"My Bad, I Thought It Was in Good Faith" is Not Good Enough - Contractor Ordered to Pay Prompt Payment Penalties
February 23, 2016 —
David A. Harris & Jesse M. Sullivan – Haight Brown & Bonesteel LLPRetention clauses are almost always included in California construction contracts and permit an Owner to withhold a portion of what is owed to the General Contractor as security to ensure the proper completion of the work. General Contractors pass the withholding of retention down to the subcontractors. Thus, if the subcontractor fails to complete its work, or fails to correct deficiencies, the Owner/General Contractor can use the retention to pay the costs of completing or correcting the subcontractor’s work.
The contractor must release any retention it receives from the owner within ten days unless a “good faith dispute exists between the direct contractor and the subcontractor.” (Civil Code section 8814.) Where there is a good faith dispute, the contractor “may withhold from the retention to the subcontractor an amount not in excess of 150 percent of the estimated value of the disputed amount.” (Civil Code section 8814(c).) If the contractor wrongfully withholds retention, it must not only pay the retention but must also pay the subcontractor “a penalty of 2 percent per month on the amount wrongfully withheld.” The contractor must also pay the subcontractor’s costs and reasonable attorney’s fees incurred in collecting the retention. (Civil Code section 8818.)
Reprinted courtesy of
David A. Harris, Haight Brown & Bonesteel LLP and
Jesse M. Sullivan, Haight Brown & Bonesteel LLP
Mr. Harris may be contacted at dharris@hbblaw.com
Mr. Sullivan may be contacted at jsullivan@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Florida Condos Bet on Americans Making 50% Down Payments
October 29, 2014 —
John Gittelsohn – BloombergJorge Perez crashed along with the real estate market, then regained his crown as Florida’s “Condo King” by building new projects with 50 percent deposits from foreign buyers. Now, for his next development, he’s looking to wealthy Americans.
In December, he’ll begin marketing the Auberge Beach Residences and Spa Fort Lauderdale, a $500 million oceanfront project 35 miles (56 kilometers) north of Miami. He expects as many as two-thirds of the buyers to come from the U.S. or Canada. All future owners must pay hefty deposits to finance construction by Perez’s Related Group, Fortune International Group and Fairwinds Group in a partnership that the companies plan to announce tomorrow.
“The U.S. buyers have made up an increasing share of luxury beachfront condominiums and, like our foreign buyers, they have shown little resistance to larger deposits,” Perez said in an e-mail. “Most feel that if they can’t put a 50 percent down payment, they probably should not be buying.”
Read the court decisionRead the full story...Reprinted courtesy of
John Gittelsohn, BloombergMr. Gittelsohn may be contacted at
johngitt@bloomberg.net
NTSB Issues 'Urgent' Recommendations After Mass. Pipeline Explosions
November 28, 2018 —
Tom Ichniowski – Engineering News-RecordThe National Transportation Safety Board has issued urgent safety recommendations in the wake of September’s natural-gas explosions and fires in the Merrimack Valley area of Massachusetts that killed one person and resulted in at least 21 others, including two firefighters, going to the hospital.
Read the court decisionRead the full story...Reprinted courtesy of
Tom Ichniowski, ENRMr. Ichniowski may be contacted at
ichniowskit@enr.com
Important Environmental Insurance Ruling Issued In Protracted Insurance-Coverage Dispute
May 16, 2018 —
Anthony B. Cavender - Gravel2Gavel Construction & Real Estate Law Blog The latest ruling in the long-running environmental insurance case, Olin Corporation v. Lamorak Ins. Co., was released on April 18, 2018, by Judge Rakoff of the U.S. District Court of the Northern District of New York. Judge Rakoff granted motions for summary judgment filed by Olin Corporation (Olin) and The London Market Insurers, and awarded Olin $55M for its claims against Lamorak Insurance Company (Lamorak).
As Judge Rakoff notes, “the overall litigation, having already outlived two federal judges, is now before the unlucky undersigned.” This ruling is in response to the Second Circuit’s most recent decision in Olin Corp. v. OneBeacon Americans Ins. Co.
Read the court decisionRead the full story...Reprinted courtesy of
Anthony B. Cavender, Pillsbury Winthrop Shaw Pittman LLPMr. Cavender may be contacted at
anthony.cavender@pillsburylaw.com
Construction Firm Settles Suit Over 2012 Calif. Wildfire
January 15, 2019 —
Associated Press - Engineering News-RecordSACRAMENTO, Calif. (AP) — Officials say a construction company and a logging firm have collectively agreed to pay $9 million for damages resulting from a 2012 wildfire that burned more than 1,600 acres of national forest land in Northern California.
The U.S. Attorney's office in Sacramento says Monday that the agreement settles a lawsuit brought by the federal government against Kernen Construction and Bundy & Sons Logging.
Read the court decisionRead the full story...Reprinted courtesy of
Engineering News-RecordENR may be contacted at
ENR.com@bnpmedia.com
Don’t Put All Your Eggs in the Silent-Cyber Basket
August 07, 2022 —
William P. Sowers, Jr. & Michael S. Levine - Hunton Insurance Recovery BlogThe Eastern District of Pennsylvania recently gave another reminder why cyber insurance should be part of any comprehensive insurance portfolio. In Construction Financial Administration Services, LLC v. Federal Insurance Company, No. 19-0020 (E.D. Pa. June 9, 2022), the court rejected a policyholder’s attempt to find coverage under its professional liability insurance for a social engineering incident that defrauded over $1 million.
Construction Financial Administrative Services, which goes by CFAS, disburses funds to contractors. One of its clients, SWF Constructors, was hacked, and a bad actor posing as the client asked CFAS to distribute $600,000 to a sham third party. John Follmer, an executive at CFAS and the only person authorized to approve distribution of funds, approved it. The next day, the bad actor, again posing as the client, asked Follmer to transfer an additional $700,000. Follmer approved that distribution too.
Reprinted courtesy of
William P. Sowers, Jr., Hunton Andrews Kurth and
Michael S. Levine, Hunton Andrews Kurth
Mr. Levine may be contacted at mlevine@HuntonAK.com
Read the court decisionRead the full story...Reprinted courtesy of
Practical Pointers for Change Orders on Commercial Construction Contracts
December 31, 2014 —
John E. Bowerbank - Newmeyer & DillionConstruction projects pose unique challenges, including keeping costs within budget, meeting project deadlines, and coordinating the work of numerous contractors and subcontractors in the wake of inevitable design revisions and changes to the plans. Anticipating potential project challenges and negotiating contract provisions before commencing work on a project is critical for all parties. Careful planning should reduce the number of contract disputes. This, in turn, can facilitate the completion of a project within budget and on schedule.
“Changes” Clauses in Construction Contracts
Most commercial construction contracts have a clause addressing changes to the contract. A “changes” clause typically requires the mutual agreement of the parties on the scope of any modifications to the contract, as well as the effect on the contract price and timeframe for the work to be performed. This results in what is generally referred to as a “change order.” Many projects have a large number of change orders, which can result in significant cost overruns and delays to the project if the contract contains a complicated change order process. Therefore, in order to minimize cost overruns and project delays, it is crucial to keep the change order process as simplified and streamlined as possible.
In the most basic terms, change orders memorialize modifications to the original contract, and typically alter the contract's price, scope of work, and/or completion dates. A typical change order is a written document prepared by the owner or its design professional, and signed by the owner, design professional, and affected contractors and subcontractors. An executed change order indicates the parties’ agreement as to what changes are taking place, including approval for additional costs and schedule impacts.
While the reasons for change orders and the parties initiating them may vary, all change orders have one feature in common. Effective change orders alter the original contract and become part of the contract. Therefore, from a legal standpoint, change orders must be approached with the same caution and forethought as the original contract.
Practice Pointers for Change Orders
In light of the foregoing, some practice pointers for change orders in commercial construction contracts are as follows:
- Carefully Negotiate and Draft Change Order Provisions in the Original Contract.
A carefully negotiated and drafted “changes” clause that accounts for “unexpected circumstances” or “hidden conditions” can protect the parties from downstream costly disputes.
- Immediately Address Changes by Following the Change Order Process, Including Obtaining Necessary Signatures.
Regardless if you are an owner, general contractor or subcontractor, you should address any proposed change order immediately. Even if a decision maker gives “verbal” approval to go ahead with changed work, the work should not proceed without following the change order process in the original contract. This includes making sure to obtain any necessary signatures for the change order, if at all possible.
- Analyze the Plans and Specifications to Determine Whether “Changes” are Within the Scope of the Original Contract, or Whether They are Extra Work.
Prior to entering an original contract, it is imperative that the parties review the plans and specifications for ambiguities regarding work included in the original contract, versus potential extra work that would require a change order. This is important because a careful review of the plans and specifications sometimes reveals that work believed to be a change order is, in fact, original work, or vice versa.
- Make Sure Requests and Approvals for Change Orders are Done by an Authorized Representative.
When a party requests or gives its approval to a change order, it is important to confirm the request or approval came from an authorized representative.
- Avoid Vague and Open-Ended Change Orders.
Indeed, the vaguer a change order, the more likely it can lead to a dispute. Vague and open-ended change orders, including change orders that provide for payment on a time and materials basis, can be difficult for an owner to budget and schedule. This can lead to disputes as to cost and/or time extensions.
- Oral Assurances for Payment Without a Signed Change Order May Not Be Recoverable.
When a party provides verbal assurances to another party for extra work without following the change order process, there is a much higher likelihood that disputes will occur. Although there is case law that may allow a contractor to recover for extra work in private contracts based on oral promises, the parties should avoid placing themselves in such a legal position. Notably, in public contracts, a contractor may not be able to recover for any extra work without a signed changed order, even with verbal assurances of payment from the owner.
About the Author:
John E. Bowerbank, Newmeyer & Dillion
Mr. Bowerbank is a partner in the Newport Beach office and practices in the areas of business, insurance, real estate, and construction litigation. You can reach John at john.bowerbank@ndlf.com
Read the court decisionRead the full story...Reprinted courtesy of
Spreading Cracks On FIU Bridge Failed to Alarm Project Team
May 20, 2019 —
Scott Judy & Richard Korman - Engineering News-RecordOn the morning of last year’s Florida International University pedestrian bridge collapse, when the engineer of record assured project team members that there were no safety risks related to cracks propagating across a part of the unusual single-truss structure, other project team members voiced mild concern, but no alarm. In hindsight, considering that the bridge had no inherent structural redundancy as it sat, incomplete, straddling a busy highway—and would suffer a sudden, catastrophic and deadly collapse just hours later—the team’s lack of urgency remains puzzling, say engineering experts contacted by ENR for comment.
Reprinted courtesy of
Scott Judy, ENR and
Richard Korman, ENR
Mr. Judy may be contacted at mailto:judys@enr.com
Mr. Korman may be contacted at kormanr@enr.com
Read the court decisionRead the full story...Reprinted courtesy of