Don’t Kick the Claim Until the End of the Project: Timely Give Notice and Preserve Your Claims on Construction Projects
December 10, 2015 —
Christopher G. Hill – Construction Law MusingsFor this week’s Guest Post Friday, we welcome
Tara L. Chadbourn. Tara is an attorney with
ReavesColey PLLC in Chesapeake, VA, where she concentrates her practice on construction law, litigation and commercial litigation. Tara counsels owners, contractors, subcontractors and materials suppliers in various government and commercial construction matters. Tara can be reached at tara.chadbourn@reavescoley.com.
You may have experienced and have certainly heard of the scenario in which a contractor waits to address a claim as part of project closeout, only to realize the applicable deadline has already passed. While there may have been discussions about claims during the course of the project, contractors cannot rely upon oral conversations about outstanding claims. Instead, contractors must be vigilant in satisfying notice requirements and preserving claims. While entitlement must still be proven, a contractor’s chances of recovery increase greatly if the contractor abides by notice requirements and consciously preserves claims in the following ways.
Contractors Must Acquaint Themselves with Contractual Notice Provisions:
Many prime and subcontract agreements contain stringent notice provisions that require the contractor to give notice within a certain time period or else the claim is expressly waived. The deadline for notice is often only a few days after the occurrence giving rise to the claim or the contractor becoming aware of the claim. To avoid waiver, contractors must carefully review their contracts for provisions requiring notice of a claims for adjustment for a variety of situations to include unforeseen site conditions, trade sequencing changes, project delay or scope of work changes.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, Law Office of Christopher G. Hill, PCMr. Hill may be contacted at
chrisghill@constructionlawva.com
Demonstrating A Fraudulent Inducement Claim Or Defense
May 18, 2020 —
David Adelstein - Florida Construction Legal UpdatesIn a recent case, Florida’s Fourth District Court of Appeal reversed a trial court’s denial of a motion for a temporary injunction sought by an employer due to an independent contractor’s violation of a non-compete and non-solicitation provision in an employment / independent contractor agreement (“employment agreement”). You can find more on this case and the enforcement of the non-compete and non-solicitation clause
here.
A worthy discussion in this case centers on the independent contractor’s fraudulent inducement defense. Specifically, the independent contractor, as a defense to the injunction, claimed that he was fraudulently induced into entering into the employment agreement because the employer promised he would make a certain amount of money and he would work predominantly in one geographic location. The employment agreement contained NO such representations. Instead, the employment agreement contained a fee and services schedule and the independent contractor would be compensated based on that schedule. It stated nothing as to the independent contractor only having to work, or predominantly working, in one geographic location, or that the independent contractor would be guaranteed “X” amount of money working in that location. Why is this important?
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
First Circuit: No Coverage, No Duty to Investigate Alleged Loss Prior to Policy Period
May 18, 2020 —
Eric B. Hermanson & Austin D. Moody - White and WilliamsOn April 1, 2020, the First Circuit, applying Massachusetts law, issued a potentially useful decision addressing the Montrose “known loss” language in ISO Form CGL policies. In Clarendon National Insurance Company v. Philadelphia Indemnity Insurance Company,[1] the court applied this language to allow denial of defense for claims of recurring water infiltration that began before the insurer’s policy period, and it found an insurer had no duty to investigate whether the course of property damage might have been interrupted, or whether other property damage might have occurred during the policy period, so as to trigger coverage during a later policy.
In the underlying dispute, a condominium owner (Doherty) asserted negligence claims against her association’s property management company (Lundgren) stemming from alleged water infiltration into her condominium. The complaint said leaks developed in 2004 in the roof above Doherty’s unit, and repairs were not made in a timely or appropriate manner. The following year, the complaint said, a Lundgren employee notified Doherty that the threshold leading to her condominium's deck was rotting. In February 2006, Doherty discovered a mushroom and water infiltration on the threshold and notified Lundgren. At that time, Lundgren asked its maintenance and repair contractor (CBD) to replace the rotting threshold. According to the complaint, CBD did not do this repair in a timely manner and left debris exposed in Doherty’s bedroom.
In March 2006, the complaint said, a mold testing company hired by Lundgren found hazardous mold in Doherty's unit, caused by water intrusions and chronic dampness. Lundgren’s attempts at remediation were ineffectual. In September 2008, Doherty's doctor ordered her to leave the condominium and not to return until the leaks were repaired and mold was eliminated.
Reprinted courtesy of
Eric B. Hermanson, White and Williams and
Austin D. Moody, White and Williams
Mr. Hermanson may be contacted at hermansone@whiteandwilliams.com
Mr. Moody may be contacted at moodya@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of
Lending Plunges to 17-Year Low as Rates Curtail Borrowing
April 15, 2014 —
Kathleen M. Howley, Zachary Tracer and Heather Perlberg – BloombergWells Fargo (WFC) & Co. and JPMorgan Chase & Co., the two largest U.S. mortgage lenders, reported a first-quarter plunge in loan volumes that’s part of an industry-wide drop off. Lenders made $226 billion of mortgages in the period, the smallest quarterly amount since 1997 and less than one-third of the 2006 average, according to the Mortgage Bankers Association in Washington.
Lending has been tumbling since mid-2013 when mortgage rates jumped about a percentage point after the Federal Reserve said it might taper stimulus spending. A surge in all-cash purchases to more than 40 percent has kept housing prices rising, squeezing more Americans out of the market. That will help push lending down further this year, according to the association.
Ms. Howley may be contacted at kmhowley@bloomberg.net; Mr. Tracer may be contacted at ztracer1@bloomberg.net; Ms. Perlberg may be contacted at hperlberg@bloomberg.net
Read the court decisionRead the full story...Reprinted courtesy of
Kathleen M. Howley, Zachary Tracer and Heather Perlberg, Bloomberg
HVAC System Collapses Over Pool at Gaylord Rockies Resort Colorado
June 12, 2023 —
Jennifer Seward - Engineering News-RecordThe collapse May 6 of the HVAC system above an indoor pool at the Gaylord Rockies Resort near Denver sent six people to local hospitals, two with life-threatening injuries. An estimated 50 to 100 people were in the water or on the pool deck as pieces of the system fell into the pool and hot tub.
Reprinted courtesy of
Jennifer Seward, Engineering News-Record
Ms. Seward may be contacted at sewardj@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Flood-Threat Assessment Finds Danger Goes Far Beyond U.S. Homes
October 18, 2021 —
Leslie Kaufman, Rachael Dottle & Mira Rojanasakul - BloombergIf the floods don’t get you, lack of electricity or a swamped hospital might.
Nearly a quarter of U.S. critical infrastructure—utilities, airports, police stations and more—is at risk of being inundated by flooding, according to a new report by First Street Foundation, a Brooklyn nonprofit dedicated to making climate risk more visible to the public.
Around 25% of national critical infrastructure is at risk.
Roughly 14% of Americans’ properties face direct risk from major storms, but the study shows danger extends far from those property lines.
Reprinted courtesy of
Leslie Kaufman, Bloomberg,
Rachael Dottle, Bloomberg and
Mira Rojanasakul, Bloomberg Read the court decisionRead the full story...Reprinted courtesy of
Sellers' Alleged Misrepresentation Does Not Amount To An Occurrence
November 30, 2020 —
Tred R. Eyerly - Insurance Law HawaiiThe insurer successfully established on summary judgment that the insureds' alleged misrepresentation in the sale of a condominium was not an occurrence. Novak v. St. Maxent-Wimberly House Condo., 2020 U.S. Dist. LEXIS 167397 (E.D. La. Sept. 14, 2020).
State Farm issued the sellers a condominium unit owner's policy. The buyers sued the sellers, contending the sellers had made misrepresentations in the sale process. The sellers allegedly failed to disclose defects in the condominium before and at the time of the sale. State Farm intervened, seeking a declaration that it was not required to defend or indemnify the sellers because there was no occurrence.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Indiana Appellate Court Allows Third-Party Spoliation Claim to Proceed
August 01, 2023 —
Ryan Bennett - The Subrogation StrategistIn Safeco Insurance Company of Indiana as Subrogee of Ramona Smith v. Blue Sky Innovation Group, Inc., et al, No. 22A-CT-1924, 2023 Ind. App. LEXIS 157, the Court of Appeals of Indiana (Appellate Court) reversed a trial court ruling that granted the motion to dismiss filed by Michaelis Corporation (Michaelis), a restoration company. The Appellate Court ruled that the trial court erred in dismissing the plaintiff’s spoliation and negligence claims against Michaelis, who discarded evidence relating to the cause of the fire at issue.
The plaintiff’s insured owned a home in Indianapolis, Indiana. On Halloween night in 2019, a fire occurred at the property. The plaintiff’s representatives preliminarily determined that the fire may have been caused by a digital dehydrator within the kitchen. Michaelis had a representative present at the site inspection and was allegedly told to preserve the kitchen area. That area was taped off with “caution” tape. Michaelis also placed a tarp over the kitchen to prevent weather damage. Despite the instructions and precautions, Michaelis demolished the kitchen and discarded the dehydrator along with other fire debris.
Read the court decisionRead the full story...Reprinted courtesy of
Ryan Bennett, White and Williams LLPMr. Bennett may be contacted at
bennettr@whiteandwilliams.com