IoT: Take Guessing Out of the Concrete Drying Process
February 06, 2019 —
Aarni Heiskanen - AEC BusinessFlooring, tiling, or painting on a concrete surface that is insufficiently dry can end up being a disaster. An experimental project recently used IoT sensors and AI to determine when it is safe to start finishing concrete surfaces.
Haste and Imperfect Conditions Lead to Failure
To successfully first cure and then dry concrete requires specific conditions. You need to maintain a temperature higher than 10°C and a relative humidity of greater than 80 percent in the concrete.
Once the concrete is hardened, you have to make sure that it is dry enough for finishing. Typically, the relative humidity should not exceed 82 percent. Some flooring materials require a humidity of less than 75 percent for successful application.
Read the court decisionRead the full story...Reprinted courtesy of
Aarni Heiskanen, AEC BusinessMr. Heiskanen may be contacted at
aec-business@aepartners.fi
Peckar & Abramson Once Again Recognized Among Construction Executive’s “Top 50 Construction Law Firms™”
July 02, 2024 —
Peckar & Abramson, P.C.Peckar & Abramson, P.C. (P&A) is pleased to announce that it has once again been ranked among the top of Construction Executive’s (CE) “The Top 50 Construction Law Firms™.” P&A has been recognized in this manner since 2019, the inaugural year of the publication’s rankings.
According to CE, its 2024 ranking was the result of a rigorous and comprehensive survey that invited numerous U.S. law firms with a construction practice to participate. The data collected focused on unique metrics such as the firm’s construction practice, number of attorneys and clients, and year of establishment. CE’s algorithm meticulously weighed these factors, among others, to determine the ranking, ensuring the credibility and accuracy of the recognition.
Firm Chair
Steven M. Charney commented, “We are honored to be recognized as one of Construction Executive’s “Top 50 Construction Law Firms.” This recognition serves as a resounding testament to our commitment to the construction industry and our team’s hard work and dedication. We remain committed to providing exceptional legal services to our clients and striving for excellence in all we do.”
The complete rankings and profile are available
here.
Read the court decisionRead the full story...Reprinted courtesy of
Peckar & Abramson, P.C.
BHA Sponsors the 9th Annual Construction Law Institute
January 21, 2016 —
CDJ STAFF Bert L. Howe & Associates, Inc. is proud to be partnering with the Florida Bar Continuing Legal Education Committee and the Construction Law Committee of the Florida Bar Real Property, Probate and Trust Law Section, as a sponsor and exhibitor at 9th Annual Construction Law Institute to be held March 11th, 12th & 13th, 2016 at the JW Marriott Orlando Grande Lakes in Orlando.
With offices in Miami serving all of Florida, Bert L. Howe & Associates, Inc. (BHA) offers the experience of over 20 years of service to carriers, defense counsel, and insurance professionals as designated experts in nearly 6,000 cases. BHA’s staff encompasses a broad range of licensed and credentialed experts in the areas of general contracting and specialty trades, as well as architects, and both civil and structural engineers, and has provided services on behalf of developers, general contractors and sub-contractors.
BHA’s experience covers the full range of construction defect litigation, including single and multi-family residential (including high-rise), institutional (schools, hospitals and government buildings), commercial, and industrial claims. BHA specializes in coverage, exposure, premises liability, and delay claim analysis as well.
As the litigation climate in Florida continues to change, and as the number of construction defect and other construction related cases continues to rise, it is becoming more important for contractors and builders here to be aggressive in preparing for claims before they are made, and in defending against those claims once they are filed. Since 1993, Bert L. Howe & Associates has been an industry leader in providing construction consulting services, and has been a trusted partner with builders and insurance carriers, both large and small, across the Western and Southern United States. Here in Florida, we have been providing construction defect and construction-claims related forensic expert services for the past decade with a proven track record of successful results.
For those of you planning on attending the conference, or those who may know someone who will be, we encourage you to stop by the BHA booth and we welcome the opportunity to discuss further the broad range of services provided by BHA.
For your convenience, here is a link to the registration page for the 9th Annual Construction Law Institute:
http://www.floridabar.org/FBWEB/CLEReg.nsf/zLocations2/MAOS-A4UK4Z?OpenDocument
Read the court decisionRead the full story...Reprinted courtesy of
Approaches to Managing Job Site Inventory
January 04, 2018 —
Jessica Stark - Construction InformerOriginally Published by CDJ on August 30, 2017
There is no question that organization on the job site can mean the difference between efficient performance and costly errors. A simple mistake can cost a company thousands, which is why details are carefully articulated and supervisors become better scrutinizers than magazine editors. But for some reason, many companies don’t consider managing job site inventory under this same attentive category, or perhaps they don’t know about the technology available to help them do it.
For contractors, keeping track of every piece of material and equipment lowers losses and keeps crews busy. This is especially true for contractors in the trades who often have specialized equipment in inventory such as power supplies, HVAC “smart energy” components or inspection equipment. Once everything is accounted for, the possibility of loss is decreased and there’s a chance to evaluate the use of all materials and equipment. This can show the efficiency of allotted resources. Is there enough equipment on the site to get tasks completed? Is there a need for more? Less? Having excess equipment can sometimes prepare a crew for problem scenarios. But it can also mean the construction company is overpaying for unneeded resources. However, the only way to know is by effectively managing job site inventory. That includes all equipment and materials
Read the court decisionRead the full story...Reprinted courtesy of
Jessica Stark, Construction Informer
Michigan Court of Appeals Remands Construction Defect Case
February 14, 2022 —
Tred R. Eyerly - Insurance Law HawaiiAfter its prior decision holding there was no coverage for faulty workmanship was remanded by the Michigan Supreme Court, the Court of Appeals remanded to the trial court. Skanska United States Bldg. v. M.A.P. Mech. Contrs., 2021 Mich. App. LEXIS 7336 (Mich. Ct. App. Dec. 28, 2021). The post summarizing the Supreme Court decision is here.
Skanska USA Building was the construction manager on a renovation project at a medical center. Skanska subcontracted the heating and cooling portion of the project to defendant M.A.P. MAP held a CGL policy from Amerisure. Skanska and the medical center were named as additional insureds.
MAP installed a steam boiler and related piping for the heating system. When completed, the heating system did not function properly. MAP installed some of the expansion joints backwards, causing damage to concrete, steel, and the heating system.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
House of the Week: Spanish Dream Home on California's Riviera
July 30, 2014 —
Emily Heffter – BloombergFamous clients of renowned Los Angeles architect Richard Landry are not known for their restraint.
The Brentwood estate he designed for Tom Brady and Gisele Bundchen has a moat and just sold to Dr. Dre for $40 million. Michael Jackson died in a home Landry designed (a rental), and he has designed luxurious mansions for Wayne Gretzky, Michael Bolton, Mark Wahlberg and Kenny G.
Still, homeowner Lorna Auerbach did something unique when Landry started designing her dream home in Pacific Palisades: She flew him to Spain, with her, for 10 days.
Read the court decisionRead the full story...Reprinted courtesy of
Emily Heffter, Bloomberg
Vallagio v. Metropolitan Homes: The Colorado Court of Appeals’ Decision Protecting a Declarant’s Right to Arbitration in Construction Defect Cases
May 20, 2015 —
David M. McLain – Colorado Construction LitigationOn May 7th, the Colorado Court of Appeals issued its much anticipated ruling in Vallagio at Inverness Residential Condominium Association, Inc. v. Metropolitan Homes, Inc., et al., 2015COA65 (Colo. App. May 7, 2015). By way of background, the Vallagio at Inverness Residential Condominiums were developed by Metro Inverness, LLC, which also served as the declarant for its homeowners association. Metropolitan Homes was Metro Inverness’ manager and the general contractor on the project. Greg Krause and Peter Kudla served as declarant-appointed members of the Association’s board during the period of declarant control.
When it set up the Association, Metro Inverness included within the Association’s declaration a mandatory arbitration provision specifically for construction defect claims. This provision stated that it “shall not ever be amended without the written consent of Declarant and without regard to whether Declarant owns any portion of the Real Estate at the time of the amendment.”
Read the court decisionRead the full story...Reprinted courtesy of
David M. McLain, Higgins, Hopkins, McLain & Roswell, LLCMr. McLain may be contacted at
mclain@hhmrlaw.com
Pay Loss Provision Does Not Preclude Assignment of Post-Loss Claim
July 30, 2015 —
Tred R. Eyerly – Insurance Law HawaiiThe court determined that a policy's loss payment provision did not bar a post-loss assignment. One Call Prop. Servs. v. Sec. First Ins. Co., 2015 Fl. App. LEXIS 7643 (Fla. Ct. App. May 20, 2015).
After One Cell performed emergency water removal for the insured, the insured assigned his rights to policy proceeds as payment. One Cell alleged that Security First refused to reimburse the insured adequately for the services provided. One Cell filed suit, and Security First moved to dismiss. The trial court granted the motion based upon the policy's non-assignment provision.
One Cell appealed. One Cell argued post-loss assignments were valid under Florida law even when the policy contained an anti-assignment provision, and the right to payment accrued on the date of the loss.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com