Significant Issues Test Applies to Fraudulent Claims to Determine Attorney’s Fees
January 13, 2017 —
David Adelstein - Florida Construction Legal UpdatesConstruction lienors need to appreciate on the frontend that recovering statutory attorney’s fees in a construction lien action is NOT automatic—far from it. This is because the prevailing party for purposes of attorney’s fees in a construction lien action is determined by the “significant issues test,” a subjective test with no bright line standards based on who the trial court finds prevailed on the significant issues in the case. If you want to talk about the subjective and convoluted nature of recovering attorney’s fees in a construction lien action under the significant issues test, a recent opinion by the Fourth District Court of Appeal is unfortunately another nail in the coffin.
In Newman v. Guerra, 2017 WL 33702 (Fla. 4th DCA 2017), a contractor recorded a construction lien on a residential renovation project and filed a lien foreclosure lawsuit. The homeowner countersued the contractor and asserted a fraudulent lien claim pursuant to Florida Statute s. 713.31. An evidentiary hearing was held on whether the lien was a fraudulent lien and the trial court held that the lien was fraudulent (therefore unenforceable) because it included amounts that were not lienable under the law. The remaining claims including both parties’ breach of contract claims proceeded to trial. There was no attorney’s fees provision in the contract. At the conclusion of the trial, the court found that the contractor was entitled a monetary judgment on its breach of contract claim.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Florida Construction Legal UpdatesMr. Adelstein may be contacted at
dadelstein@gmail.com
Jury Awards 20 Million Verdict Against Bishop Abbey Homes
April 08, 2014 —
Beverley BevenFlorez-CDJ STAFFA Rockwall County, Texas “jury has awarded a $20.8 million verdict against a Dallas homebuilder for performing substandard work on a local family's home and refusing to accept responsibility,” according to a press release published in The Wall Street Journal.
The lawsuit alleged that “the defendants were aware that the site of the Hales' future Highpoint Lake Estates home had significant foundation defects before construction began. The Hales said Mr. Halsey later promised that his company would take responsibility by fixing the structural defects that arose after construction, but he reneged and refused to repair the problems.”
The award included “damages for the cost of repairs, lost value and additional penalties based on Mr. Halsey's actions and the defendants' ‘grossly negligent’ conduct, including violations of the Texas Deceptive Trade Practices Act. The jury award includes attorneys' fees for the Hales' legal team.”
Read the court decisionRead the full story...Reprinted courtesy of
Project Completion Determines Mechanics Lien Recording Deadline
April 08, 2024 —
William L. Porter - Porter Law GroupThe California mechanics lien is one of the most powerful collection remedies available to contractors, subcontractors and suppliers who are unpaid for work performed and materials supplied in relation to a California private works construction project. The mechanics lien allows the claimant to actually sell the property where the work was carried out in order to obtain payment, entirely of course, against the wishes of the property owner. There are a number of important steps to follow and timelines to be met in order to pursue this remedy.
First, Understand Your Preliminary Notice Deadline
Working within deadlines is absolutely crucial to preserving mechanics lien rights under California law. The deadlines differ, depending on whether you are a “direct” contractor, also known as “original” or “prime” contractor (one who contracts directly with the property owner) or a subcontractor or material supplier. The process begins with the serving of a “preliminary notice” no later than 20 days after the party serving the preliminary notice begins supplying labor or materials to the project. Direct contractors are only required to serve the preliminary notice on the construction lender (Civil Code section 8200-8216), whereas subcontractors and material suppliers must serve not only the construction lender, but also the owner and direct contractor (see Civil Code section 8200(e)).
Read the court decisionRead the full story...Reprinted courtesy of
William L. Porter, Porter Law GroupMr. Porter may be contacted at
bporter@porterlaw.com
For US Cities in Infrastructure Need, Grant Writers Wanted
July 22, 2024 —
Patrick Sisson - BloombergIt’s a big windfall of federal investment. Together, bills like the Inflation Reduction Act, the Bipartisan Infrastructure Law, and the CHIPS Act present a substantial shift in how the US government funds local economic development, clean energy and environmental justice efforts, potentially giving cities and towns a huge boost.
That is, if the nation’s 90,000-plus municipalities and tribal governments can finish filling out all the paperwork.
The trillion-dollar trifecta of Biden administration legislation from 2022 underscores just how important grant writing has become. In many ways, the ability of cities to enact new policies and tap federal resources rests on the desks of the staffers or contract workers who research, write and submit applications for funding. Uncle Sam will cheerfully write a check for cities to install solar panels via Clean Electricity Investment and Production Tax Credits, for example, or provide tax credits for buying electric vehicles. But first, you have to ask.
Read the court decisionRead the full story...Reprinted courtesy of
Patrick Sisson, Bloomberg
Guarantor’s Liability on Partially Secured Debts – The Impacts of Pay Down Provisions in Serpanok Construction Inc. v. Point Ruston, LLC et al.
October 24, 2021 —
Margarita Kutsin - Ahlers Cressman & SleightIn
Serpanok Construction, Inc. v. Point Ruston, LLC, Division Two of the Washington Court of Appeals decided an issue of first impression in Washington—whether a guarantor of a partially secured debt remains liable until the last dollar of the entire debt is paid off. After examining cases from other jurisdictions, the court held that that a guarantor is liable until the underlying debt is paid in full unless the agreement contains an express pay down provision. A pay down provision sets forth the guarantor’s right to reduce its obligation to the extent of any payment toward the debt, and it establishes that the guaranty applies only until an amount equivalent to the guaranteed amount is paid off.
The Serpanok decision addressed several other issues, but the published portion of this part-published case focused on whether an entity involved in a real estate development, Point Ruston LLC, was discharged from its guaranty obligation following a foreclosure sale where the proceeds did not cover the entire debt owed to a subcontractor. Point Ruston LLC, Point Ruston Phase II LLC (“Phase II”), and Century Condominiums (“Century”) were affiliated entities (collectively “Point Ruston parties”) that constructed retail and residential structures on a site in Point Ruston. Serpanok Construction Inc. (“Serpanok”) entered into subcontract agreements with Phase II and Century to perform concrete and steel work on a parking garage and movie theater for the project. Point Ruston LLC was not a party to either subcontract.
Read the court decisionRead the full story...Reprinted courtesy of
Margarita Kutsin, Ahlers Cressman & SleightMs. Kutsin may be contacted at
margarita.kutsin@acslawyers.com
So a Lawsuit Is on the Horizon…
August 10, 2021 —
Sean Donoghue - Construction ExecutiveAs certain as death and taxes, documents will need to be exchanged in the event of a lawsuit. Here is what to expect and a few tips for reducing costs and protecting the case.
What Needs to Be Produced?
Discovery is broad, but proportional to the needs (i.e., usually the dollar value) of the case. Cost reports, bid back up and scheduling information are often at the heart of damages issues in construction disputes. Thus, while it will depend on the nature of the dispute, these items will generally need to be produced.
It is no secret that electronically stored information (ESI) can be a big part of discovery in litigation, particularly in a document intensive industry like construction. In addition to electronically stored project files, expect that the inboxes of employees who are close to the dispute will need to be searched. How many will depend on the size of the dispute and the number of players involved. Hard-drives and text messages of those employees may also be discoverable.
Reprinted courtesy of
Sean Donoghue, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Mr. Donoghue may be contacted at
sdonoghue@eckertseamans.com
Apple to Open Steve Jobs-Inspired Ring-Shaped Campus in April
February 23, 2017 —
Adam Satariano - BloombergApple Inc. co-founder Steve Jobs’ last public event in 2011 was a city council meeting in Cupertino, California, where he presented plans for a sprawling new campus with a spaceship-shaped building and tree-filled park. Apple announced Wednesday that it will begin moving employees into the 2.9 million-square-foot facility in April.
Apple said a new 1,000-seat auditorium at the facility will be named the Steve Jobs Theater in honor of its co-founder, who died four months after his city council presentation and would have turned 62 on Feb. 24.
As with many large-scale construction projects, Apple faced budget overruns and delays. The building cost an estimated $5 billion (though Apple has never said how much), and the opening date had initially been set for 2015.
Read the court decisionRead the full story...Reprinted courtesy of
Adam Satariano, BloombergMr. Satariano may be followed on Twitter @satariano
It Pays to Review the ‘Review the Contract Documents’ Clause Before You Sign the Contract
March 11, 2024 —
Alan Winkler - ConsensusDocsIt is fairly common for a construction contract to include a provision requiring the contractor to perform some level of review of the plans and specifications and perhaps other contract documents as part of their responsibilities. Typically, this provision is found in a section of the contract on the contractor’s responsibilities, although it can be anywhere. Owners and contractors are, with reason, focused on three main issues in reviewing contracts: (1) price, costs, and payments, (2) time and scheduling, and (3) scope of the work. Eyes may glaze over the contractor’s responsibilities section. Not only does it seem to be boilerplate, but industry professionals know what a contractor is supposed to do; in a nutshell, build the project.
An old school type of contractor may regard this role as strictly following the plans and specifications, no matter what they provide. That could lead to a situation where construction comes to a complete stop because, for example, two elements are totally incompatible with each other. If that happens, the contractor would then turn to the owner and architect to ask for a corrective plan and instructions on how to proceed. That may also be accompanied by a request for more time and money while the problem is resolved. The ‘review the contract documents’ clause is designed to avoid this. It is intended to address an understanding that everyone makes mistakes, even architects and engineers whose job it is to design a buildable, functional project. The clause also addresses the understanding that a contractor is more than a rote implementer of plans and specifications because its expertise in building necessarily means the contractor has expertise in understanding the documents that define the construction and how things are put together.
Read the court decisionRead the full story...Reprinted courtesy of
Alan Winkler, Peckar & Abramson, P.C.Mr. Winkler may be contacted at