How to Determine the Deadline for Recording a California Mechanics Lien
September 17, 2015 —
William L. Porter, Esq. – Porter Law Group BulletinThe California Mechanics Lien is one of the most valuable collection devices available to contractors, subcontractors and suppliers who are unpaid for work performed and materials supplied in relation to a California private works construction project. The mechanics lien allows the claimant to sell the property where the work was performed in order to obtain payment. As noted below, in order to pursue this remedy, certain deadlines must be met.
Know Your Mechanics Lien Filing Deadlines Generally
Working within deadlines is absolutely crucial to preserving mechanics lien rights under California law. The deadlines differ, depending on whether you are a ”direct” contractor, also known as “original” or “prime” contractor (one who contracts directly with the property owner) or a subcontractor or material supplier. The primary differences are that the direct contractor is only required to serve the “Preliminary Notice” on the Construction Lender (Civil Code section 8200-8216), whereas the subcontractor and material supplier must serve not only the Construction Lender, but also the Owner and Direct Contractor (see Civil Code section 8200(e)). Another difference is that a direct contractor has a longer period of time in which to record a mechanics lien after a valid “notice of completion” or a “notice of cessation” has been recorded (Civil Code sections 8180-8190), (60 days for original contractors as compared to 30 days for subcontractors and suppliers – See Civil Code sections 8412 and 8414).
Read the court decisionRead the full story...Reprinted courtesy of
William L. Porter, The Porter Law GroupMr. Porter may be contacted at
bporter@porterlaw.com
Thank Your Founding Fathers for Mechanic’s Liens
August 04, 2015 —
Craig Martin – Construction Contract AdvisorYep, our founding fathers, Thomas Jefferson and James Madison specifically, Craig Martin, Construction Attorney Lamson Dugan & Murray LLPwere responsible for proposing the first mechanic’s lien laws in the United States. Mechanic’s liens were not a new concept when the first law was passed in the United States; France, Spain and other countries already had them. But, in England, where landownership was limited to the upper classes, the concept of giving a tradesman an interest in the land for his labors was a truly foreign concept.
The Early Years—Pre Mechanic Lien
In the 1700s, there was no right to a mechanic’s lien. The possession of land was never deemed to be changed by its improvement and the laborer or material supplier was held to have acquired no right of lien in the property. The only remedy the laborer or material supplier had was to bring an action against the land owner. If the laborer or material supplier obtained a judgment, he would acquire the lien of a judgment creditor. A Treatise on the law of Mechanics’ Liens on Real and Person Property, 1893.
Read the court decisionRead the full story...Reprinted courtesy of
Craig Martin, Lamson, Dugan and Murray, LLPMr. Martin may be contacted at
cmartin@ldmlaw.com
Contractors Admit Involvement in Kickbacks
December 09, 2011 —
CDJ STAFFTwo New Jersey contractors have pleaded guilty to charges that they made false representations for a government contract in a case related to kickbacks for construction work done in two school districts. New Jersey is recommending that the two men, Martin Starr and Stephen Gallagher, will each pay $50,000 in penalties, serve up to a year in jail, and be unable to accept public contracts for five years.
Last month, another individual in the case, Kenneth Disko, who had been the engineer for the school district, pleaded guilty on a similar charge. In addition to a $50,000 penalty, he will be serving three to five years in prison. A fourth conspirator, Robert Berman, the former business administrator for one of the school districts, has to pay a $13,000 fine and cooperate with the investigation. He is also barred from public employment in New Jersey and has been terminated from his position.
Starr admitted to preparing fictitious quotes which appeared to be from other contractors in order that his firm would seem to be the lowest bidder. Gallagher helped in preparing the fictitious bids and also provided cash kickbacks to Disko.
Read the full story…
Read the court decisionRead the full story...Reprinted courtesy of
Washington Court Tunnels Deeper Into the Discovery Rule
July 09, 2019 —
Lian Skaf - The Subrogation StrategistOften times, properly analyzing when a statute of limitations begins to run – not just how long it runs – is crucial to timely pleading. In Dep’t of Transp. v. Seattle Tunnel Partners, 2019 Wash.App. LEXIS 281 (Was. Ct. App. Feb. 5, 2019), Division Two of the Court of Appeals of Washington addressed when the discovery rule starts the statute of limitations clock on a negligence cause of action. The court held that the statute of limitations begins to run when the plaintiff knows that the factual elements of the claim against the defendant exist. The clock starts to run even if the plaintiff wants to investigate the possibility of other contributing factors or the defendant identifies opposing viewpoints on the theory of the claim.
In this matter, the Washington State Department of Transportation (WSDOT) contracted with an engineering firm, WSP USA, Inc. (WSP), for an evaluation of the Alaskan Way Viaduct in 2001. As part of this project, WSP retained the services of Shannon and Wilson (S&W), another engineering firm, to conduct geological profile logs, groundwater-pumping tests, and prepare technical memoranda. In 2002, WSP and S&W installed a pumping well with an eight-inch steel casing (TW-2). In 2009, apparently based on the work done by WSP and S&W, WSDOT determined that a bored underground tunnel was the best option for replacing the viaduct.
Read the court decisionRead the full story...Reprinted courtesy of
Lian Skaf, White and Williams LLPMr. Skaf may be contacted at
skafl@whiteandwilliams.com
Miller Act Payment Bond Surety Bound to Arbitration Award
December 29, 2020 —
David Adelstein - Florida Construction Legal UpdatesHere is an interesting case binding a Miller Act payment bond surety to an arbitration award against its prime contractor (bond principal) that it received sufficient notice of. Notice is the operative word. The surety could have participated in the arbitration, elected not to, and when its prime contractor (bond principal) lost the arbitration, it was NOT given another bite out of the apple to litigate facts already been decided.
In BRC Uluslararasi Taahut VE Ticaret A.S. v. Lexon Ins. Co., 2020 WL 6801933 (D. Maryland 2020), a prime contractor was hired by the federal government to make security upgrades and interior renovations to a United States embassy in the Czech Republic. The prime contractor hired a subcontractor to perform all of the installed contract work. The prime contractor terminated the subcontractor for default during the course of construction.
The subcontractor demanded arbitration in accordance with the subcontract claiming it was wrongfully terminated. The subcontractor also filed a lawsuit asserting a Miller Act payment bond claim against the prime contractor’s surety (as well as a breach of contract action against the prime contractor). The subcontractor made clear it intended to pursue its claims in arbitration and hold the payment bond surety jointly and severally liable. The parties agreed to stay the lawsuit since the facts were identical to those being arbitrated. The arbitration went forward and an award was entered in favor of the subcontractor and against the prime contractor for approximately $2.3 Million.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Personal Injury Claims – The Basics
February 11, 2019 —
Jessica L. Mulvaney - Bremer Whyte Brown & O'Meara LLPPersonal injury claims can manifest in multiple ways, and while procedurally many may be similar, no two cases are ever exactly alike. The basis of all personal injury claims is a person suffering some injury or harm. The laws related to personal injury claims are in place to allow for the party at fault to be held responsible, and the injured party to seek a remedy and be “made whole” after suffering injury.
Typical causes of action for personal injury claims can include intentional actions (torts) against an individual, negligence, or strict liability. At the heart of all injury claims are the issues of liability and damages. Liability is the determination of whether the defendant being accused of the harm is responsible, i.e. caused the injury and resulting harm. Damages is a concept that encompasses the harm a person suffered as a result of the injury. For personal injury, typical damages can include medical bills, loss of earnings, future medical care, and pain and suffering.
Read the court decisionRead the full story...Reprinted courtesy of
Jessica L. Mulvaney, Bremer Whyte Brown & O'Meara LLP
Meet the Forum's In-House Counsel: ERIN CANNON-WELLS
June 26, 2023 —
Jessica Knox - The Dispute ResolverCompany: Keller North America, Inc.
Email: ecannon@keller-na.com
Website: https://www.keller-na.com/
Under Grad: University of Delaware (Bachelor of Civil Engineering 2000)
Grad School: The University of Texas (Master of Civil Engineering 2002)
Law School: Howard University (JD 2008)
States Where Company Operates/Does Business: Throughout the US and Canada
Q: Describe your background and the path you took to becoming in-house counsel.
A: I studied civil engineering in undergrad and finally found my "calling" when I took a construction course, prompting me to pursue a master's in construction engineering. I started my career at Turner, holding various engineering positions, the last of which introduced me to the "contracting" side of construction. I was inspired to go to law school (in hopes of becoming an in-house lawyer there). After law school, I joined BigLaw, but maintained my desire to practice construction law. I then jumped to a small construction practice group at a mid-size firm, and the mentoring and experience there was everything I could hope for (but for the looming business development and billable hour requirements). From there, I became the sole in-house counsel for a large cement manufacturer and was a true construction generalist. Now I am part of a great legal team for a leading geotechnical specialty contractor. My moves were strategic, and I'm pleased to say that this is the very career I went to law school to have.
Read the court decisionRead the full story...Reprinted courtesy of
Jessica Knox, Stinson LLPMs. Knox may be contacted at
jessica.knox@stinson.com
Priority of Liability Insurance Coverage and Horizontal and Vertical Exhaustion
June 22, 2020 —
David Adelstein - Florida Construction Legal UpdatesRecently, I participated in a webinar involving the horizontal and vertical exhaustion of insurance coverage. Say what?
This pertains to the PRIORITY of liability insurance coverage and the interface between a general contractor’s (or upstream party’s) primary insurance and the subcontractor’s (or downstream party’s) excess insurance, particularly when the general contractor is required to be indemnified by the subcontractor and named as an additional insured under the subcontractor’s liability policies.
For instance, let’s assume the general contractor has a $2M primary policy and a $5M excess policy. Its subcontractor has a $1M primary and a $5M excess policy. The general contractor is an additional insured under the subcontractor’s policies and the subcontractor is required to contractually indemnify the general contractor. An issue occurs caused by the subcontractor’s negligence resulting in a $5M judgment against the general contractor and the subcontractor.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com