Security on Large Construction Projects. The Payment Remedy You Probably Never Heard of
May 07, 2015 —
Garret Murai – California Construction Law BlogCalifornia has a number of statutory payment remedies available on construction projects. Some, such as the mechanics lien, are relatively well known and often utilized. Others, such as the stop payment notice, are somewhat less so.
However, there’s one statutory payment remedy you may not have heard of at all.
And that is, security requirements for large projects.
What is security for large projects?
Security is required on certain large construction projects to guarantee the payment by owners to direct contractors, and applies if either:
1.
Fee Interest and Contract of Greater Than $5 million: The owner contracting for a work of improvement holds a
fee interest in the property being improved and enters into a construction contract for the improvement of the property greater than
$5 million; or
2.
Less Than Fee Interest, Including Leasehold Interest, and Contract of Greater Than $1 million: The owner contracting for a work of improvement holds less than a fee interest (including a
leasehold interest) in the property being improved and enters into a construction contract for the improvement of the property greater than
$1 million.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel Rosen Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com
Don’t Fall in Trap of Buying the Cheapest Insurance Policy as it May be Bad for Your Business Risks and Needs
March 25, 2024 —
David Adelstein - Florida Construction Legal UpdatesDon’t fall in the trap of buying the cheapest insurance policy. It will come and bite you in the butt big time! Consult with an insurance broker that understands construction and, importantly, your specific industry, to provide you coverage within your industry. Otherwise, you’ll be paying for a policy that may (i) not be a good policy, and (ii) may provide you minimal to no value for your industry’s RISKS and NEEDS when factoring in exclusions. When procuring insurance, think of the old adage “penny wise and pound foolish,” and don’t make decisions that fit within this adage!
The recent decision in Nautilus Ins. Co. v. Pinnacle Engineering & Development, Inc., 2024 WL 940527 (S.D. Fla. 2024) serves as an example. Here, a subcontractor was hired by a general contractor to perform underground utility work for a townhome development which consisted of 57 townhome units included in 18 detached structures. The subcontractor’s underground work was defective which caused damage to the property’s water line, sewer system, plumbing lines, pavers, etc. The general contractor was liable to the owner for this defective work. Although the general contractor was an additional insured under the subcontractor’s commercial general liability (CGL) policy, the subcontractor’s CGL carrier denied the duty to defend and initiated an insurance coverage lawsuit. Motions for summary judgment were filed.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Jury Trials and Mediation in Philadelphia County: Virtually in Person
July 27, 2020 —
Andrew F. Susko, Robert G. Devine & Daniel J. Ferhat - White and Williams LLPWhen will the trial court in Philadelphia County be open for jury trials in civil actions? While a precise prediction, given the current state of our trial courts in the middle of the COVID-19 pandemic, is difficult to make, what is known is that the use of virtual technology is likely permanently changing the landscape of civil litigation, including depositions, mediation, and other forms of alternative dispute resolution. Even civil jury trials, at least in the near term and during the pandemic, are being conducted virtually, either by private agreement, or through the courts, as is occurring in Texas and most recently in Florida with its pilot virtual trial program in five of its trial courts. While it is necessary at present for the parties to consent to a virtual trial, courts may ultimately compel the parties’ participation. Regardless, litigants and their counsel are well advised to understand the complexities and manner of a virtual trial.
Seasoned trial attorneys have long experienced and are comfortable with virtual depositions bringing distant counsel, parties and witnesses together through technology to present testimony. The use of virtual technology as a means for court arguments and hearings, mediation, and alternative dispute resolution, while novel and emerging as the new normal, is territory where a comfort level can be achieved. And while distinctions most assuredly exist, recent experience has demonstrated that court arguments, mediations and depositions can be conducted effectively remotely and virtually. Legal issues certainly do remain in the context of the deposition of parties to a civil action regarding whether a lawyer’s physical presence in the same room with a party-witness can be demanded, and whether courts would compel a virtual deposition during the COVID-19 pandemic where such physical presence of a party and their attorney could not be achieved. Undoubtedly these issues will be resolved, likely sooner than later, given the scope of the pandemic in certain areas.
Reprinted courtesy of White and Williams LLP attorneys
Andrew F. Susko,
Robert G. Devine and
Daniel J. Ferhat
Mr. Susko may be contacted at suskoa@whiteandwilliams.com
Mr. Devine may be contacted at deviner@whiteandwilliams.com
Mr. Ferhat may be contacted at ferhatd@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of
Home Builder Doesn’t See Long Impact from Hurricane
November 07, 2012 —
CDJ STAFFNo one needs to tell Toll Brothers about the impact of Hurricane Sandy. The Wall Street Journal reports that the home building company lost power as a result of the storm. Martin Connor, the company’s CFO, told the Journal that he did not expect the hurricane to have a big effect on sales. Luckily for the company, many of its large projects are either sufficiently completed to provide shelter or too early in the process to be affected by the storm. “This type of weather event has limited impact on the market. It may move settlements later, and may defer people a weekend or two until they go out shopping. But it doesn’t have a long impact.”
Read the court decisionRead the full story...Reprinted courtesy of
Damage to Plaintiffs' Home Caused By Unmoored Boats Survives Surface Water Exclusion
April 06, 2016 —
Tred R. Eyerly – Insurance Law HawaiiThe magistrate's recommended decision found that damage to plaintiffs' home caused by boats that became loose during Hurricane Sandy was not barred as "water borne material" under the surface water exclusion. Spindler v. Great N. Ins. Co., 2016 U.S. Dist. LEXIS 16532 (E.D. N. Y. Feb. 2, 2016).
Plaintiffs' home abutted the East Bay. The property had an exterior deck and a long dock that floated on the bay. Hurricane Sandy damaged plaintiffs' home and dock. A neighbor witnessed two boats, driven by the storm, repeatedly strike plaintiffs' dock, house, and deck. There was no dispute that water infiltrated plaintiffs' yard prior to the entry of the boats. Plaintiffs spent $286,280 to repair damaged items from the storm.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
If You Don’t Like the PPP Now, Wait a Few Minutes…Major Changes to PPP Loan Program as Congress Passes Payroll Protection Program Flexibility Act
July 27, 2020 —
Ryan J. Udell & Adam J. Chelminiak - White and Williams LLPOn June 5, 2020, President Trump signed into law the Payroll Protection Program Flexibility Act of 2020 (the Flexibility Act). The Flexibility Act provides much-needed flexibility for the Paycheck Protection Program (PPP) and its millions of business participants.
The PPP offers loans to small businesses that have been adversely impacted by the COVID-19 pandemic and the measures taken by various governmental authorities to stem the spread of the virus so that they could keep their employees on the payroll during an eight-week period after receiving the funds. The PPP was particularly alluring to borrowers because the loans could be forgiven. But as the duration of lockdown orders and the accompanying economic aftershocks have extended longer than initially anticipated, particularly in those sectors that depend on in-person business such as restaurants, hospitality and other “main street” retail establishments, many recipients of PPP loans have found it challenging to use the PPP funds for payroll and other authorized purposes within the eight-week period after they had received the PPP funds, as is necessary to preserve eligibility for forgiveness. The Flexibility Act makes several key changes to the PPP program in order to allow borrowers who need a longer re-opening runway to do so without jeopardizing their ability to qualify for loan forgiveness.
This alert outlines the key changes to the PPP made by the Flexibility Act.
Reprinted courtesy of
Ryan J. Udell, White and Williams LLP and
Adam J. Chelminiak, White and Williams LLP
Mr. Udell may be contacted at udellr@whiteandwilliams.com
Mr. Chelminiak may be contacted at chelminiaka@whiteandwilliams.com;
Read the court decisionRead the full story...Reprinted courtesy of
Construction Law- Where Pragmatism and Law Collide
January 06, 2020 —
Christopher G. Hill - Construction Law MusingsIf there is one “theme” to Construction Law Musings, those that read regularly hopefully see that I take my role as counselor to construction companies seriously. Aside from the fact that litigation and arbitration are both expensive and not a great way for any business, particularly a construction business, to make money, I have found construction professionals to be a pragmatic group of people that would rather solve a problem than go to court.
I have also discussed the need for a good foundation for the project in the form of a well drafted and properly negotiated contract. This contract sets out the rights of the parties and essentially makes the “law” for your construction project. Virginia courts will not renegotiate the terms for you and while this can lead to problems where parties either don’t understand the terms or don’t work to level the terms, it does mean that the parties know what the expectations are where the expectations are properly set, preferably with the help of your friendly neighborhood construction attorney and counselor at law. Practical considerations such as your feel for the other party and which terms are worth forgoing the work for should drive your considerations almost as much as the legal implications.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
United States Supreme Court Backtracks on Recent Trajectory Away from Assertions of General Jurisdiction in Mallory v. Norfolk Southern
August 01, 2023 —
Charles S. Anderson - Lewis BrisboisWashington, D.C. (June 28, 2023) – On June 27, 2023, the U.S. Supreme Court issued a sharply divided opinion that appears to backtrack on the Court’s steady trajectory away from assertions of general jurisdiction in recent years, e.g. Goodyear Dunlop Tires Operations, S.A. v. Brown, 564 U.S. 915, 919 (2011), Daimler AG v. Bauman, 134 S. Ct. 746 (2014), BNSF Railway Co. v. Tyrrell, 2017, 137 S. Ct. 1549 (2017). Relying on a case from 1917, Pennsylvania Fire Ins. Co. of Philadelphia v. Gold Issue Mining & Milling Co., 243 U. S. 93 (1917), Justice Gorsuch, writing on behalf of the plurality, (Justices Gorsuch, Thomas, Sotomayor, and Jackson) (Justice Alito concurring) found that Norfolk Southern “consented” to jurisdiction in Mallory via 42 Pa. Cons. Stat. §5301(a)(2)(i),(b) by registering to do business in Pennsylvania. This statute, 42 Pa. Cons. Stat. §5301, specifically permits jurisdiction over a corporation “incorporat[ed] under or qualifi[ed]as a foreign corporation under the laws of this Commonwealth … for any cause of action that may asserted against him, whether or not arising from acts enumerated in this section.”
In Pennsylvania Fire, the U.S. Supreme Court addressed the Due Process Clause of the U.S. Constitution in connection with a Missouri law that required an out-of-state insurance company desiring to transact any business in the state to file paperwork agreeing to (1) appoint a state official to serve as the company’s agent for service of process and (2) accept service on that official as valid in any suit. After more than a decade of complying with the law, Pennsylvania Fire was served with process and argued that the Missouri law violated due process. The Court unanimously found that there was “no doubt” that Pennsylvania Fire could be sued in Missouri because it had agreed to accept service of process in Missouri on any suit as a condition of doing business there.
Read the court decisionRead the full story...Reprinted courtesy of
Charles S. Anderson, Lewis BrisboisMr. Anderson may be contacted at
Charles.Anderson@lewisbrisbois.com