Fourth Circuit Holds that a Municipal Stormwater Management Assessment is a Fee and Not a Prohibited Railroad Tax
April 22, 2019 —
Anthony B. Cavender - Gravel2GavelOn February 15, the U.S. Court of Appeals for the Fourth Circuit decided Norfolk Southern Railway Co. v. City of Roanoke, et al.; the Chesapeake Bay Foundation was an Intervenor-Defendant. The Fourth Circuit held that a large stormwater management fee (stated to be $417,000.00 for the year 2017) levied by the City of Roanoke against the railroad to assist in the financing of the City’s permitted municipal stormwater management system was a permissible fee and not a discriminatory tax placed on the railroad.
The Railroad Revitalization and Regulatory Reform Act of 1976 specifically provides that states and localities may not impose any tax that discriminates against a rail carrier, 49 U.S.C. § 11501. Accordingly, the issue confronting the Fourth Circuit was whether the assessment was fee and not a tax.
Read the court decisionRead the full story...Reprinted courtesy of
Anthony B. Cavender, PillsburyMr. Cavender may be contacted at
anthony.cavender@pillsburylaw.com
Subsequent Purchaser Can Assert Claims for Construction Defects
October 17, 2022 —
David Adelstein - Florida Construction Legal UpdatesCan a subsequent purchaser pursue construction defect claims relating to the original construction of the property? This was the threshold issue on a motion for summary judgment by a drywall manufacturer against a subsequent purchaser of a home in Karpel v. Knauf Gips KG, 2022 WL 4366946 (S.D. Fla. 2022). This matter deals with the defective Chinese drywall that was installed in homes years ago. The plaintiffs, which were subsequent purchasers of a home, sued the manufacturer of the defective drywall for various theories including negligence, negligence per se, strict liability, breach of express and/or implied warranty, private nuisance, unjust enrichment, and Florida’s Deceptive and Unfair Trade Practices Act.
The trial court noted, from the onset, that Florida does NOT have a subsequent purchaser rule that prohibits subsequent purchasers from asserting construction defect claims. With this consideration in mind, the trial court went through the claims the plaintiff, as a subsequent purchaser, asserted against the manufacturer to determine whether they were viable claims as a matter of law.
Negligence Claim
The trial court found that a subsequent purchaser could sue in negligence. “Florida courts have long allowed subsequent purchasers to sue for negligence including in construction defect litigation.” Karpel, supra, at *2.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
SFAA and Coalition of Partners Encourage Lawmakers to Require Essential Surety Bonding Protections on All Federally-Financed Projects Receiving WIFIA Funds
February 21, 2022 —
The Surety & Fidelity Association of AmericaFebruary 17, 2022 (WASHINGTON, DC) – The Surety & Fidelity Association of America (SFAA) in collaboration with 15 trade associations, sent a letter strongly encouraging members of the Senate Environment and Public Works Committee, led by Chairman Tom Carper (D-DE) and Ranking Member Shelly Moore Capito (R-WV), to require payment and performance protections on federally-financed infrastructure projects receiving Water Infrastructure Finance and Innovation Act (WIFIA) loans, including public-private projects (P3s).
“As the Environment and Public Works Committee looks at legislation in the second session of the 117th Congress to continue the important work of addressing our nation’s water infrastructure, we urge the Committee to amend the Water Infrastructure Finance and Innovation Act (WIFIA) program to help protect taxpayer funds, workers, subcontractors and suppliers, including Small and Disadvantaged Business Enterprise (DBE) Program participants and subcontractors, who build water infrastructure especially in at-risk low income communities,” said Lee Covington, president and CEO, SFAA.
The coalition of partners includes:
American Property and Casualty Association
American Subcontractor Association
Business Coalition for Fair Competition
Council of Insurance Agents and Brokers
Finishing Contractors Association International
International Union of Operating Engineers
Mechanical Contractors Association of America
National Association of Electrical Contractor
National Association of Minority Contractors
National Association of Mutual Insurance Companies
National Association of Surety Bond Producers
Sheet Metal and Air Conditioning Contractors’ National Association
The Association of Union Constructors
The Construction Employers of America
Women Construction Owners and Executives
The Surety & Fidelity Association of America (SFAA) is a nonprofit, nonpartisan trade association representing all segments of the surety and fidelity industry. Based in Washington, D.C., SFAA works to promote the value of surety and fidelity bonding by proactively advocating on behalf of its members and stakeholders. The association’s more than 450 member companies write 98 percent of surety and fidelity bonds in the U.S. For more information visit www.surety.org.
Read the court decisionRead the full story...Reprinted courtesy of
Important Information Regarding Colorado Mechanic’s Lien Rights.
November 07, 2012 —
David McLain, Colorado Construction LitigationWith payment problems in the construction economy having accelerated over the past few years, there has been a substantial increase in mechanic’s lien activity and associated litigation. The typical mechanic’s lien claimant is a material supplier, a trade subcontractor, or even a general contractor that has not been paid by the developer/owner of the construction project. The reason for filing a mechanic’s lien claim is that it offers the prospect in many cases to make the unpaid construction professional a priority creditor, with a lien on the real estate that is superior to the construction lender.
One of the primary rules governing a mechanic’s lien claim is that the creditor’s formal written “Notice of Intent to File a Mechanic’s Lien” (hereafter “Lien Notice”) must be (1) served on the owner of the property for which the work was done or the materials used, and (2) served at the same time on the general contractor who has handled the construction project. After the creditor has made service of the lien claim by USPS certified mail (using the green return receipt card for proof of service) or separate personal delivery of the notice to the property owner and general contractor, ten full days must pass (not including the date of mailing of the notices) before the lien notice is filed in the public records.
After ten days have expired following the date of mailing using certified mail, or personal delivery of the notice to the property owner and the general contractor, the lien notice can be filed to make the lien valid.
Read the court decisionRead the full story...Reprinted courtesy of
David M. McLain, Higgins, Hopkins, McLain & Roswell, LLC.Mr. McLain can be contacted at
mclain@hhmrlaw.com
Builder’s Be Wary of Insurance Policies that Provide No Coverage for Building: Mt. Hawley Ins. Co v. Creek Side at Parker HOA
May 01, 2014 —
David M. McLain – Higgins, Hopkins, McLain & Roswell, LLCOn the heels of a recent order regarding coverage under a Comprehensive General Insurance policy issued by Mt. Hawley Insurance Company (“Mt. Hawley”), builders should be very wary of CGL policies providing no coverage for property damage.
On January 8, 2013, District Court Judge R. Brooke Jackson granted a motion for declaratory judgment filed by Mt. Hawley. The order states that the subject insurance policies issued by Mt. Hawley to Mountain View Homes II, LLC (“MV Homes”), the builder developer of the Creek Side at Parker development (the “Project”), did not provide coverage for any of the work performed by MV Homes or its subcontractors on the Project.
MV Homes originally began construction on the Project in 2002 and completed construction in 2005. MV Homes was insured by National Fire and Marine Insurance Company (“National Fire”) and Mt. Hawley. In December 2008, Creek Side at Parker Homeowners Association, Inc. (“the HOA”) served notice on MV Homes. The HOA then instituted a construction defect lawsuit on June 1, 2009 against MV Homes and others. MV Homes initially demanded a defense and indemnity from National Fire, which provided a defense. Then, after two years, MV Homes demanded a defense and indemnity from Mt. Hawley in July 2011. Mt. Hawley denied coverage and did not provide a defense. The case was settled soon after, and National Fire reserved or assigned claims against Mt. Hawley.
Read the court decisionRead the full story...Reprinted courtesy of
David M. McLain, Higgins, Hopkins, McLain & Roswell, LLCMr. McLain may be contacted at
mclain@hhmrlaw.com
ASCE Statement on House Passage of Infrastructure Investment and Jobs Act
November 15, 2021 —
American Society of Civil EngineersThe following is a statement by Dennis D. Truax, P.E., President, American Society of Civil Engineers (ASCE):
WASHINGTON, DC. – It is a great day for the nation as the U.S. House of Representatives passed the Infrastructure Investment and Jobs Act (IIJA), fulfilling President Biden's vision with a historic piece of legislation that will have monumental impacts on the economy, public safety, global competitiveness, and each American's well-being. Passage of this five-year, $1.2 trillion bill proves once again that the country can lead with infrastructure.
With this legislation, the federal government will restore their critical partnership with cities and states to modernize our nation's roads, bridges, transit systems, drinking water pipes, school facilities, broadband, ports, airports and more. Without a strong federal partner, local projects that are community lifelines have hung in the balance, oftentimes being paused or outright cancelled due to funding uncertainties. When this happens, American households and businesses are the ones who pay the price.
The IIJA is the culmination of decades of advocacy by American Society of Civil Engineers (ASCE) members who worked tirelessly to educate Congress about the role infrastructure plays in supporting the economy and our quality of life. ASCE's Infrastructure Report Cards have sounded the alarm on our nation's infrastructure conditions since 1998, with new reports being released every four years. While all categories of infrastructure have been the cause of some concerns, the common denominator behind each category's struggles has been a backlog of projects, overdue maintenance, and a need for resilience. This bill includes investments to repair and modernize these critical assets for almost all of the 17 categories in the 2021 Report Card for America's Infrastructure, which assigned our nation's infrastructure a cumulative grade of 'C-'.
ABOUT THE AMERICAN SOCIETY OF CIVIL ENGINEERS
Founded in 1852, the American Society of Civil Engineers represents more than 150,000 civil engineers worldwide and is America's oldest national engineering society. ASCE works to raise awareness of the need to maintain and modernize the nation's infrastructure using sustainable and resilient practices, advocates for increasing and optimizing investment in infrastructure, and improve engineering knowledge and competency. For more information, visit www.asce.org or www.infrastructurereportcard.org and follow us on Twitter, @ASCETweets and @ASCEGovRel.
Read the court decisionRead the full story...Reprinted courtesy of
Preliminary Notice Is More Important Than Ever During COVID-19
June 01, 2020 —
Christopher G. Hill - Construction Law MusingsFor this week’s Guest Post Friday here at Construction Law Musings, we welcome Justin Gitelman. Justin is the Content Coordinator at Levelset, where over 500,000 contractors and suppliers connect on a cloud-based platform to make payment processes stress-free. Levelset helps contractors and suppliers get payment under control, and sees a world where no one loses a night’s sleep over payment.
As the construction industry continues to adjust to the coronavirus and an uncertain future, contractors are struggling to get paid. During the COVID-19 pandemic, construction businesses across Virginia need to do everything they can to protect their payments, and get paid faster. One simple action that can help fight payment delays: sending preliminary notice on every job.
Subcontractors and suppliers should send preliminary notices out to the GC, project owner, and/or lender at the start of every single project. These tools allow contractors to make themselves visible on crowded job sites, helping contractors get paid more quickly, and, in some cases, securing their right to file a mechanics lien or bond claim.
Preliminary Notices in Construction
The purpose of a preliminary notice is to allow each member of a construction project to know who you are and what work you’ll be performing. With coronavirus in mind, contractors can use preliminary notices to remind the hiring party of their payment expectations. When you submit a preliminary notice on every project, you’ll have legal protection in your corner while also giving yourself a greater opportunity to get paid.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrissghill@constructionlawva.com
A General Contractor’s Guide to Additional Insured Coverage
August 10, 2017 —
Gregory D. Podolak - Saxe Doernberger & Vita, P.C.LAW360.com recently surveyed attorneys to offer tips for what general contractors should – and shouldn’t – do when pursuing additional insured coverage. According to the article, “With the broad array of risks present on a typical construction site, one of a general contractor’s top options to shield itself from liability for property damage and bodily injury claims is to secure expansive “additional insured” coverage through its subcontractors.”
In the piece, Greg Podolak discussed techniques for avoiding potential gaps in coverage:
“Carriers will try to say in the additional insured endorsement that they will only be responsible to provide limits for what is required in the trade contract,” said Greg Podolak, managing partner of Saxe Doernberger & Vita PC’s southeast office. “If it turns out the trade contract requires lower limits than the policy, the insurer will likely say it only wants to be responsible for those lower limits.”
Read the court decisionRead the full story...Reprinted courtesy of
Gregory D. Podolak, Saxe Doernberger & Vita, P.C.Mr. Podolak may be contacted at
gdp@sdvlaw.com