California’s Right To Repair Act Is The Sole Remedy For Damages For Construction Defects In New Residential Construction
March 14, 2018 —
Mark Johnson – Real Estate Litigation Blog The California Supreme Court ruled in
McMillin Albany LLC et al. v. The Superior Court of Kern County, (1/18/2018) 4 cal. 5th 241, that California’s Right to Repair Act, California Civil Code sections 895 et seq. (“Act”) is the sole remedy for construction defect claims for economic loss and property damages regarding new residential construction. The Act establishes a pre-litigation dispute resolution process that must be followed before filing a construction defect action for new residential construction purchased after January 1, 2003. The Act provides a builder with the right to attempt to repair construction defects before litigation is filed.
The
McMillin ruling resolved a split among two court of appeal decisions regarding the scope of the Act:
Liberty Mutual Insurance Company v. Brookfield Crystal Cove LLC (2013) 219 Cal.App.4th 98 and
Burch v. Superior Court [(2014) 223 Cal.App.4th 1411. Those cases held that the Act is not the exclusive remedy for construction defect lawsuits that allege property damage arising from new residential construction. Therefore owners of new residential construction where construction defects had caused property damage were not required to proceed under the Act and instead could proceed with common law claims.
McMillilin removes that option.
Read the court decisionRead the full story...Reprinted courtesy of
Mark Johnson, Snell & WilmerMr. Johnson may be contacted at
majohnson@swlaw.com
Elon Musk’s Proposed Vegas Strip Transit System Advanced by City Council Vote
January 11, 2021 —
Sarah McBride - BloombergElon Musk’s tunneling company Boring Co. is already building a transit system for Las Vegas convention-goers. Now, he wants to build one for the rest of the city.
On Wednesday, the Las Vegas City Council voted unanimously to advance plans to dramatically expand Musk’s Loop project from a convention center transit system to a citywide network that would include hotels and, one day, potentially even the airport.
The proposed expansion brings the tunnel-based transportation system as far north as Ogden Avenue, near attractions such as the Downtown Container Park and classic casinos like the Golden Nugget. Proposed stops en route include the Arts District and the Stratosphere tower, the spaceship-like landmark that is part of a hotel. The precise location of stations will be determined later in the process, according to documents submitted to the council.
Read the court decisionRead the full story...Reprinted courtesy of
Sarah McBride, Bloomberg
Sometimes You Get Away with Unwritten Contracts. . .
January 20, 2020 —
Christopher G. Hill - Construction Law MusingsI have spoken often regarding the need for a well written construction contract that sets out the “terms of engagement” for your construction project. A written construction contract sets expectations and allows the parties to the contract to determine the “law” of their project. An unwritten “gentleman’s agreement” can lead to confusion, faulty memories, and more money paid to construction counsel than you would like as we lawyers play around in the grey areas.
One other area where the written versus unwritten distinction makes a difference is in the calculation of the statute of limitations. In Virginia, a 5 year statute of limitations applies to written contracts while a 3 year statute of limitations applies to unwritten contracts. This distinction came into stark relief in the case of M&C Hauling & Constr. Inc. v. Wilbur Hale in the Fairfax, Virginia Circuit Court. In M&C Hauling, M&C provided hauling services to the defendant through a subcontract with Hauling Unlimited in 2014, the last of which was in July. M&C provided over 2000 hours of hauling and provided time tickets (that were passed to Mr. Hale on Hauling Unlimited letterhead and signed by Mr. Hale or his agent) and an invoice stating the price term of $75.00 per hour. No separate written contract between M&C and Hauling Unlimited or Mr. Hale existed.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
A Court-Side Seat: As SCOTUS Decides Another Regulatory “Takings” Case, a Flurry of Action at EPA
July 19, 2021 —
Anthony B. Cavender - Gravel2GavelThis is a brief account of some of the important environmental and administrative law cases recently decided.
THE U.S. SUPREME COURT
Pakdel v. City and County of San Francisco
On June 28, 2021, the Supreme Court decided this regulatory “takings” case, and, in a Per Curium opinion, reversed the Ninth Circuit’s ruling that that petitioners had to exhaust their state administrative remedies before they could file this lawsuit under 42 USC Section 1983. The City government had already come to a sufficient regulatory conclusion, and the Constitution does not require additional processing. In so ruling, the Ninth Circuit ignored last term’s decision in Knick v. Township of Scott.
Read the court decisionRead the full story...Reprinted courtesy of
Anthony B. Cavender, PillsburyMr. Cavender may be contacted at
anthony.cavender@pillsburylaw.com
Contractors Liable For Their Subcontractor’s Failure To Pay Its Employees’ Wages And Benefits
November 01, 2022 —
Edward O. Pacer & David J. Scriven-Young - ConsensusDocsRecently, Illinois Governor J.B. Pritzker signed two House Bills that amend the Illinois Wage Payment & Collections Act, 820 ILCS 115 et. seq. (“Wage Act”), to provide greater protection for individuals working in the construction trades against wage theft in a defined class of projects. Pursuant to this new law, every general contractor, construction manager, or “primary contractor,” working on the projects included in the Bill’s purview will be liable for wages that have not been paid by a subcontractor or lower-tier subcontractor on any contract entered into after July 1, 2022, together with unpaid fringe benefits plus attorneys’ fees and costs that are incurred by the employee in bringing an action under the Wage Act. This new wage theft law follows several other states that have considered and passed similar legislation.
These amendments to the Wage Act apply to a primary contractor engaged in “erection, construction, alteration, or repair of a building structure, or other private work.” However, there are important limitations to the amendment’s applicability. The amendment does not apply to projects under contract with state or local government, or to general contractors that are parties to a collective bargaining agreement on a project where the work is being performed. Additionally, the amendment does not apply to primary contractors who are doing work with a value of less than $20,000, or work that involves only the altering or repairing of an existing single-family dwelling or single residential unit in a multi-unit building.
Reprinted courtesy of
Edward O. Pacer, Peckar & Abramson, P.C. (ConsensusDocs) and
David J. Scriven-Young, Peckar & Abramson, P.C. (ConsensusDocs)
Mr. Pacer may be contacted at epacer@pecklaw.com
Mr. Scriven-Young may be contacted at dscriven-young@pecklaw.com
Read the court decisionRead the full story...Reprinted courtesy of
A Landlord’s Guide to California’s New Statewide Rent Control Laws
May 18, 2020 —
Colton Addy - Snell & Wilmer Real Estate Litigation BlogApplicability of California’s Rent Control Laws: California Civil Code Sections 1946.2 and 1947.12 took effect on January 1, 2020, and implement statewide rent control in California for most residential properties. The rent control laws, however, do not apply to a rental property that was issued a certificate of occupancy in the last 15 years. (Civ. Code §§ 1947.12(d)(4), 1946.2(e)(7)). The statutes also do not apply to most single-family residences, provided that (a) the owner is not a real estate investment trust, a corporation, or a limited liability company where one of the members is a corporation, and (b) the required statutory language is included in the lease agreement for tenancies commencing or renewing on or after July 1, 2020. (Civ. Code §§ 1947.12(d)(5), 1946.2(e)(8)).
Annual Increases Permitted Under California’s Rent Control Laws: Commencing on January 1, 2020, unless otherwise permitted by California law, a Landlord cannot increase the gross rental rate for a rental unit over a continuous 12-month period more than the change in the regional cost of living index where the property is located plus 5%, and gross rental rate increases are subject to a maximum cap of 10% over a continuous 12-month period regardless of the change in the cost of living index. (Civ. Code § 1947.12(a)(1)). The gross rental rate is determined using the lowest rental amount charged in any month in the immediately preceding 12 months. (Id.) Any incentives, discounts, concessions, or credits are not taken into account. (Id.) Even if a rent increase does not exceed the amount permitted under the statute, a Landlord is prohibited from increasing rent more than twice in any continuous 12-month period. (Civ. Code § 1947.12(a)(2)).
Retroactive Applicability of Restrictions on Rent Increases: Although the statute took effect on January 1, 2020, the statute retroactively applies to all rent increases that occurred on or after March 15, 2019. (Civ. Code § 1947.12(h)(1)). If a landlord increased the rent amount more than the amount permitted under California Civil Code Section 1947.12(a)(1) after March 15, 2019, and prior to January 1, 2020, the rent amount on January 1, 2020, is reduced to the amount of the rent on March 15, 2019, plus the maximum permissible increase under California Civil Code Section 1947.12(a)(1). (Civ. Code § 1947.12(h)(2)). The Landlord does not have to refund the tenant any rent payments that were in excess of the permissible rent increase that the tenant made prior to January 1, 2020. (Id.)
Read the court decisionRead the full story...Reprinted courtesy of
Colton Addy, Snell & WilmerMr. Addy may be contacted at
caddy@swlaw.com
Application Of Two Construction Contract Provisions: No-Damages-For-Delay And Liquidated Damages
February 14, 2022 —
David Adelstein - Florida Construction Legal UpdatesA recent Florida opinion between a prime contractor and a Florida public body touches upon two important issues: (1) the application of a no-damage-for-delay provision; and (2) the application of a liquidated damages provision. Both provisions find there way into many construction contracts. Unfortunately, the opinion is sparse on facts. Nevertheless, the application of these provisions is worthy of consideration.
In this opinion, Sarasota County v. Southern Underground Industries, Inc., 2022 WL 162977 (Fla. 2d DCA 2022), a county hired a contractor to install sanitary and water piping underneath a waterway. During construction, a nearby homeowner complained that vibration from the drilling caused damage to his home. As a result, the county stopped the contractor’s work to address a potential safety issue, as it was contractually entitled to do. The contractor hired a structural engineer to inspect the house and the engineer issued a report determining that any alleged damage was cosmetic and that there was sufficient monitoring of the vibrations to prevent future damage. The contractor also had an insurance policy to cover any homeowner claim for damage. However, upon receipt of the engineer’s report, the county did not lift its stop work order. Rather, the stop work order remained in place for an additional 71 days.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Persimmon Offers to Fix Risky Homes as Cladding Crisis Grows
February 22, 2021 —
Olivia Konotey-Ahulu - BloombergPersimmon Plc, the U.K.’s biggest homebuilder, has offered to pay for work on potentially unsafe buildings in the wake of the cladding scandal that arose from London’s Grenfell Tower fire.
The firm has made a provision of 75 million pounds ($104 million) in its 2020 results for any necessary repair work on 26 buildings it developed that may be affected by the issue, it said in a statement Wednesday. It no longer owns the properties and said it would provide support where owners failed to accept their legal responsibilities.
“The concern around now banned cladding is affecting many thousands of homeowners who live in high-rise buildings right across the country,” Chairman Roger Devlin said in the statement. “We believe we have a clear duty to act to address this issue.”
Read the court decisionRead the full story...Reprinted courtesy of
Olivia Konotey-Ahulu, Bloomberg