Common Construction Contract Provisions: Indemnity Provisions
January 19, 2017 —
David R. Cook Jr. - Autry, Hanrahan, Hall & Cook, LLP BlogUpcoming blog posts will focus on common contract provisions found in construction contracts. Such provisions are not solely limited to construction contracts and can be found in many other types of business contracts as well. This post will highlight indemnity clauses.
An indemnity clause is a common contract provision used to allocate risk between parties to a contract. The clause obligates one party (the Indemnitor) to protect the other party (the Indemnitee) from certain losses, typically arising from claims of third parties. It may require the Indemnitor to reimburse the Indemnitee for losses or expenses, or satisfy judgments, or even defend the Indemnitee in a lawsuit.
Read the court decisionRead the full story...Reprinted courtesy of
David R. Cook Jr., Autry, Hanrahan, Hall & Cook, LLPMr. Cook may be contacted at
cook@ahclaw.com
Musk Backs Off Plan for Tunnel in Tony Los Angelenos' Backyard
December 19, 2018 —
Sarah McBride & Edvard Pettersson - BloombergElon Musk’s futuristic tunneling company, Boring Co., is no longer embroiled in a lawsuit with the residents of West Los Angeles.
A May lawsuit aimed at stopping the Boring Co.’s proposed tunnel under Sepulveda Boulevard has been settled, according to a notice filed at the Superior Court of Los Angeles County. Neighbors in the Brentwood and Sunset Boulevard areas, near the proposed tunnel, had sued the City of Los Angeles over the Boring Co.’s plans to build a test tunnel without going through an environmental review process, as recommended in April by the city’s public works committee.
Read the court decisionRead the full story...Reprinted courtesy of
Sarah McBride & Edvard Pettersson, Bloomberg
Embracing Generative Risk Mitigation in Construction
February 12, 2024 —
Georgia Stillwell - Construction ExecutiveProject delays have long plagued the construction industry, with risk often identified as the primary culprit. However, finding effective solutions to mitigate risk on complex projects has remained daunting. Traditional methods for simulating risk primarily focus on extending project timelines, overlooking the diverse range of opportunities available for risk mitigation. With the construction industry’s digital transformation, generative methodologies have emerged to handle complex decision-making in uncertain situations. This article aims to shed light on the limitations of existing risk modeling and introduce a novel approach known as generative risk mitigation to enhance decision-making under deep uncertainty.
According to McKinsey, 98% of megaprojects experience cost overruns exceeding 30%. Project delays have become so pervasive that the industry has grown accustomed to them. For example, in 2022, the UK government issued ‘
The Green Book,’ which requires contingency funds in projects, such as a 44% contingency budget for standard civil projects. This implies that for a $100 million project, you should allocate $144 million to manage expected risks. There is no denying significant academic literature on the root cause of these delays: it is ‘risk,’ and there is an entire industry based on it.
Conversations with project directors and risk experts reveal the same issue, different project. And that issue is that we cannot easily forecast risk, qualify the impacts or fully understand the opportunities that exist to mitigate risks and make timely decisions. A method that will finally help us overcome this has emerged within the industry.
Reprinted courtesy of
Georgia Stillwell, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Genuine Dispute Over Cause of Damage and Insureds’ Demolition Before Inspection Negate Bad Faith and Elder Abuse Claims
June 30, 2016 —
Christopher Kendrick & Valerie A. Moore – Haight Brown & Bonesteel LLPIn Paslay v. State Farm General Ins. Co. (No. B265348, filed 6/27/16), a California appeals court found triable issues of fact regarding whether State Farm breached its contract in paying a water loss, but affirmed summary adjudication for the insurer on bad faith and elder abuse claims based on the genuine dispute doctrine.
Reprinted courtesy of
Christopher Kendrick, Haight Brown & Bonesteel LLP and
Valerie A. Moore, Haight Brown & Bonesteel LLP
Mr. Kendrick may be contacted at ckendrick@hbblaw.com
Ms. Moore may be contacted at vmoore@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Miller Act Bond Claims Subject to “Pay If Paid”. . . Sometimes
November 04, 2019 —
Christopher G. Hill - Construction Law MusingsThe Federal Miller Act is a great tool that subcontractors and suppliers on Federal projects can use for collection of wrongfully withheld amounts due. However, as a recent federal case from the Eastern District of Virginia points out, the construction contract’s terms affect when a subcontractor or supplier can use this great collection tool and how much it can recover.
In Aarow v Travelers the Court looked at the interaction between a typical termination clause, a “pay when paid” clause, and the Miller Act. The key facts are these. The general contractor on the project at issue, Syska, did not get paid some disputed amounts by the owner and subsequently did not pay Aarow, the plaintiff and a subcontractor on the project. Aarow then refused to continue work and was terminated by Syska who then took over the completion of the work. Aarow sued, seeking damages for the value of its work prior to the termination. Travellers, the surety defended stating that, if Aarow was properly terminated for cause by Syska, then Aarow was not entitled to payment under the contract until such time as the work was completed and accepted by the owner. The termination clauses are set out in the linked opinion.
The Court agreed with Travelers, stating that the pay when paid clause created a situation whereby Aarow could not stop work merely because of a non-payment by Syska attributed to non-payment by the owner. The Court was clear in stating that the Miller Act trumps “pay when paid” in instances where the only cause for non-payment is non-payment by an owner. The Court then reasoned that it is the interaction between the termination and “pay when paid” provisions, and not the “pay when paid” clause itself, that exonerated Travelers because it created the default by Aarow due to its refusal to continue work. In short, Aarow was properly terminated for cause because it left the job without justification and therefore Travelers was not liable.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Be Proactive, Not Reactive, To Preserve Force Majeure Rights Regarding The Coronavirus
March 30, 2020 —
David Adelstein - Florida Construction Legal UpdatesIf you are involved in construction, NOW is the time to consider the potential force majeure impacts associated with the pandemic Coronavirus. Things are beginning to drastically change on a minute-by-minute basis. From travel restrictions, to the suspension or cancellation of events on an international level, to company-wide policies and restrictions, the global uncertainty has led to the possibility that a force majeure delay will occur. Thinking otherwise is not being proactive. The Coronavirus, and the impacts / delays associated therewith, is beyond anyone’s control. Due to the uncertainty, it is hard to fathom at this time a reasonable challenge to someone’s reaction to this concern or their companywide response to the concern.
If you are a contractor, subcontractor, or even a supplier, my suggestions would be as follows:
- Revisit your contracts and see what type of force majeure language it has – anything relating to delays beyond your control or epidemics;
- Examine to see whether you have a basis for additional compensation AND additional time;
- Examine what type of notice you are required to provide for force majeure events;
- Be proactive – send notice now of the potentiality that this pandemic can impact / delay the job –no one should take offense to this letter as this pandemic has impacted all walks of life;
- If an impact occurs, send follow-up notice accordingly to ensure rights under the contract are preserved; and
- For future contracts, incorporate language that specifically addresses epidemics and pandemics now that the occurrence of this issue has become real.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Potential Pitfalls Under the Contract Disputes Act for Federal Government Contractors
February 28, 2018 —
Sarah K. Carpenter – Smith Currie PublicationsThe Contract Disputes Act (CDA) governs monetary and non-monetary disputes arising out of contracts or implied-in-fact contracts between the federal government and contractors. Because the CDA is an exclusive remedy, it is important that contractors be wary of the many pitfalls that may be encountered by a contractor seeking to assert a claim against the government under the CDA.
The pitfalls faced by a contractor under the CDA can arise before a contractor becomes aware of a potential claim. Pursuant to the Federal Acquisition Regulation (FAR) § 43.204(c), a contracting officer should include in any supplemental agreement, including any change order, a Contractor’s Statement of Release which requires a contractor to execute a broad release of the government from any and all liability under the contract. As a result of this FAR provision, in executing a routine change order, a contractor may inadvertently release its right to pursue a potential claim under the CDA. A contractor should always review any release language prior to executing a supplemental agreement or change order with the government.
Read the court decisionRead the full story...Reprinted courtesy of
Sarah K. Carpenter, Smith CurrieMs. Carpenter may be contacted at
skcarpenter@smithcurrie.com
Indicted Union Representatives Try Again to Revive Enmons
June 22, 2016 —
Wally Zimolong – Supplemental ConditionsThe
Boston Globe reports that the Massachusetts AFL-CIO has filed a friend of the court brief seeking to have the indictment of five members of the Teamsters Union in Boston dismissed. The Teamsters members are facing federal charges that they extorted non-union contractors and owners that employed non-union contractors. The Massachusetts AFL-CIO is arguing that under the Supreme Court’s 1972 decision in
U.S. v. Enmons the Teamsters alleged conduct was in furtherance of a legitimate union objective and, therefore, no illegal.
Read the court decisionRead the full story...Reprinted courtesy of
Wally Zimolong, Supplemental ConditionsMr. Zimolong may be contacted at
wally@zimolonglaw.com