New Stormwater Climate Change Tool
February 26, 2015 —
Beverley BevenFlorez-CDJ STAFFBuilder magazine reported that the Environmental Protection Agency (EPA) has released a Climate Adjustment Tool that “allows engineers and planners to evaluate the performance of water infrastructure while considering future climate change projections, such as more frequent high-intensity storms and changes in evaporation rates of seasonal precipitation, to determine the benefits of resiliency decisions to reduce local economic burden and protect communities.”
The tool is part of President Obama’s Climate Action Plan Virtual Climate Resilience Toolkit. “Climate change means increased risks to our health, our economy, and our environment,” says EPA Administrator Gina McCarthy, as quoted by Builder. “But with the president’s Climate Action Plan, the agency is taking action to advance science-based technology, such as the addition of the Climate Adjustment Tool, to help state and local planners combat the impacts of climate change, especially significant economic burden from severe weather, and protect communities through sustainability and resiliency measures.”
Read the court decisionRead the full story...Reprinted courtesy of
Why A Jury Found That Contractor 'Retaliated' Against Undocumented Craft Worker
August 22, 2022 —
Richard Korman - Engineering News-RecordOn May 10, 2017, a Boston wall taper who had broken his leg in a fall from a ladder during work six weeks earlier took his two-year-old son to an office of a West Bridgewater, Mass.-based contractor, on the invitation of the CEO who asked him to come and gave the worker $500 to help him get by while recovering.
Reprinted courtesy of
Richard Korman, Engineering News-Record
Mr. Korman may be contacted at kormanr@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
WSDOT Excludes Non-Minority Women-Owned DBEs from Participation Goals
June 15, 2017 —
Ellie Perka - Ahlers & Cressman PLLCA drastic change has been implemented by the Washington State Department of Transportation (“WSDOT”) to the Disadvantaged Business Enterprise (“DBE”) Program in Washington. Effective June 1, 2017, WSDOT has implemented a “waiver” to exclude women-owned DBEs[i] from qualifying toward Condition of Award (“COA”) Goals on federally-funded projects. This move is significant. It will likely result in long-lasting detrimental impacts on the DBE community, women-owned businesses, and the entire construction community in Washington. The construction industry should be in an uproar over this change. Instead, it has largely gone unnoticed (likely because its impacts have not yet been felt). It is a de facto exclusion of women-owned businesses from the DBE program, and the severity of this change cannot be overstated.
Under the waiver, women-owned businesses no longer satisfy COA Goals on federally-funded projects (i.e., projects receiving funding from the Federal Highway Administration) advertised after June 1, 2017. Existing contracts are not impacted and may continue to utilize women-owned DBEs to satisfy COA Goals until the project is complete. The waiver is not retroactive.
Read the court decisionRead the full story...Reprinted courtesy of
Ellie Perka, Ahlers & Cressman PLLCMs. Perka may be contacted at
eperka@ac-lawyers.com
What if the "Your Work" Exclusion is Inapplicable? ISO Classification and Construction Defect Claims.
February 14, 2023 —
David Humphreys - Carson Law Group, PLLCThis article was first published by the National Association of Home Builders (NAHB) on their NAHBNow blog
One of the risks faced by a residential builder is that, following completion of construction, the homeowner may assert a claim against the builder for damage to the home caused by an alleged construction defect. One of the ways a builder manages the risk of such construction defect claims is by purchasing commercial general liability (“CGL”) insurance.
A builder’s CGL policy covers those sums the builder is legally obligated to pay as damages because of bodily injury or property damage caused by an “occurrence,” that is, damage that is accidental rather than being expected or intended by the builder, so long as the claim does not fall within any of the policy’s several “exclusions” from coverage.
When faced with a construction defect lawsuit, our builder clients are often surprised—and dismayed—when their CGL insurer denies coverage and refuses to defend the builder. However, builders shouldn’t take their insurer’s denial of coverage at face value. This article discusses a new argument we recently discovered that has been a game-changer for our builder clients who were denied coverage in construction defect cases.
Whether coverage exists always depends on the specific language of the particular CGL policy, and courts generally construe exclusions against insurers. This allows experienced coverage attorneys to, at times, successfully challenge declinations of coverage and, at a minimum, convince insurers to pay for the builder’s defense.
A typical CGL policy provides products-completed operations coverage, which is sought by businesses that face potential liability arising out of the products that they have sold or operations that they have completed. Products-completed operations coverage allows builders to obtain many years of coverage for a completed project. Over the years, insurers have added to their policies modifications and exclusions that limit their exposure for claims that fall under that coverage.
Exclusion (l) or the “your work” exclusion, will often exclude coverage for a latent defect claim against the builder. A standard “your work” exclusion provides:
This insurance does not apply to: . . . “[p]roperty damage” to “your work” arising out of it or any part of it and included in the “products-completed operations hazard.”
This “your work” and similar exclusions are designed to limit coverage for business risks that are within the contractor’s own control; e.g., a claim that the contractor caused damage to the contractor’s own work. These exclusions apply both to ongoing and completed projects, which can leave a builder unprotected from lawsuits for years after a project is completed.
However, builders who are classified on the declarations page with Code 91580 Contractors— Executive Supervisors or Executive Superintendents, may not be subject to the “your work” exclusion. 91580 is a common classification assigned to builders during insurance underwriting. This classification falls into what is referred to as “dagger class” or “plus sign class,” which indicates that Products and/or Completed Operations coverage is
included as part of and not separate from the Premises/Operations coverage (emphasis added).
It has been noted that dagger” and “plus sign” classifications create confusion because of the seeming contradiction between policy wording and coverage rules.* The CGL policy seems to expressly exclude products and/or completed operations losses for “dagger” or “plus sign” classes. In the definitions section we find the following:
“Products-completed operations hazard”: . . .b. Does not Include “bodily Injury” or “property damage” arising out of:. . . (3) Products or operations for which the classification, listed In the Declarations or in a policy schedule, states that products- completed operations are subject to the General Aggregate Limit.”
This apparent exclusionary language, however, must be read in conjunction with the Insurance Services Office’s (ISO) Rule 25.F.1.:
Rule 25. CLASSIFICATIONS
F. Symbols
1. Plus Sign
A plus sign when shown in the Premium Base column under General Liability insurance in the Classification Table - means that coverage for Products and/or Completed Operations is included in the Premises/Operations coverage at no additional premium charge. When this situation applies, the classification described in the policy schedule or Declarations must state that:
“Products-completed operations are subject to the General Aggregate Limit” to provide Products and/or Completed Operations coverage(s).
When read together then, the exclusionary wording in the policy definition removes any product or operation loss subject to the “dagger” or “plus sign” classification from the definition of Products Completed Operations Hazard. Under the dagger or plus sign classification of Rule 25, coverage for products and/or operations is included in the premises operations coverage. Consequently, a loss can no longer be defined as a product completed loss, and as a result it is no longer subject to the “your work” exclusion.
Recall that the standard “your work” exclusion quoted above excludes coverage for “property damage” to “your work” “arising out of it or any part of it
and included in the “products-completed operations hazard”.” Here, we emphasize “and” because the “your work” exclusion applies only to property damage that is also included in the “products-completed operations hazard.” Since property damage claims arising under “plus sign” classifications are expressly excluded from the “products-completed operations hazard” (they are included in the premises/operations coverage) the “your work” exclusion simply does not apply. This means that, if your CGL insurer denies your construction defect claim based on the “your work” exclusion, do what the title of this article suggests: Check your ISO classification! If 91580 “Executive Supervisors or Executive Superintendents” is listed on your Declarations page, you may be in luck.
This new ISO classification-based coverage argument will likely also apply to other exclusions and endorsements that CGL insurers routinely rely on in denying coverage in construction defect cases. We recently successfully challenged a coverage denial based on the following “prior work” exclusionary endorsement:
”This insurance does not apply to ‘your products’ or ‘your work’ completed prior to” a certain date listed in the endorsement. . .
“Specifically, this insurance does not apply to. . . “property damage”. . . included in the ‘products-completed operations hazard’ and arising out of. . . ‘your work’ performed by or on behalf of you prior to the date shown above.”
Again, this endorsement incorporates the “products-completed operations hazard,” which allowed us to successfully argue that the exclusion was inapplicable to a builder classified as a 91580 “Executive Supervisor or Executive Superintendent.”
To our knowledge, this new ISO classification-based coverage argument has not yet been addressed by a court. Our recent successes with it have concluded with favorable settlements for our clients. Accordingly, for now, the ISO classification-based argument is a powerful new tool to challenge denials of coverage in construction defect cases where the builder is classified under 91580 “Executive Supervisors or Executive Superintendents.”
David Humphreys is a Partner at Carson Law Group, PLLC, and has been representing construction contractors, subcontractors, and owners for more than two decades in Mississippi and throughout the Southeast.
*See “Dagger” or Plus Symbol Classes: What They Mean, Chris Boggs - Virtual University | “Dagger” or Plus Symbol Classes: What They Mean) (independentagent.com)
Read the court decisionRead the full story...Reprinted courtesy of
No Friday Night Lights at $60 Million Texas Stadium: Muni Credit
March 26, 2014 —
Darrell Preston and Aaron Kuriloff – BloombergPervasive cracking has shuttered the $60 million home of a high-school football championship team in Texas after less than two years. Investors in the tax-free bonds that paid for the stadium are unscathed.
Taxpayers in Allen Independent School District north of Dallas and the $29 billion Texas Permanent School Fund, a state bond insurer, are responsible for $119 million of debt that paid for the venue and other facilities, leading officials to find a new site for graduation and possibly games after closing 18,000-seat Eagle Stadium last month.
The development suggests the fund, created in 1854 to help pay for education, shouldn’t be used for stadiums, said Colby Harlow, president of hedge fund Harlow Capital Management. The Permanent Fund has top credit ratings and secures about $55 billion of bonds, according to the Texas Education Agency. The pool has at times reached the limit of debt it can back, preventing districts from accessing it. The guarantee is still a boon to bondholders.
Mr. Merelman may be contacted at smerelman@bloomberg.net; Mr. Sillup may be contacted at msillup@bloomberg.net
Read the court decisionRead the full story...Reprinted courtesy of
Darrell Preston and Aaron Kuriloff, Bloomberg
Mixing Concrete, Like Baking a Cake, is Fraught with Problems When the Recipe is Not Followed
February 26, 2015 —
Garret Murai – California Construction Law Blog“Mixing concrete, like baking a cake, is fraught with problems when the recipe is not followed.” – Justice Kenneth Yegan, State Ready Mix, Inc. v. Moffatt & Nichol, California Court of Appeal for the Second District, Case No. B253421 (January 8, 2015).
I love jurists who aren’t afraid to mix in a little humour in their opinions.
But “[t]he law,” as a framed needlepoint in one of my colleague’s offices says, “is serious business.” And the State Ready Mix case involved one of the thorniest problems in construction litigation:
What to do when you’re sued and you think someone else is to blame.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel Rosen Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com
Design-Assist, an Ambiguous Term Causing Conflict in the Construction Industry[1]
December 02, 2019 —
John P. Ahlers - Ahlers Cressman & Sleight PLLC“Design-Assist” is one of the recent cost-saving trends being touted for construction projects and, in particular, construction projects utilizing alternative procurement methods. If an internet search for the term, “design-assist” is made, the result will be numerous construction industry articles and white papers lauding “design-assist” as a recent cost-saving trend in construction procurement. From a legal perspective, however, the term “design-assist” is notably absent from court opinions and most state licensing laws. With the exception of the ConsensusDocs, few standard form contracts even include the term “design-assist” in their text.
The ConsensusDocs agreement provides examples of the Constructor’s obligations to perform “assisting activities” (the term “design-assist” is not used) and states that, notwithstanding the performance of such “assisting activities” by the Constructor, the responsibility of the design remains with the Designer unless otherwise stated in the Contract:
- Article 4.5 DESIGN PROFESSIONAL’S RESPONSIBIITIES The Designer shall furnish or provide all design and engineering services necessary to design the Project in accordance with the Owner’s objectives … the Designer shall draw upon the assistance of Constructor and others in developing the design, but the Designer shall retain overall responsibility for all design decisions….
- Article 4.6 CONSTRUCTOR’S RESPONSIBILITIES [T]he Constructor shall assist the Designer in the development of the Project Plan and Project Design but shall not provide professional services which constitute the practice of architecture or engineering unless the Constructor needs to provide such services in order to carry out its responsibilities … or unless specifically called for by the Contract Documents.
Read the court decisionRead the full story...Reprinted courtesy of
John P. Ahlers, Ahlers Cressman & Sleight PLLCMr. Ahlers may be contacted at
john.ahlers@acslawyers.com
The Economic Loss Rule and the Disclosure of Latent Defects: In re the Estate of Carol S. Gattis
January 15, 2014 —
Brady Iandiorio - Higgins, Hopkins, McLain & Roswell, LLCIn a recent case of first impression, the Colorado Court of Appeals determined that the economic loss rule does not bar a nondisclosure tort claim against a seller of a home, built on expansive soils which caused damage to the house after the sale. The case of In re the Estate of Carol S. Gattis represents a new decision regarding the economic loss rule. Because it is a case of first impression, we must wait to see whether the Colorado Supreme Court grants a petition for certiorari.
Until then, we will analyze the decision handed down on November 7, 2013. The sellers of the home sold it to an entity they controlled for the purpose of repairing and reselling the home. Before that purchase, Sellers obtained engineering reports including discussion of structural problems resulting from expansive soils. A structural repair entity, also controlled by Sellers, oversaw the needed repair work. After the repair work was completed, Sellers obtained title to the residence and listed it for sale.
Sellers had no direct contact with Gattis, who purchased the residence from Sellers. The purchase was executed through a standard-form real estate contract, approved by the Colorado Real Estate Commission: Contract to Buy and Sell Real Estate, to which no changes were made. Several years after taking title to the residence, Gattis commenced action, pleading several tort claims alleging only economic losses based on damage to the residence resulting from expansive soils.
Read the court decisionRead the full story...Reprinted courtesy of
Brady Iandiorio, Higgins, Hopkins, McLain & Roswell, LLCMr. Iandiorio may be contacted at
iandiorio@hhmrlaw.com