Blindly Relying on Public Adjuster or Loss Consultant’s False Estimate Can Play Out Badly
May 03, 2021 —
David Adelstein - Florida Construction Legal UpdatesInsurance policies, particularly property insurance policies, have a concealment or fraud provision that, in essence, gives the insurer an out if the insured submits a fraudulent claim, a false claim, or conceals material facts. Unlike a traditional fraud claim where a party needs to prove intent, the provision is broad enough that it does not require any intent behind making a false statement. See Mezadieu v. Safepoint Ins. Co., 46 Fla.L.Weekly D691c (Fla. 4th DCA 2021). For this reason, and as exemplified below, do NOT blindly rely on a public adjuster or loss consultant’s estimate that contains false statements because those false statements, particularly if you know they are false, can play out badly for you! Review the estimate and ask questions about it to make sure you understand what is being included in the loss or damages estimate.
In Mezadieu, a homeowner submitted a claim to her property insurance carrier due to a second-floor water leak emanating from her bathroom. She submitted an estimate from her public adjuster that included damages for her kitchen cabinets directly below the second-floor bathroom, as well as other items on her first-floor. Her carrier denied coverage based on the exclusion that the policy excludes damage caused by “[c]onstant or repeated seepage of water or steam…which occurs over a period of time.”
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Slow Down?
December 03, 2024 —
Daniel Lund III - LexologyAbsolutely not, said the Louisiana Fifth Circuit Court of Appeal to a masonry subcontractor being sued for allegedly improperly refusing to honor a subcontract bid.
A general contractor preparing its overall bid for a public project in Jefferson Parish relied in the process on the defendant masonry subcontractor’s bid. After a public bid process and receiving the award of the project, the general contractor was informed by the subcontractor that it believed that the unit price form that had been supplied to the sub “contained inaccuracies.” Notwithstanding offers by the GC to endeavor to address the purported “inaccuracies” during the project, most likely by a change order, the subcontractor refused to execute its subcontract. The general contractor then awarded the masonry work to another subcontractor for $368,222 more than the original sub’s bid.
The GC filed suit – for recovery of $368,222 – against the defendant subcontractor during the course of the public project. The defendant sub objected, arguing to the court that the lawsuit was “premature.” At the heart of the prematurity argument: the sub urging that the general contractor filed suit before its right to recover damages had accrued.
Read the court decisionRead the full story...Reprinted courtesy of
Daniel Lund III, PhelpsMr. Lund may be contacted at
daniel.lund@phelps.com
A Termination for Convenience Is Not a Termination for Default
April 22, 2024 —
David Adelstein - Florida Construction Legal UpdatesA termination for convenience is NOT a termination for default. They are NOT the same. They should NOT be treated as the same. I am a huge proponent of termination for convenience provisions because sometimes a party needs to be able to exercise a termination for convenience, but the termination is not one that rises to a basis for default. However, exercising a termination for convenience does not mean you get to go back in time and convert the termination for convenience into a termination for default. It does not work like that. Nor should it.
An opinion out of the Civilian Board of Contract Appeals – Williams Building Company, Inc. v. Department of State, CBCA 7147, 2024 WL 1099788 (CBCA 2024 – demonstrates a fundamental distinction between a termination for convenience and a termination for default, i.e., that you don’t get to conjure up defaults when you exercise a termination for convenience:
Because a termination for convenience essentially turns a fixed-price construction contract into a cost-reimbursement contract, allowing the contractor to recover its incurred performance costs, the resolution of this appeal will involve identifying the total costs that [Contractor] incurred in performing this contract before [Government] terminated it for convenience. Since [Government] terminated the contract for convenience rather than for default, it no longer matters whether, in the past,[Contractor] acted intentionally in overstating the amount of its incurred costs or committed a contract breach. Ultimately, as permitted in response to a termination for convenience, [Contractor] will recover those allowable costs that [Contractor]establishes it incurred in performing the contract.
Williams Building Company, supra.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Meet the Forum's In-House Counsel: J. PAUL ALLEN
May 28, 2024 —
Jessica Knox - The Dispute ResolverCompany: Fischer Homes
Email: paul@jpaulallen.com
Law School: Chase College of Law at Northern Kentucky University (JD 1992)
States Where Company Operates/Does Business: Kentucky, Ohio, Indiana, Georgia, Missouri, Florida
Q: Describe your background and the path you took to becoming in-house counsel.
A: I started at a large Cincinnati firm straight out of law school. I moved in-house for a client of the firm after about 8 years and have remained in-house ever since. The in-house experience has been rewarding and varied over the last 24 years. I have worked for a Fortune 500, publicly traded steel company, a private equity led construction products company, and, finally, a family-owned residential homebuilder. I had the good fortune to be General Counsel at the last 2 in-house companies and was able to establish a legal department from scratch at Fischer Homes. As time went on and I gained experience, I stayed in-house because of the ability to work for a single client and have a greater impact on the business side of things.
Read the court decisionRead the full story...Reprinted courtesy of
Jessica Knox, Stinson LLPMs. Knox may be contacted at
jessica.knox@stinson.com
Subcontractors Have a Duty to Clarify Ambiguities in Bid Documents
August 19, 2015 —
Craig Martin – Construction Contractor AdvisorSeveral months ago, I wrote about an escalator subcontractor that sued a general contractor, demanding payment for work completed based on approved shop drawings. The trial court agreed with the subcontractor, but the general contractor appealed. Ten months later, the Court of Appeals reversed, finding that the subcontractor had a duty to bring to the general contractor’s attention major discrepancies or errors they detect in the bid documents.
“The subcontractor failed to disclose ambiguities in the plans and must suffer the peril.”
Construction Difficulties
The subcontractor installed 32 inch escalators throughout the project, but the plans called for 40 inch escalators. The general contractor and subcontractor could not reach agreement on how the dispute should be resolved. The subcontractor sued the general to get paid for replacing the escalators and the general sued to subcontractor for concessions it had to pay to the owner.
Read the court decisionRead the full story...Reprinted courtesy of
Craig Martin, Lamson, Dugan and Murray, LLPMr. Martin may be contacted at
cmartin@ldmlaw.com
Connecticut Reverses Course for Construction Managers on School Projects
August 05, 2024 —
Anand Gupta - Construction Law Zone BlogOn June 6, 2024, Connecticut Governor Ned Lamont signed into law Public Act 24-151 (H.B. 5524) (Bill 5524). Bill 5524 authorized and adjusted bonds of the state and provisions related to state and municipal tax administration, as well as addressed school building projects. Notably, Bill 5524 removed the ban on construction managers self-performing work on public school construction projects, effective July 1, 2024. Allowing construction managers to self-perform certain portions of the work, such as general trades, subject to the standard bidding requirements, is a common industry practice that, theoretically, reduces total project costs by reducing the amount of subcontracted work. However, proponents of banning self-performance argue that construction managers have too much information to bid fairly and competitively.
Reprinted courtesy of
Anand Gupta, Robinson+Cole
Mr. Gupta may be contacted at agupta@rc.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Contractors: Consult Your Insurance Broker Regarding Your CGL Policy
February 15, 2018 —
David Adelstein – Florida Construction Legal UpdatesContractors: do yourself a favor and consult your insurance broker regarding your commercial general liability (CGL) policy. Do this now, especially if you subcontract out work.
CGL policies contain a “your work” exclusion. The CGL policy is written such that it excludes “‘property damage’ to ‘your work’ arising out of it or any part of it and included in the ‘products-completed operations hazard.’” This exclusion will be raised in the post-completion latent construction defect scenario. (There are other exclusions that will be raised to a defect discovered during construction.) Certain policies will contain a subcontractor exception to this “your work” exclusion. You WANT this exception- no doubt about it so that this exclusion does not apply to work performed by your subcontractors. Without this subcontractor exception, truth be told, this “your work” exclusion is a total back-breaker to contractors. It will give your insurer an immediate out for many latent defect property scenarios since excluded from coverage is property damage to your work including work performed by your subcontractors.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Florida Construction Legal UpdatesMr. Adelstein may be contacted at
dadelstein@gmail.com
Hawaii Supreme Court Finds Excess Can Sue Primary for Equitable Subrogation
July 30, 2015 —
Tred R. Eyerly – Insurance Law HawaiiIn responding to a certified question from the U.S. Distric Court, the Hawaii Supreme Court determined that an excess carrier can sue the primary carrier for failure to settle a claim in bad faith within primary limits. St. Paul Fire & Marine Ins. Co. v. Libery Mut. Ins. Co., 2015 Haw. LEXIS 142 (Haw. June 29, 2015).
St. Paul, the excess carrier, and Liberty Mutual, the primary carrier, issued polices to Pleasant Travel Service, Inc. The primary policy covered up to $1 million.
Pleasant Travel was sued for damages resulting from an accidental death. St. Paul alleged that Liberty Mutual rejected multiple pretrial settlement offers within the $1 million primary policy limit. A trial resulted in a verdict of $4.1 million against Pleasant Travel. The action settled for a confidential amount in excess of the Liberty Mutual policy limit. St. Paul paid the amount in excess.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com