Construction Lien Waiver Provisions Contractors Should Be Using
January 06, 2020 —
Jason Lambert - Construction ExecutiveIt is common in construction for a subcontractor or material supplier of any tier to be required to provide a lien waiver when receiving payment. But not all lien waivers are created equal. While at a minimum, a lien waiver, by definition, needs to include a release of liens, it can also include many other terms that can tie up loose ends or resolve potential problems before they begin.
Additional Releases
A typical lien release is going to release any liens and right to claim liens on the subject property. But a lien waiver can also include releases of any claims against surety bonds, other statutory rights or claims, and at its broadest, claims against the paying party. One example of a provision that could help accomplish this is a release of “any right arising from a payment bond that complies with a state or federal statute, any common law payment bond right, any claim for payment, and any rights under any similar ordinance, rule, or statute related to claim or payment rights.” Broad release language can also be used to effectively preclude any claims arising prior to the date of the release.
Payment Representations and Warranties
A typical lien release has no representations or warranties about payment to subcontractors or material suppliers of a lower tier. But contractors can include language requiring the company receiving payment to represent and warrant that all subcontractors of a lower tier have been paid or will be paid within a certain timeframe using the funds provided and that these are material representations and inducements into providing payment. On a related note, if the contract requires subcontractors to provide lien releases from lower tier subcontractors in addition to their own release when seeking payment, contractors can require the sub-subcontractor releases to include representations that they have been paid by the subcontractor to try and tie up payment loose ends all around.
Reprinted courtesy of
Jason Lambert, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Mr. Lambert may be contacted at
jason.lambert@nelsonmullins.com
With VA Mechanic’s Liens Sometimes “Substantial Compliance” is Enough (but don’t count on it)
August 10, 2017 —
Christopher G. Hill - Construction Law MusingsVirginia mechanic’s liens are a powerful and tricky beast that in most cases require absolute precision in their preparation. However, an interesting opinion recently came out of the Virginia Supreme Court that may provide a bit of a “safe harbor” from the total form over function nature of a mechanic’s lien.
In Desai, Executrix v. A.R. Design Group Inc., the Court considered a lien memorandum that had what could be described as technical flaws in the preparation of the mechanic’s lien by A. R. Design Group. The basic facts are that A. R. Design Group used the form of lien found in Va. Code Sec. 43-5 (also found as Form CC-1512 at the Virginia Judiciary website) when it recorded two lien memoranda for two pieces of property owned by a trust. Relating to one of the two properties, the memorandum failed to identify the “Owner” as the trustee of the trust. On the memoranda relating to both properties the affidavit verifying the amounts claimed did not identify the signatory as agent for A. R. Design Group, instead listing the agent as the claimant and further failed to state a date from which interest is claimed or a date on which the debt was due.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Insurers Can Sue One Another for Defense Costs on Equitable Indemnity and Equitable Contribution Basis
March 21, 2022 —
Garret Murai - California Construction Law BlogSince I don’t do insurance defense work, fights between insurers isn’t something I have to deal with. It’s good sport nonetheless. In the next case, Travelers v. Navigators Specialty Insurance Company, Case No. D078852 (October 15, 2021), three of the biggies – Travelers, Navigators and Mt. Hawley – got into it over indemnity.
The Travelers Case
General contractor TF McGukin, Inc. was involved in a construction defect lawsuit with respect to a condominium project. TFM entered into subcontracts with several subcontractors including F&F Steel and Stairway, Inc and Calvac Paving which required the subcontractor to defend and indemnify TFM against any claims arising out of the subcontractor’s work. The subcontracts also required the subcontractors to name TFM as an additional insured.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
Design-build Trends, Challenges and Risk Mitigation
August 26, 2019 —
Bill Webb - Construction ExecutiveAs the commercial construction industry continues to evolve and grow, design-build methodologies are becoming increasingly popular for their ability to speed completion rates, control costs and produce an overall more efficient process under the guidance of the design-build contractor (DBC).
The Design-Build Institute of America (DBIA) predicts that “over half of owners have already or will use design-build in the next five years” due to the opportunities it provides for innovation and fast-tracking projects. The organization also expects that design build methodologies will account for approximately 45% of all nonresidential construction spending over the 2018 – 2021 forecast period.
Design-build provides many benefits to projects owners, however, holding contractual responsibility for both design and construction does accompany its fair share of challenges and risks for the DBC. Although basic risk management principles are inherent to design build through improved communication and collaboration, strong contractual language and proper insurance programs can greatly control risk exposures.
Reprinted courtesy of
Bill Webb, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Mr. Webb may be contacted at
Bill.Webb@rtspecialty.com
Muir named Brown and Caldwell Eastern leader
January 09, 2023 —
Brown and CaldwellHARTFORD, Conn., Jan. 04, 2023 — Leading environmental engineering and construction services firm Brown and Caldwell today announces Senior Vice President Eric Muir has been promoted to leader of its growing Eastern business.
The largest of the company's regions with over 40 offices east of the Mississippi River, the Eastern business consists of clients in the water, wastewater, stormwater, environmental services, and water resources sectors.
Muir has a 20-year background in delivering highly technical civil and environmental engineering projects. He has held leadership and technical roles on some of the most complex projects encompassing water and wastewater treatment, distribution and collection, pumping, and conveyance systems. His experience includes master planning, detailed design, permitting, and construction services.
Since joining Brown and Caldwell in 2018, Muir's business development expertise and client-centric focus have played a key role in setting the company's regional strategic direction to achieve strong financial results.
"Eric is a highly strategic and inclusive leader, passionate about mentoring employees to reach their full potential," said Brown and Caldwell Chief Operating Officer Euan Finlay. "His deep knowledge of clients' environmental obstacles will enhance the positive impacts our teams have on the communities we serve."
Based in Connecticut, Muir will manage overall operations and lead the implementation of the firm's strategy in the East. He will continue the region's growth and lead efforts to make Brown and Caldwell the company of choice for clients, employees, and partners. He will work alongside regional leadership to align the firm's talent pool with clients to provide innovative, cost-effective solutions to challenges related to water quality, biosolids management, and aging infrastructure.
About Brown and Caldwell
Headquartered in Walnut Creek, California, Brown and Caldwell is a full-service environmental engineering and construction services firm with 52 offices and 1,800 professionals across North America and the Pacific. For 75 years, our creative solutions have helped municipalities, private industry, and government agencies successfully overcome their most challenging water and environmental obstacles. As an employee-owned company, Brown and Caldwell is passionate about exceeding our clients' expectations and making a difference for our employees, our communities, and our environment. For more information, visit www.brownandcaldwell.com
Read the court decisionRead the full story...Reprinted courtesy of
M&A Representation and Warranty Insurance Considerations in the Wake of the Coronavirus Pandemic
April 06, 2020 —
Lori Smith & Patrick Devine - White and Williams Taking Care of Business BlogIncreasingly, M&A transactions are using representation and warranty insurance (RWI) to bridge the gap between a buyer’s desire for adequate recourse to recover damages arising out of breach of representations in the purchase agreement and a seller’s desire to minimize post-closing risk and holdbacks or purchase price escrows traditionally used as the means to satisfy such obligations. When it works, RWI provides a significant benefit to both parties: it mitigates the buyer’s risk in the event that the seller’s representations and warranties prove untrue, and it permits the seller to reduce the portion of the purchase price that it would otherwise have to leave in escrow to cover future claims for breach of those representations and warranties. However, as the coronavirus pandemic ravages the global economy, insurers are now expressly adding COVID-19 exclusions to their RWI policies. If RWI insurers decline coverage for these losses, the allocation of risk in the representations and warranties (and related indemnity provisions) will be more critical than the parties contemplated when they negotiated the transaction documents.
Unlike in the case of a natural disaster, insurers cannot quantify the economic fallout that may result from the coronavirus pandemic. This uncertainty breeds systemic concern about the number of insurance claims that covered parties of all varieties will bring, which in turn creates an industry-wide reluctance to cover the claims. Based on discussions with market participants, we understand that, at the present time, 70% to 80% of RWI insurers are broadly excluding losses resulting from COVID-19 and similar viruses, epidemics, and pandemics (including government actions in response thereto), 5% to 10% are narrowly excluding specific coronavirus-related losses that are more likely to be implicated in a particular transaction (e.g., losses caused by business interruption), and 10% to 15% may be willing to narrow their exclusions upon completion of the underwriting process, depending on their comfort level after conducting rigorous and heightened diligence. Insurers’ concerns are wide-ranging, but the representations and warranties causing the greatest distress appear to be those regarding customer retention, supply chain matters, undisclosed liabilities, and the absence of changes between the date of the seller’s most recent financial statements and the transaction closing date.
Reprinted courtesy of
Lori Smith, White and Williams and
Patrick Devine, White and Williams
Ms. Smith may be contacted at smithl@whiteandwilliams.com
Mr. Devine may be contacted at devinep@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of
Federal Court Enforces “Limits” and “Most We Will Pay” Clauses in Additional Insured Endorsement
September 13, 2021 —
Craig Rokuson - Traub Lieberman Insurance Law BlogIn the recent case of Zurich Am. Ins. Co. v. XL Ins. Am., Inc., 20-CV-4614 (LJL), 2021 WL 3617218 (S.D.N.Y. Aug. 16, 2021), the United States District Court for the Southern District of New York—in deciding a motion for consideration—had occasion to review the 2013 ISO changes to the additional insured endorsement, and held that coverage under a policy providing additional insured coverage was limited to the $1,000,000 required by contract, and not the $2,500,000 limit to the policy.
In Zurich, Zurich and its named insured D.A. Collins sought the full limits of the primary policy issued by XL to the D.A. Collins’ subcontractor, HBI, which are $2,5000 per occurrence and in the aggregate, for an underlying personal injury lawsuit. XL also issued an excess policy in the amount of $5,000,000 to HBI.
The contract between D.A. Collins and HBI required HBI to obtain commercial liability coverage “in an amount of $1,000,000 per occurrence and $2,000,000 in the aggregate. It further provides that the “required limits for the umbrella excess coverage shall be sufficient to provide a total of $5,000,000 per occurrence/aggregate.”
Read the court decisionRead the full story...Reprinted courtesy of
Craig Rokuson, Traub LiebermanMr. Rokuson may be contacted at
crokuson@tlsslaw.com
When Cyber Crooks Steal Payments, Think Insurance Makes Up The Loss? Think Again.
November 18, 2024 —
Richard Korman - Engineering News-RecordIn Summer 2023, the payment system for a small office and warehouse project that Beck Properties was developing for itself in South St. Paul, Minn., seemed to be running smoothly. Emails were criss-crossing back and forth and paper checks were landing in mailboxes.
Reprinted courtesy of
Richard Korman, Engineering News-Record
Mr. Korman may be contacted at kormanr@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of