Appeals Court Upholds Decision by Referee in Trial Court for Antagan v Shea Homes
May 10, 2012 —
CDJ STAFFIn the case Antangan v. Shea Homes Ltd. Partnership (Cal. App., 2012), Plaintiffs appealed “an order vacating a judgment and entering a modified judgment in their construction defect action against defendants Shea Homes, Inc. and Shea Homes Limited Partnership,” while the Defendant, Shea Homes Limited Partnership (Shea Homes) appealed “an order of the judicial referee denying its motion to strike and tax costs.”
On the Antagon issue, the appeals court concluded that “the trial court did not err by vacating and modifying its judgment so that the cost of referee’s fees would be equally divided by the parties and consistent with a prior stipulation they filed in court.”
On the Shea Homes issue, the appeals court concluded: “1) the judicial referee did not err by ruling that plaintiffs’ offers to compromise (§ 998) were validly served on Shea Homes’ counsel, 2) the offers substantially complied with statutory requirements, 3) the offers were not required to be apportioned, and 4) the referee’s award of $5,000 as costs for a person assisting plaintiffs’ counsel was not an abuse of discretion.” The appeals court affirmed the judgment.
Here is a brief history of the trial case: “Plaintiffs Chito Antangan, Jimmy Alcova and other homeowners brought an action against defendants Shea Homes, Inc. and Shea Homes Limited Partnership for damages alleging that the properties they purchased from these ‘developer defendants’ were defective. Plaintiffs claimed numerous construction defects required them ‘to incur expenses’ for ‘restoration and repairs’ and the value of their homes had been diminished.”
In response, Shea Homes filed a motion for an order to appoint a judicial referee. The motion was granted and it was ruled that “a referee would ‘try all issues’ and ‘report a statement of decision to this court.’”
On May 10, 2010 the judicial referee (Thompson) “awarded plaintiffs damages and various costs, and ruled that ‘Shea Homes shall bear all of the Referee’s fees.’” The latter ruling would become a matter for contention later on.
In July of 2010, the plaintiffs “sought, among other things, $54,409.90 for expert fees, and $14,812.50 for the services of Melissa Fox for ‘exhibit preparation & trial presentation.’ Shea Homes filed a motion to strike and/or tax costs claiming: 1) Fox was a paralegal, 2) plaintiffs were not entitled to attorney’s fees, and 3) the fees for Fox’s services were an indirect and improper method to obtain attorney’s fees. The referee disagreed and awarded $5,000 for Fox’s services. The referee also ruled that plaintiffs had properly served valid offers to compromise (§ 998) on Shea Homes’ counsel in 2009. He said those offers to defendants in the case at that time did not have to be apportioned.”
“Antangan contends the trial court erred when it vacated and modified its original judgment, which ordered Shea Homes to pay all the referee’s fees. We disagree.”
Antagon contended that the trial court erred when it vacated and modified its original judgment regarding Shea Homes paying the referee’s fees. The appeals court disagreed: “A trial court has inherent authority to vacate or correct a judgment that is void on its face, incorrect, or entered by mistake. (§ 473; Rochin v. Pat Johnson Manufacturing Co. (1998),67 Cal.App.4th 1228; Olivera
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
Maryland Court Affirms Condo Association’s Right to Sue for Construction Defects
November 27, 2013 —
CDJ STAFFThe Maryland Court of Appeals, that state’s highest court, recently reaffirmed that condominium association have broad discretion in suing for construction defects in when they are representing at least two unit owners. Nicholas D. Cowie of the Baltimore-based construction defect legal firm Cowie & Mott, gives his summary of the case on his firm’s web site.
Mr. Cowie notes that the Council of Unit Owners of Bentley Place Condominium sued the developer and builder for construction defects in both common areas and within units, representing itself and “two or more” unit owners. A jury awarded $6.6 million; the builder and developer appealed.
The court ruled on the appeal that the Council of Unit Owners had a right to pursue these claims, and could recover full damage to common elements, even if some owners are time-barred due to their date of purchase. Mr. Cowie represented the Council of Unit Owners during the lawsuit.
Read the court decisionRead the full story...Reprinted courtesy of
Payment Bond Claim Notice Requires More than Mailing
June 18, 2019 —
Christopher G. Hill - Construction Law MusingsIt’s been a while since I posted something new relating to Virginia’s “Little Miller Act” and its various notice requirements for a subcontractor to make a payment bond claim.
I have posted on the basics of a Virginia payment bond claim previously here at Musings. One of these basics is the 90 day notice requirement for suppliers or second tier subcontractors with no direct contractual relationship to the general contractor. A recent case from the Norfolk, Virginia Circuit Court examined when notice is “given” under the Little Miller Act.
In R T Atkinson Building Corp v Archer Western Construction, LLC the Court looked at the question of whether mailing of the notice of claim is enough to constitute notice being “given” in a manner that would satisfy the statutory requirements. In that case, the supplier mailed the notice within the 90 day window, but the defendant argued on summary judgment that it did not receive the notice until 2 days after the 90 day window had closed. In support of this contention, the defendant provided tracking information showing delivery by the USPS on the non-compliant date.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Reporting Requirements for Architects under California Business and Professions Code Section 5588
December 22, 2019 —
Jordan Golden - Gordon & Rees Construction Law BlogBelow is an overview of the changes to California Business and Professions Code Section 5588 and its effect on the reporting requirements, for architects, in the construction industry.
Section 5588 Prior to 2005 Legislative Changes
Section 5588 of the California Business and Professions Code sets forth the reporting requirements for many business professionals including architects. Since 1979, Section 5588 has required architects and their insurers to report to the California Architect Board (the Board) “any settlement or arbitration award in excess of five thousand dollars ($ 5,000) of a claim or action for damages caused by the license holder’s fraud, deceit, negligence, incompetency, or recklessness in practice.”1
The language of the code section left open for interpretation the question of what types of settlement claims must be reported to the Board. Thus, in 2004, the Attorney General of the State of California published an opinion stating that a reportable settlement includes “any agreement resolving all or part of a demand for money which is based upon an insured architect’s alleged wrongful conduct.”2 He then went on to conclude that the only qualifications placed on the term “claim” for purposes of Section 5588 is that “(1) the demand be premised on the license holder’s alleged ‘fraud, deceit, negligence, incompetency, or recklessness in practice,’ and (2) the value of the claim, as measured by the settlement amount or arbitration award, exceeds $5,000.”3
Read the court decisionRead the full story...Reprinted courtesy of
Jordan Golden, Gordon & Rees Scully Mansukhani
Judge Rejects Extrapolation, Harmon Tower to Remain Standing
November 07, 2012 —
CDJ STAFFCityCenter has filed an emergency motion asking the Nevada Supreme Court to intervene in Judge Elizabeth Gonzalez’ order that the building’s defects cannot be extrapolated from those tested. CityCenter’s structural engineering expert “evaluated 397 of the Harmon’s critical structural elements and found all but one defective,” according to the article on Vegas.Inc. Judge Gonzalez would not permit this to be extrapolated to the untested 1,072, as the locations tested were not random.
Judge Gonzalez also ruled that if CityCenter does additional testing, they may not appeal her order that ruled the extrapolation inadmissible. CityCenter argued to the Nevada Supreme Court that “the notion that CityCenter should be forced to incur additional millions of dollars in testing costs and sanctions – on the condition that it waive its right to appeal this ruling – just to be permitted to present its own damages evidence, shocks the conscience.”
Gonzalez gave the okay to CityCenter to demolish the building, but its demolition would make any further testing impossible. Under Gonzalez’ ruling, the untested structural elements cannot b assumed to be defective.
Read the court decisionRead the full story...Reprinted courtesy of
Industry Groups Decry Jan. 6 Riot; DOT Chief Chao Steps Down in Protest
January 11, 2021 —
Aileen Cho & Pam Radtke Russell - Engineering News-RecordIndustry and business groups and labor unions universally denounced the actions of rioters who broke into the U.S. Capitol on Jan. 6, with statements going as far as calling for President Donald Trump to step down but others taking a more measured response.
Reprinted courtesy of
Aileen Cho, Engineering News-Record and
Pam Radtke Russell, Engineering News-Record
Ms. Cho may be contacted at choa@enr.com
Ms. Russell may be contacted at Russellp@bnpmedia.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Ohio Supreme Court Case to Decide Whether or Not to Expand Insurance Coverage Under GC’s CGL Insurance Policies
August 14, 2018 —
David Suggs – Bert L. Howe & Associates, Inc.According to W. Matthew Bryant of Saul Ewing Arnstein & Lehr LLP, the Ohio Supreme Court will be deciding whether or not a general contractor's commercial general liability ("CGL") insurance policy may provide coverage for damage caused by a subcontractor's defective construction work.
Bryant explained the status quo in Ohio: “Since 2012, Ohio has followed the rule that a CGL policy would not cover damage caused by a contractor to the contractor's own work.” That could change depending on how the Ohio Supreme Court rules in an upcoming case: “The Ohio Supreme Court will decide whether to affirm or overturn Ohio Northern University v. Charles Construction Services, Inc., 77 N.E.3d 538 (Ohio Ct. App. 2017) ("ONU"), an Ohio Court of Appeals decision holding that CGL coverage may exist for property damage caused by faulty work performed by the subcontractor of an insured general contractor.”
Read the court decisionRead the full story...Reprinted courtesy of
Fourth Circuit Holds that a Municipal Stormwater Management Assessment is a Fee and Not a Prohibited Railroad Tax
April 22, 2019 —
Anthony B. Cavender - Gravel2GavelOn February 15, the U.S. Court of Appeals for the Fourth Circuit decided Norfolk Southern Railway Co. v. City of Roanoke, et al.; the Chesapeake Bay Foundation was an Intervenor-Defendant. The Fourth Circuit held that a large stormwater management fee (stated to be $417,000.00 for the year 2017) levied by the City of Roanoke against the railroad to assist in the financing of the City’s permitted municipal stormwater management system was a permissible fee and not a discriminatory tax placed on the railroad.
The Railroad Revitalization and Regulatory Reform Act of 1976 specifically provides that states and localities may not impose any tax that discriminates against a rail carrier, 49 U.S.C. § 11501. Accordingly, the issue confronting the Fourth Circuit was whether the assessment was fee and not a tax.
Read the court decisionRead the full story...Reprinted courtesy of
Anthony B. Cavender, PillsburyMr. Cavender may be contacted at