Insurer Must Defend Contractor Against Claims of Faulty Workmanship
May 30, 2018 —
Tred R. Eyerly - Insurance Law HawaiiThe magistrate judge recommended that the insurer's motion for summary judgment seeking to determine there was no coverage for claims of faulty workmanship be denied. Greystone Multi-Family Builders v. Gemini Ins. Co., 2018 U.S. Dist. LEXIS 56770 (S.D. Tex. Feb. 26, 2018).
TPG (Post Oak) purchased an OCIP policy to cover construction of an apartment complex. TPG was sued by the contractor, Greystone, after TPG cancelled the construction contract. TPG filed a counterclaim against the contractor, alleging that Greystone had failed to properly perform in building a luxury apartment complex which resulted in monetary damages to TPG. The complaint further alleged that the project was nine months behind its substantial completion date, far from complete, and over budget when TPG cancelled the contract. The cost to fix the mismanagement caused by Greystone was $18.9 million.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Are Housing Prices Poised to Fall in Denver?
December 10, 2015 —
Beverley BevenFlorez-CDJ STAFFDenver, Dallas, and Houston’s housing markets are rising too quickly and will soon hit “’bubble territory’” according to a housing market index by Florida Atlantic University and Florida International University, reported the Denver Business Journal.
"There is about a 70 percent chance that renters in Denver will get more wealth on average than buyers," Ken Johnson, a real estate economist at the university in Boca Raton, Florida, told the Denver Post.
Read the court decisionRead the full story...Reprinted courtesy of
Suing the Lowest Bidder on Public Construction Projects
September 17, 2015 —
Craig Martin – Construction Contractor AdvisorThe California Court of Appeals has allowed the second lowest bidders on public construction projects to sue the lowest bidder where it appears that the lowest bidder was only the lowest because it paid its employees less than the established prevailing wage. This is a novel theory for recovery, but may provide for an opportunity to challenge improperly low bids.
Background
Between 2009 and 2012, American Asphalt outbid two asphalt companies on 23 public works projects, totaling nearly $15 million. The two asphalt companies sued American Asphalt alleging that they were the second lowest bidder all 23 construction projects and they would have been the lowest had American Asphalt paid its employees the required prevailing wage. Importantly, the municipality awarding the contracts was not sued by the second lowest bidders. Instead, the second lowest bidders alleged that American Asphalt intentionally interfered with a business expectancy and sought damages from American Asphalt, specifically the profit that they lost by not performing these contracts.
Read the court decisionRead the full story...Reprinted courtesy of
Craig Martin, Lamson, Dugan and Murray, LLPMr. Martin may be contacted at
cmartin@ldmlaw.com
No Jail Time for Disbarred Construction Defect Lawyer
May 10, 2013 —
CDJ STAFFThe New Mexico Supreme Court decided that a lawyer who defrauded clients will not be spending any time in jail, although they did disbar him in February. Bradley R. Sims brought a cashier’s check for $10,000 to repay his former client. Casa Bandera had hired Sims to sue over construction defects at apartment buildings it owned in Las Cruces, New Mexico. The court had found that Sims did not file the lawsuit but that created documents to convince his clients that he had.
Sims initially intended to repay Casa Bandera through monies owed him by Sundland Park, New Mexico. When that did not arrive at the court, Sims borrowed the money. He has yet to comply with a court order to turn over his client lists so that the disciplinary board can determine if he owes money to any other clients.
Read the court decisionRead the full story...Reprinted courtesy of
Where Breach of Contract and Tortious Interference Collide
July 18, 2022 —
Christopher G. Hill - Construction Law MusingsClaims for breach of contract are numerous in the construction law world. Without these claims we construction attorneys would have a hard time keeping the doors open. A 2021 case examined a different sort of claim that could arise (though, “spoiler alert” did not in this case) during the course of a construction project. That type of claim is one for tortious interference with business expectancy.
In Clark Nexsen, Inc. et. al v. Rebkee, the U. S. District Court for the Eastern District of Virginia gave a great explanation of the law of this type of claim in analyzing the following basic facts:
In 2018, Clark Nexsen, Inc. (“Clark”) and MEB General Contractors, Inc. (“MEB”) responded to Henrico County’s (“Henrico”) Request for Proposals (“RFP”) for the design and construction of a sport and convocation center (the “Project”). Henrico initially shortlisted Clark and MEB as a “design-build” team for the Project, but later restarted the search, issuing a second RFP. Clark and MEB submitted a second “design-build” proposal, but Henrico selected Rebkee Co. (“Rebkee”) for certain development aspects of the Project. MEB also submitted proposals to Rebkee, and Rebkee selected MEB as the design-builder for the Project. MEB, at Rebkee’s request, solicited proposals from three design firms and ultimately selected Clark as its design partner. From December 2019 to May 2020, Clark and MEB served as the design-build team to assist Rebkee in developing the Project. In connection therewith, Clark developed proprietary designs, technical drawings, and, with MEB, several cost estimates. In February 2020, MEB submitted a $294,334.50 Pay Application to Rebkee for engineering, design, and Project development work. Rebkee never paid MEB. Henrico paid MEB $50,000.00 as partial payment for MEB’s and Clark’s work. MEB then learned that Rebkee was using Clark’s drawings to solicit design and construction proposals from other companies. On July 23, 2020, Rebkee told MEB that Henrico directed it to cancel the design-build arrangement with MEB and Clark and pursue a different planning method. MEB and Clark sued and Rebkee for, among other claims, tortious interference with a business expectancy. Rebkee moved to dismiss the tortious interference claim.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Mold Due to Construction Defects May Temporarily Close Fire Station
October 25, 2013 —
CDJ STAFFFire Station 5 in Chino, California is about to undergo mold remediation. Ruben Martinez, the city’s Public Works Director, expects the station to be closed during remediation. “We’d like to get the firemen out of there so there isn’t any potential infection or worker’s compensation issues,” he said. However, Fire Department Captain Steve Harrison did not think the station needed to be closed. “We are adamant the station stays staffed while the remediation work is completed.”
The mold came about due to problems the station has had with roof leaks since its opening in 1999. The current set of repairs will cost between $12,000 and $25,000, and the city is discussing matters with its insurer to determine who will pay for the repairs. It’ won’t be the original contractor, as the building is past the 10-year limit for construction defect claims. Even if a claim were possible, the contractor who built the building is bankrupt.
Read the court decisionRead the full story...Reprinted courtesy of
Restaurant Wants SCOTUS to Dust Off Eleventh Circuit’s “Physical Loss” Ruling
February 01, 2021 —
Michael S. Levine & Geoffrey B. Fehling - Hunton Insurance Recovery BlogA South Florida restaurant has asked the US Supreme Court to overturn a federal district court’s ruling that the restaurant is not entitled to coverage under an “all risk” commercial property insurance policy for lost income and extra expenses resulting from nearby road construction. In the underlying coverage action, the policyholder, Mama Jo’s (operating as Berries in the Grove), sought coverage under its all-risk policy for business income losses and expenses caused by construction dust and debris that migrated into the restaurant. Should the Supreme Court grant certiorari, the case will be closely watched by insurers and policyholders alike as an indicator of the scope of coverage available under all-risk policies and whether the principles pertinent to construction dust and debris (at issue in Mama Jo’s claim) have any application to the thousands of pending claims for COVID-19-related business interruption losses pending in the state and federal court systems.
As previously discussed on this blog, the Eleventh Circuit’s decision deviates from Florida precedent on the issue of “direct physical loss” and even its own understanding of that term as described in the August 18, 2020 decision now at issue before the Supreme Court. Mama Jo’s points to this in its petition along with several other errors arguing, for example, that the appellate court’s ruling renders entire areas of coverage nonexistent by requiring “tangible destruction” of property under all-risk policies that expressly afford coverage for types of clean-up costs required to remove debris from covered property.
Reprinted courtesy of
Michael S. Levine, Hunton Andrews Kurth and
Geoffrey B. Fehling, Hunton Andrews Kurth
Mr. Levine may be contacted at mlevine@HuntonAK.com
Mr. Fehling may be contacted at gfehling@HuntonAK.com
Read the court decisionRead the full story...Reprinted courtesy of
California Bullet Train Clears Federal Environmental Approval
June 30, 2014 —
Michael B. Marois – BloombergThe U.S. Federal Railroad Administration has approved an environmental review needed to begin building a portion of a $68 billion California high-speed rail line that has been mired in lawsuits.
The agency, part of the Transportation Department, said in a release that it cleared a 114-mile (183-kilometer) stretch of the project in the Central Valley.
The California High-Speed Rail Authority has been blocked from selling bonds to begin construction of the first U.S. bullet train until a court decides whether details of the financing were adequately disclosed.
Read the court decisionRead the full story...Reprinted courtesy of
Michael B. Marois, BloombergMr. Marois may be contacted at
mmarois@bloomberg.net