Heads I Win, Tails You Lose. Court Finds Indemnity Provision Went Too Far
May 25, 2020 —
Garret Murai - California Construction Law BlogWe all love David and Goliath stories. The underdog winning against the far stronger (and dastardly) opponent. Think Rocky Balboa versus Ivan Drago, the Star Wars Rebellion versus the Galatic Empire, Indiana Jones versus a good chunk of the Third Reich. And now, we have Margaret Williams.
The Story of Margaret Williams and her LLC
The story, told in Long Beach Unified School District v. Margaret Williams, LLC, Case No. B290069 (December 9, 2019), is about Margaret Williams. Ms. Williams (we’ll just call her “Margaret” going forward because it just sounds better when telling a story) worked for nearly ten years full-time for the Long Beach Unified School District, toiling day in and day out doing construction management and environmental compliance work, including work involving the clean up of material at a school construction site contaminated with arsenic.
Although she worked full-time for the District for nearly ten years, she wasn’t an employee. Rather, she was a contractor. And, on top of it all, as a condition of working for the District, the District required that she form a company in order to contract with the District. According to Margaret, “In order to work with the District, I was directed . . . to form a corporation or partnership. This was the only way I could work for the District: I could not enter into a contract with the District as an individual.” So, in 2006, she formed a company, simply called Margaret Williams, LLC.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
Luxury Villa Fraudsters Jailed for Madeira Potato Field Scam
September 25, 2018 —
Franz Wild - BloombergFour men and a woman convicted of conning people to invest in a fraudulent luxury villa construction scheme on a potato field in the Portuguese island of Madeira were sentenced to as long as 5 1/2 years in a U.K. jail.
Read the court decisionRead the full story...Reprinted courtesy of
Franz Wild, Bloomberg
Wisconsin High Court Rejects Insurer’s Misuse of “Other Insurance” Provision
March 04, 2019 —
Michael S. Levine & David M. Costello - Hunton Andrews KurthThe Wisconsin Supreme Court held last week in Steadfast Ins. Co. v. Greenwich Ins. Co. that two insurers must contribute proportionally to the defense of an additional insured under their comprehensive liability policies.
In 2008, torrential rainstorms battered the Milwaukee area for two days. The downpour overwhelmed the city’s sewer system, causing significant flooding in homes throughout the region. Out of those floods sprang several lawsuits against the Milwaukee Metropolitan Sewerage District (“MMSD”) for negligent inspection, maintenance, repair, and operation of Milwaukee’s sewage system.
MMSD was an additional insured under liability policies covering two other water service providers responsible for the city’s sewer systems. The first policy was issued by Greenwich Insurance Company for United Water Services Milwaukee, LLC, and the second was issued by Steadfast Insurance Company for Veolia Water Milwaukee, LLC. After learning of the lawsuits, MMSD tendered its defense of the sewage suits to both insurers. Steadfast accepted the defense; but Greenwich refused, claiming that its policy was excess to Steadfast’s based on an “other insurance” clause in Greenwich’s policy.
Reprinted courtesy of
Michael S. Levine, Hunton Andrews Kurth and
David Costello, Hunton Andrews Kurth
Mr. Levine may be contacted at mlevine@HuntonAK.com
Mr. Costello may be contacted at dcostello@HuntonAK.com
Read the court decisionRead the full story...Reprinted courtesy of
U.S. Steel Invoking Carnegie’s Legacy in Revival Strategy
July 23, 2014 —
Sonja Elmquist – BloombergIn March 2013, Mario Longhi lobbed an unexpected question into a roomful of 150 U.S. Steel Corp. managers: Who here would buy the company’s stock, tomorrow?
He gave them three seconds, and “only a few reacted in that time frame positively,” Longhi said.
Since that meeting, Longhi has been promoted to chief executive officer, and nine months into his tenure he’s closed one plant permanently, two more are temporarily idled and he’s planning to overhaul another. It’s all part of his plan to transform the 144-year-old company into a lean, modern steel producer. Investors are taking note, with the shares up 53 percent since he took over.
Read the court decisionRead the full story...Reprinted courtesy of
Sonja Elmquist, BloombergMs. Elmquist may be contacted at
selmquist1@bloomberg.net
ASCE Statement on Hurricane Milton and Environmental Threats
October 15, 2024 —
Feniosky Peña-Mora, P.E., President - American Society of Civil EngineersWASHINGTON, DC. – On the heels of the tragic damage caused by Hurricane Helene throughout the Southeast, Floridians were struck by another major hurricane, Milton, less than two weeks later. Our hearts go out to those impacted again by this storm through property damage, lack of water access, power outages, or worse, loss of life, all before getting a chance to recover from Helene. Civil engineers are dedicated to protecting the public with projects that can lessen the impacts of these storms, and we are eager to help communities rebuild as quickly as possible following events like Milton and Helene.
Although we do not yet know the full scope of destruction caused by Hurricane Milton, severe weather, including compound flooding events, are increasing regularly and pose a great risk to our safety and economic vitality. While so many eyes are fixated on hurricanes impacting the Southeast, wildfires are burning across several western states, including the Elk Fire in Wyoming, the largest wildfire the Bighorn National Forest has experienced in more than a century, now spanning over 75,000 acres as the region is experiencing unusually hot and dry weather and strong winds that are helping this fire to spread rapidly. The climate impacts we are accustomed to – wildfires in the West and hurricanes in the Southeast – are getting stronger, and now environmental challenges are occurring in areas we wouldn't suspect, such as Hurricane Helene striking mountain communities in Western North Carolina that have been labeled as "climate safe-havens," and Texas dealing with annual winter storms.
ASCE is a leader in codes and standards development and has created an
easy-to-understand toolkit for legislators and the public to learn the benefits of these up-to-date standards and determine when and how to adopt them, making our built environment more resilient to natural catastrophes. ASCE's flagship standard,
ASCE/SEI 7-22, recently underwent the most significant update to its
flooding chapter to ensure structures following this standard are prepared for 500-year flood events.
Read the court decisionRead the full story...Reprinted courtesy of
Avoid a Derailed Settlement in Construction
March 28, 2022 —
Patrick Barthet - Construction ExecutiveMore and more construction cases are settling because lawyers know juries can prove to be unpredictable. The litigation process, as well as any actual trial, can be stressful, expensive and quite lengthy. Settlements are, for the most part, private while suits are public. Current reports find more than 90% of civil cases filed in state circuit courts are disposed of before trial. When that doesn't happen, things could go very poorly, as the case below illustrates.
The Case
Adam was seriously injured in a collision with a dump truck owned by Bang and driven by Tomas. While suit by Adam against Bang and Tomas was pending, Adam suggested they settle by having Bang pay him. Upon receipt of the offer, Bang's lawyer reached out confirming that his client was okay with the settlement amount but wished to add that the settlement also include the satisfaction of a lien filed by Adam's workers' compensation carrier. Adam's attorney refused that additional request, but that didn't stop Bang's lawyer. Based on the fact that Adam had agreed to the settlement amount, the lawyer filed a boiler plate notice of acceptance of settlement and had Bang issue a settlement check payable to Adam in the amount Adam had requested. Adam remained unwilling to compromise. He continued to resist the modified terms, which added satisfaction of the worker’s compensation lien. Bang then filed a motion to enforce settlement, arguing that since there was agreement on the settlement amount, Adam was required to do the deal.
Reprinted courtesy of
Patrick Barthet, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Mr. Barthet may be contacted at
pbarthet@barthet.com
Ownership is Not a Conclusive Factor for Ongoing Operations Additional Insured Coverage
November 15, 2017 —
Christopher Kendrick & Valerie A. Moore – Haight Brown & Bonesteel LLPIn McMillin Management Services v. Financial Pacific Ins. Co. (No. D069814, filed 11/14/17), a California appeals court held that an insurer had a duty to defend a general contractor under an “ongoing operations” additional insured (AI) endorsement for damage occurring after the named insured subcontractor completed its work, because the endorsement did not limit coverage solely to liability during the subcontractors’ ongoing operations, but rather, broadly provided coverage for liability “arising out of” such operations.
Reprinted courtesy of
Christopher Kendrick, Haight Brown & Bonesteel LLP and
Valerie A. Moore, Haight Brown & Bonesteel LLP
Mr. Kendrick may be contacted at ckendrick@hbblaw.com
Ms. Moore may be contacted at vmoore@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Event-Cancellation Insurance Issues During a Pandemic
September 07, 2020 —
Lorelie S. Masters & Latosha M. Ellis - Hunton Andrews KurthAs the effects of coronavirus continue, organizations and companies now are considering whether events in late 2020 and early 2021 can take place or need to be converted to virtual events. What insurance effects will those changes and cancellations have? Consideration of these important decisions requires a review of both event-cancellation insurance and a consideration of force majeure and other such issues.
On the insurance front, years ago, many policyholders purchased event-cancellation insurance for events in 2020, 2021, and even as far out as 2024. Such policies, purchased before the middle of March 2020, generally contain explicit coverage “buy-backs” for losses from “communicable disease.” That is, the policyholders paid an extra, specifically identified premium to remove any exclusion for communicable disease from these policies. Typically, these policies do not use the word, “virus”, but rather use “communicable disease”; and exclude neither. Those policies typically cover a specified amount of net profit and include additional coverages for “Cost of Remedial Action”, “Future Marketing Expense”, etc., over and above that specified amount of coverage.
Reprinted courtesy of
Lorelie S. Masters, Hunton Andrews Kurth and
Latosha M. Ellis, Hunton Andrews Kurth
Ms. Masters may be contacted at lmasters@HuntonAK.com
Ms. Ellis may be contacted at lellis@HuntonAK.com
Read the court decisionRead the full story...Reprinted courtesy of