Michigan Supreme Court Finds Faulty Subcontractor Work That Damages Insured’s Work Product May Constitute an “Occurrence” Under CGL Policy
November 02, 2020 —
Jason Taylor - Traub Lieberman Insurance Law BlogIn Skanska USA Bldg. Inc. v. M.A.P. Mech. Contractors, Inc., 2020 WL 3527909 (Mich. June 29, 2020), the Michigan Supreme Court addressed whether unintentionally faulty subcontractor work that damages an insured’s work product constitutes an “accident” under a commercial general liability insurance policy. In aligning itself with a growing number of jurisdictions, the Michigan Supreme Court answered, “yes.” In Skanska, a construction manager brought an action against a commercial general liability (CGL) insurer seeking coverage as additional insured for the cost of repairs to correct faulty work performed by its subcontractor in renovation of medical center. In 2009, the construction manager hired MAP to install a steam boiler and related piping for the medical center’s heating system. MAP’s installation included several expansion joints, which it was later discovered, were installed backward. Significant damage to concrete, steel, and the heating system occurred as a result. The construction manager performed the work of repairing and replacing the damaged property to the tune of $1.4 million, and submitted a claim to MAP’s CGL insurer, Amerisure, seeking coverage as an additional insured.
Amerisure denied the claim contending that MAP’s defective construction was not a covered “occurrence” within the CGL policy. The policy defined “occurrence” as “an accident, including continuous or repeated exposure to substantially the same general harmful conditions,” but did not define the term “accident.” The trial court looked to the Court of Appeal’s decision in Hawkeye-Sec. Ins. Co. v. Vector Const. Co., 185 Mich. App. 369 (1990), which defined “accident” as “…a result which is not anticipated and…takes place without the insured’s foresight or expectation and without design or intentional causation on his part.” But, again citing Hawkeye, the trial court concluded that “[d]efective workmanship, standing alone, is not an occurrence within the meaning of a[ ] general liability insurance contract[;] an occurrence exists where the insured’s faulty work product damages the property of another.”
Read the court decisionRead the full story...Reprinted courtesy of
Jason Taylor, Traub LiebermanMr. Taylor may be contacted at
jtaylor@tlsslaw.com
Use It or Lose It: California Court of Appeal Addresses Statutes of Limitations for Latent Construction Defects and Damage to Real Property
August 02, 2017 —
Omar Parra & Jesse M. Sullivan - Haight Brown & Bonesteel LLPThe First Appellate District of the California Court of Appeal recently confirmed California’s latent defect statute of limitations, codified in California Code of Civil Procedure section 337.15, bars only claims based on construction defects. Estuary Owners Association v. Shell Oil Company, No. A145516, (Cal. Ct. App. July 26, 2017). The Court also reemphasized that under California’s three-year statute of limitations for damage to real property, delineated in California Code of Civil Procedure section 338(b), the actual and constructive knowledge of the prior landowner is imputed to the current landowner.
Estuary Owners Association concerned the development and construction of a 100-unit condominium by Signature at the Estuary, LLC (“Signature”) on land Shell Oil Company (“Shell”) previously used as a fuel distribution terminal. Construction of the condominiums was completed in 2006. In 2008, it was discovered that residual concentrations of petroleum related chemicals remained in the soil, soil gas, and groundwater beneath the development. Later that year, Signature revealed that the condominiums had been constructed with moisture barriers beneath the building slabs instead of the vapor/gas barriers called for in the corrective action plan.
Reprinted courtesy of
Omar Parra, Haight Brown & Bonesteel LLP and
Jesse M. Sullivan, Haight Brown & Bonesteel LLP
Mr. Parra may be contacted at oparra@hbblaw.com
Mr. Sullivan may be contacted at jsullivan@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
If You Don’t Like the PPP Now, Wait a Few Minutes…Major Changes to PPP Loan Program as Congress Passes Payroll Protection Program Flexibility Act
July 27, 2020 —
Ryan J. Udell & Adam J. Chelminiak - White and Williams LLPOn June 5, 2020, President Trump signed into law the Payroll Protection Program Flexibility Act of 2020 (the Flexibility Act). The Flexibility Act provides much-needed flexibility for the Paycheck Protection Program (PPP) and its millions of business participants.
The PPP offers loans to small businesses that have been adversely impacted by the COVID-19 pandemic and the measures taken by various governmental authorities to stem the spread of the virus so that they could keep their employees on the payroll during an eight-week period after receiving the funds. The PPP was particularly alluring to borrowers because the loans could be forgiven. But as the duration of lockdown orders and the accompanying economic aftershocks have extended longer than initially anticipated, particularly in those sectors that depend on in-person business such as restaurants, hospitality and other “main street” retail establishments, many recipients of PPP loans have found it challenging to use the PPP funds for payroll and other authorized purposes within the eight-week period after they had received the PPP funds, as is necessary to preserve eligibility for forgiveness. The Flexibility Act makes several key changes to the PPP program in order to allow borrowers who need a longer re-opening runway to do so without jeopardizing their ability to qualify for loan forgiveness.
This alert outlines the key changes to the PPP made by the Flexibility Act.
Reprinted courtesy of
Ryan J. Udell, White and Williams LLP and
Adam J. Chelminiak, White and Williams LLP
Mr. Udell may be contacted at udellr@whiteandwilliams.com
Mr. Chelminiak may be contacted at chelminiaka@whiteandwilliams.com;
Read the court decisionRead the full story...Reprinted courtesy of
Foreclosures Decreased Nationally in September
October 29, 2014 —
Beverley BevenFlorez-CDJ STAFFAccording to the San Diego Source, in “September 2014, there were 46,000 completed foreclosures nationally, down from 68,000 in September 2013, a year-over-year decrease of 32.6 percent and down 61 percent from the peak of completed foreclosures in 2010, according to the September National Foreclosure Report of CoreLogic.”
Between 2000 and 2006, “completed foreclosures averaged 21,000 per month nationwide.” Furthermore, the San Diego Source reported that “[s]ince the financial crisis began in September 2008, there have been approximately 5.2 million completed foreclosures across the country, and since homeownership rates peaked in Q2 of 2004, there have been approximately 7 million homes lost to foreclosure.”
Read the court decisionRead the full story...Reprinted courtesy of
Ten-Year Statute Of Repose To Sue For Latent Construction Defects
November 12, 2019 —
David Adelstein - Florida Construction Legal UpdatesIf you are dealing with latent construction defects, it is imperative that you consult with counsel to understand your rights. This not only includes claims for property damage stemming from latent construction defects, but also personal injury stemming from such defects. There is a ten-year statute of repose to sue for latent construction defects. See Fla.Stat. s. 95.11(3)(c). After the expiration of this statute of repose you are out of luck, meaning you can no longer sue.
Now, I probably will not be the first to tell you that the statute of repose is not written so clear that you know the precise date it ends (or the last date you can sue for a latent defect). For this reason, you really want to operate conservatively, meaning it is always better to sue early if you think you could be running on the end of the statute of repose period. It is always advisable to avoid any legitimate argument that you filed your construction defect lawsuit too late.
In Harrell v. The Ryland Group, 44 Fla. L. Weekly D2054b (Fla. 1st DCA 2019), a subsequent owner of a house sued the original homebuilder in negligence for a construction defect causing a personal injury. The subsequent owner claimed the homebuilder defectively installed an attic ladder (that provided access to the attic for the original construction) which collapsed as he was using it. The homebuilder filed a motion for summary judgment that the statute of repose expired so the owner’s claim was time-barred. The First District agreed.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Property Damage, Occurrences, Delays, Offsets and Fees. California Decision is a Smorgasbord of Construction Insurance Issues
November 21, 2017 —
Garret Murai - California Construction Law BlogOriginally published by CDJ on November 15, 2017
I read once that 97 percent of cases never go to trial. However, there are still the ones that do. And, then, there are the ones that do both. The following case, Global Modular, Inc. v. Kadena Pacific, Inc., California Court of Appeals for the Fourth District, Case No. E063551 (September 8, 2017), highlights some of the issues that can arise when portions of cases settle and other portions go to trial, the recovery of delay damages on a construction project through insurance, and the recovery of attorneys’ fees.
Global Modular, Inc. v. Kadena Pacific, Inc.
The U.S. Department of Veterans Affairs contracted with general contractor Kadena Pacific, Inc. (Kadena) to oversee construction of its Center for Blind Rehabilitation in Menlo Park, California. Kadena, in turn, contracted with subcontractor Global Modular, Inc. (Global) to construct, deliver and install 53 modular units totaling more than 37,000 square feet for a contract price of approximately $3.5 million.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel Rosen Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com
Video: Contractors’ Update on New Regulations Governing Commercial Use of Drones
September 01, 2016 —
David R. Cook Jr. – AHHC Construction Law BlogAt a presentation before the AGC of Georgia, AHHC attorneys Mark Hanrahan, David Cook, and Chadd Reynolds covered “Contractors’ Update on New Regulations Governing Commercial Use of Drones.” View the presentation here: https://vimeo.com/177566370
On June 23, 2016, the Department of Transportation and Federal Aviation Administration issued new regulations regarding non-hobby and non-recreational civil operation of small unmanned aircraft systems. These regulations are intended to limit interference with federal airspace while advancing research and safety in commercial industries. They also addressed practical implications and how to comply by the August 29, 2016 deadline.
Read the court decisionRead the full story...Reprinted courtesy of
David R. Cook Jr., Autry, Hanrahan, Hall & Cook, LLPMr. Cook may be contacted at
cook@ahclaw.com
Effectively Managing Project Closeout: It Ends Where It Begins
August 06, 2019 —
William E. Underwood - ConsensusDocsProject closeout is sometimes one of the last things on a contractor’s mind at the beginning of a project, but project closeout can have a huge impact on a contractor’s overall profitability and success. Effectively managing the closeout process is critical, and it all begins with the negotiation and execution of the project contract. This contract can, and should, provide a complete roadmap for project closeout, as addressing these issues on the front end can set up the parties for successful project completion. It is then equally important to re-review the terms of the contract as project closeout approaches to ensure that everyone, including the owner, adheres to all contractual requirements.
This article examines several pertinent issues related to project closeout that should be addressed during the contracting stage, including defining substantial and final completion, inspection and acceptance, punch lists, and warranties.
Defining Substantial and Final Completion
Having clear definitions for both substantial and final completion in your construction contract is an important and necessary early step in achieving successful project closeout.
Read the court decisionRead the full story...Reprinted courtesy of