Pennsylvania Supreme Court Dismisses Appeal of Attorney Fee Award Under the Contractor and Subcontractor Payment Act
February 16, 2016 —
William J. Taylor – White and Williams LLPIn late December, the Supreme Court of Pennsylvania dismissed, as improvidently granted, the appeal in Waller Corporation v. Warren Plaza, Inc., No. 6 WAP 2015 (December 21, 2015). As a result, the Superior Court’s holding in that case that there is no good faith exception to the attorney fee provision of the Pennsylvania Contractor and Subcontractor Payment Act (CASPA), 73 P.S. §§ 501-516, remains intact.
In its decision in Waller, 95 A.3d 313 (Pa. Super. 2014), the Superior Court considered if there was a “good faith” exception to the interest and penalties provision of CASPA, 73 P.S. § 512(a), and whether there was a similar good faith exception to the attorney fee provision of the statute, 73 P.S. § 512(b). The court held that while an award of interest and penalties under § 512(a) could be denied if a party had a good faith basis for withholding payments due under a construction contract, no such exception exists for an award of attorney fees under § 512(b). Rather, an award of attorney fees is appropriate for the “substantially prevailing party” under a CASPA claim, and a claimant can be the substantially prevailing party even if the other party withheld payments in good faith.
Read the court decisionRead the full story...Reprinted courtesy of
William J. Taylor, White and Williams LLPMr. Taylor may be contacted at
taylorw@whiteandwilliams.com
Corps of Engineers to Prepare EIS for Permit to Construct Power Lines Over Historic James River
May 01, 2019 —
Anthony B. Cavender - Gravel2GavelOn March 1, the U.S. Court of Appeals for the District of Columbia decided National Parks Conservation Assoc. v. Todd T. Simonite, Lieutenant General, et al. The case involves an application to the U.S. Army Corps of Engineers (Corps) for a construction permit to build electric power lines over the “historic James River, from whose waters Captain John Smith explored the New World.”
The Corps concluded after reviewing the thousands of comments submitted to it in connection with this application, and after considering the views of several government agencies and conservation groups, that an Environment Impact Statement (EIS) was not required, and that its Environmental Assessment assured the Corps that the project would not result is significant environmental impacts. The Court of Appeals has concluded that, based on this evidence, the Corps’ refusal to prepare an EIS thoroughly discussing all these points was arbitrary and capricious. The Corps has been ordered to prepare the EIS and to take special note of its obligations under the National Environmental Protection Act (NEPA), the Clean Water Act (CWA) and its obligations under the National Historic Preservation Act.
Read the court decisionRead the full story...Reprinted courtesy of
Anthony B. Cavender, PillsburyMr. Cavender may be contacted at
anthony.cavender@pillsburylaw.com
Minneapolis Condo Shortage Blamed on Construction Defect Law
November 20, 2013 —
CDJ STAFFDemand for condos in the Minneapolis, Minnesota area is outstripping demand. Currently inventory of available condos represents less than four months’ worth of sales. But despite the demand, only three condominium buildings are under construction in the Minneapolis metropolitan area.
Some blame this on difficulty in finding financing, where some lenders are looking for projects to be sold before the builders get the money to build what they’ve just sold. Another problem is Minnesota construction defect law. “There are law firms in this town that have filed lawsuit after lawsuit on behalf of homeowners associations alleging construction defects,” said one builder, Kelly Doran, who now builds luxury apartment buildings. “”With that 10-year warranty, there’s no way I would build condos.”
Read the court decisionRead the full story...Reprinted courtesy of
Arguing Cardinal Change is Different than Proving Cardinal Change
April 05, 2021 —
David Adelstein - Florida Construction Legal UpdatesThe cardinal change doctrine has become a popular doctrine for a contractor to argue under but remains an extremely difficult doctrine to support and prove. Arguing cardinal change is one thing. Proving cardinal change is entirely different. As shown below, this is a doctrine with its origins under federal government contract law with arguments extending outside of the federal government contract arena. For this reason, the cases referenced below are not federal government contract law cases, but are cases where the cardinal change doctrine has been argued (even though these cases cite to federal government contract law cases).
A party argues cardinal change to demonstrate that the other party (generally, the owner) materially breached the contract based on the cardinal change. In reality, a party argues cardinal change because they have cost overruns they are looking to recover and this doctrine may give them an argument to do so. But it is important to recognize the distinction between raising it as an argument and the expectation that this (difficult doctrine to prove) will carry the day.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Defeating the Ten-Year Statute of Repose For Latent Construction Defects
January 28, 2015 —
The Porter Law GroupIt is an all-too-common scenario in California construction: Nine and a half years after completion of a major California construction project, immediately before the 10-year “statute of repose” for suing on “latent” construction defects expires, a lawsuit claiming damages for “recently discovered” latent construction defects is filed. The property owner sues the contractor for the alleged defects. The direct contractor sues all its subcontractors for indemnity and defense. The attorneys spontaneously generate. Experts proliferate. Claimed defects are extrapolated. Four or five years later, after a few dozen attorneys earn a small fortune in fees, the insurance companies make payments. Attorneys collect more fees. The owners take what remains. They repair nothing... and buy vacation homes.
Perhaps a cynical view, but there are many in the construction defect world who would reach a similar conclusion. The question is: How can you defeat this seemingly inevitable chain of events? Under a case known as Brisbane Lodging L.P. v. Webcor Builders, Inc. 216 Cal.App 4th 1249 (2013) there may be hope. California Code of Civil Procedure sections 337.1 and 337.15 grant a 10-year “statute of repose” for bringing claims for “latent” construction defects. These statutes allow a lawsuit for such claimed defects to be filed in court up until ten years after the project has been completed. Latent defects are generally defined as those which are “not apparent by reasonable inspection” (CCP §337.15(b)). It is extremely common for such claims to be filed immediately before this 10-year deadline expires. When the lawsuit is brought, the cash register begins to ring.
Read the court decisionRead the full story...Reprinted courtesy of
The Porter Law Group
Seventh Circuit Confirms Additional Insured's Coverage for Alleged Construction Defects
August 10, 2017 —
Tred R. Eyerly - Insurance Law HawaiiThe Seventh Circuit held that the underlying complaint alleged an occurrence by asserting that the painting subcontractor was negligent in causing damage to the building. Westfield Ins. Co. v. Nat'l Decorating Serv., Inc., 2017 U.S. App. LEXIS 12516 (7th Cir. July 13, 2017).
McHugh Construction, the general contractor for construction of a 24 story condominium building in Chicago, retained National Decorating Service, Inc. as a subcontractor to perform all of the painting work. This meant National Decorating would paint the exterior of the building with a protective coating that was a waterproof sealant.
After completion, the building's board of managers sued McHugh, National Decorating, and others for damages resulting from faulty workmanship. The third amended complaint alleged: (1) significant cracking of the exterior concrete walls, interior walls, and ceilings; (2) significant leakage through the exterior concrete walls, balconies, and windows; (3) defects to the common elements of the building; and (4) damage to the interior ceilings, floors, interior painting, drywall, and furniture in the units.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly - Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Texas “your work” exclusion
January 06, 2012 —
CDCoverage.comIn American Home Assurance Co. v. Cat Tech, L.L.C., No. 10-20499 (5th Cir. Oct. 5, 2011), claimant Ergon hired insured Cat Tech to perform service on a reactor at Ergon’s refinery. During a start-up of the reactor after Cat Tech had completed its work, the reactor suffered damage. Cat Tech performed additional service and repairs. However, again upon start-up of the reactor, it suffered additional damage. Ergon hired another contractor to repair the reactor. Ergon initiated arbitration proceedings against Cat Tech. Cat Tech’s CGL insurer American Home defended Cat Tech against the Ergon arbitration under a reservation of rights.
Read the full story…
Reprinted courtesy of CDCoverage.com
Read the court decisionRead the full story...Reprinted courtesy of
Should I Pull the Pin? Contractor and Subcontractor Termination for Cause
January 26, 2017 —
Patrick McNamara - Porter Law GroupAny owner or general contractor who has a few projects under his or her belt has likely had this thought: “My contractor (or subcontractor) is not performing the way I expected; should I replace him?” The other side of the termination coin is: “This project is not going the way I expected; should I get out?”
While there may be an emotional high that immediately comes from terminating a contractor or subcontractor (or leaving a project, in mid-stream), there are many factors to be weighed, before making that decision.
Project Delay. Replacing a contractor or subcontractor that has already begun performance always results in delays to the project. Assessing the work in place, interviewing replacement contractors, and negotiating the terms of the new relationship can easily consume weeks, if not months of project time.
Read the court decisionRead the full story...Reprinted courtesy of
Patrick McNamara, Porter Law GroupMr. McNamara may be contacted at