certain coverage for unnamed locations. The sub-limit applicable to unnamed locations was $1,000,000. The sub-limit for flood, however, was $50,000, annual aggregate "as respects Errors & Omissions, Off-Premises Service Interruption, Unnamed Locations and Supply Chain combined." Affiliated paid $50,000 for the loss based upon the $50,000 Flood annual aggregated Sub-Limit for Unnamed Locations. DSB disagreed that the $50,000 sub-limit applied and filed suit.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at