Foreclosing Junior Lienholders and Recording A Lis Pendens
July 13, 2020 —
David Adelstein - Florida Construction Legal UpdatesWhen you foreclose on a construction lien, there are a couple of pointers to remember.
First, you want to make sure you include junior lienholders or interests you are looking to foreclose (or you want to be in a position to amend the foreclosure lawsuit to identify later). The reason being is you want to foreclose their interests to the property. “[J]unior interest holders are a narrow class of mortgagees whose interest in the underlying property is recorded after the foreclosing contractor’s claim of lien is filed. This class is routinely joined to the construction lien enforcement action under section 713.26 to allow the construction lienor to foreclose out the junior lienholder’s interest in the property encumbered by the construction lien.” See Decks N Sunch Marine, infra.
Second, you want to record a lis pendens with the lien foreclosure lawsuit. Failure to do so could be problematic because Florida Statute s. 713.22(1) provides in part, “A lien that has been continued beyond the 1-year period by the commencement of an action is not enforceable against creditors or subsequent purchasers for a valuable consideration and without notice, unless a notice of lis pendens is recorded.”
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Insurer Need Not Pay for Rejected Defense When No Reservation of Rights Issued
November 08, 2017 —
Tred R. Eyerly - Insurance Law HawaiiThe Massachusetts Appeals Court reversed the trial court's order that defense costs be paid for a period during which the insured rejected the defense even though no reservation of rights was issued. OneBeacon Am. Ins. Co. v. Celanese Corp., 2017 Mass. App. LEXIS 140 (Mass. App. Ct. Oct. 16, 2017).
Celanese was sued over many years for claims of bodily injury due to asbestos and chemicals allegedly contained in its products and facilities. For many years, Celanese had an agreement with its insurer, OneBeacon, for defense cost-sharing. In April 2009, Celanese terminated this agreement and demanded that OneBeacon defend the cases under the policies previously issued. OneBeacon agreed to defend without a reservation of rights. OneBeacon also agreed to waive any issues of coverage and to indemnify Celanese from any settlements of judgments up to ts full liability limits. However, OneBeacon also sought to assume full control of the defense of claims against Celanese.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly - Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
In One of the First Civil Jury Trials to Proceed Live in Los Angeles Superior Court During Covid, Aneta Freeman Successfully Prevailed on Behalf of our Client and Obtained a Directed Verdict and Non-Suit
July 05, 2021 —
Aneta B. Freeman – Chapman Glucksman Dean & Roeb News AlertIn one of the first civil jury trials to proceed live in Los Angeles Superior Court during Covid, Aneta Freeman obtained a rare directed verdict and nonsuit in a complex, high exposure action, after seven days of trial. The dismissal was obtained after the parties rested after the liability phase of the bifurcated trial.
Ms. Freeman represented a general contractor in an action in which Plaintiff alleged that the general contractor and the County of Los Angeles (which was dismissed earlier on statutory immunity grounds) created a dangerous condition when they allegedly allowed mosquitos to breed in 2015 during construction at a flood retention basin in Marina Del Rey.
Plaintiff contracted West Nile Virus, and subsequently developed myasthenia gravis and a myriad of other conditions and ailments. Plaintiff relied heavily on a 2015 report from the Los Angeles West Vector Control District which suggested that the construction was the source of mosquitos which resulted in a “cluster” of West Nile Virus cases in the Marina Del Rey and surrounding areas.
In pretrial motions, Ms. Freeman successfully excluded that report, opinion testimony from the vector control former executive director, narrowed the scope of plaintiff’s entomologist testimony, and excluded Brad Avrit from testifying for the Plaintiff on construction standard of care.
The matter proceeded with a stipulated a 10 person jury, and all participants socially distanced and masked throughout the trial. Witnesses appeared live, with the exception of Plaintiff’s entomologist, portions of whose video deposition were played.
Following seven days of trial after both parties rested, Judge Mark Young granted the general contractor’s nonsuit and also, in the alternative, a directed a verdict for our client.
Plaintiff had demanded $10,000,000 of the County and the general contractor globally prior to trial, and $5,000,000 from the general contractor. The general contractor issued two CCP 998s, which were ignored by Plaintiff.
Read the court decisionRead the full story...Reprinted courtesy of
Aneta B. Freeman, Chapman Glucksman Dean & RoebMs. Freeman may be contacted at
afreeman@cgdrlaw.com
Sureties and Bond Producers May Be Liable For a Contractor’s False Claims Action Violation
October 26, 2017 —
Michael C. Zisa & Susan Elliot – Peckar & Abramson, P.C.Two recent decisions from the United States District Court for the District of Columbia and the United States Court of Federal Claims highlight that sureties and bond producers are not immune to the potentially severe consequences of the False Claims Act (“FCA”) and related federal fraud statutes. In each case, the Court determined that sureties and bond producers can face potential liability under these fraud statutes for direct and indirect submission of false claims to the federal government
Reprinted courtesy of
Michael C. Zisa, Peckar & Abramson, P.C. and
Susan Elliott, Peckar & Abramson, P.C.
Mr. Zisa may be contacted at mzisa@pecklaw.com
Ms. Elliott may be contacted at selliott@pecklaw.com
Read the court decisionRead the full story...Reprinted courtesy of
The Cheap and Easy Climate Fix That Can Cool the Planet Fast
January 10, 2022 —
Hayley Warren & Akshat Rathi - BloombergLet a molecule of carbon dioxide escape into the atmosphere, and it stays for centuries. There’s more than enough up there to smother the planet like a too-warm quilt, trapping heat within and weirding the weather. The damage will be felt for generations.
But CO2 is only part of the patchwork of warming. Methane locks in far more heat in the short term and has been leaking just as relentlessly.
Methane Surge
Atmospheric concentrations of methane are 2.5x higher than in pre-industrial times.
The difference is that methane’s power fades faster, within just decades. If we stopped emissions today, almost all the methane in the atmospheric blanket would degrade within a lifetime.
Reprinted courtesy of
Hayley Warren, Bloomberg and
Akshat Rathi, Bloomberg Read the court decisionRead the full story...Reprinted courtesy of
“Professional Best Efforts” part 2– Reservation of Rights for Engineers who agree to “best” efforts? (law note)
April 20, 2017 —
Melissa Dewey Brumback - Construction Law in North CarolinaRecently, a reader reached out to me to ask about case examples of an engineer losing his insurance coverage because he agreed to a “heightened” or “best” standard of care. The reader stated that he was an insurance adviser who handled various construction professional coverages, and that in his experience it was very unusual to deny or limit damages because of a heightened standard of care.
This comment led me to an informal survey of several insurance brokers that I deal with, and the general consensus is that instead of outright denying a claim, most E&O insurers will issue a “reservation of rights” letter. What that means is that the insurance company will defend the claim (i.e., pay for your lawyer to defend you and your Firm), but with the understanding that they are (potentially) denying any liability for any adverse money judgment against you.
Inevitably, most such cases settle, but if they do not, the question then is whether the heightened duty created part of the damages. The insurer may ask to intervene in the lawsuit to ask the jury that question, in an effort to limit its share of the damages.
Read the court decisionRead the full story...Reprinted courtesy of
Melissa Dewey Brumback, Ragsdale Liggett PLLCMs. Brumback may be contacted at
mbrumback@rl-law.com
Construction Defects Up Price and Raise Conflict over Water Treatment Expansion
August 27, 2013 —
CDJ STAFFThe owner of a regional water treatment plant in California has filed a lawsuit against the where they operate. Construction defects lead to cost overruns at the Modesto Irrigation District’s water treatment plant. Now the question is whether MID or Modesto will be paying for the expenses. Both parties sued Black & Veatch and others, receiving $14.9 million.
But the problems have lead to the cost of the water treatment plant expansion ballooning to $107.5 million, a big jump over the planned $62.9 million. Also, instead of being completed in 2009, the completion date has been pushed to 2015.
Modesto originally agreed to pay for the expansion, which will increase plant’s ability to provide drinking water to 66 million gallons per day with the agreement that MID would provide the water at the cost of producing it. But now the cost to Modesto of those additional 36 million gallons a day is an additional $44.6 million.
Read the court decisionRead the full story...Reprinted courtesy of
$31.5M Settlement Reached in Contract Dispute between Judlau and the Illinois Tollway
September 16, 2024 —
Annemarie Mannion - Engineering News-RecordThe Illinois Tollway will pay nearly $31.5 million to New York-based Judlau Contracting and its trade contractors to resolve a lawsuit filed after the tollway, in April, terminated a $324-million contract with Judlau to rebuild the southbound lanes of the Interstate 290 and Interstate 88 interchange near Oak Brook, Ill.
Reprinted courtesy of
Annemarie Mannion, Engineering News-Record
Ms. Mannion may be contacted at manniona@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of