The Court of Appeals Holds That Indifference to Safety Satisfies the Standard for a Willful Violation Under WISHA
May 16, 2022 —
Cameron Sheldon - Ahlers Cressman & Sleight PLLCIn March 2022, the Washington State Court of Appeals, Division One, issued Marpac Constr., LLC v. Dep’t of Lab. & Indus., No. 82200-4-I, 2022 WL 896850, at *1 (Wash. Ct. App. Mar. 28, 2022) holding Marpac Construction, LLC (“Marpac”) liable for three willful Washington Industrial Safety and Health Act of 1973 (WISHA) violations pertaining to safe crane operation near energized power lines.
Marpac was the general contractor on an apartment complex construction project in West Seattle. The worksite had high voltage power lines running throughout the site. Seattle City Light had flagged some with a 10-foot offset, but none of the other power lines were flagged. Marpac’s superintendent assumed that the lines were between 26 kilovolts (kV) and 50 kV based on their connection to the lines flagged by Seattle City Light. The superintendent never called Seattle City Light to check the voltage of the lines and the lines remained above ground.
In September 2016, a subcontractor began work on the project’s structural foundation. The subcontractor expressed concerns about working around the power lines, but Marpac promised it was working on mitigation of the power line hazard and directed the subcontractor continue working. At one point, the subcontractor’s employees had to move the crane and concrete forms away from the power lines to allow a cement truck to park in its place. The crane’s line contacted the power lines, causing serious injuries to two of the subcontractor’s employees.
Read the court decisionRead the full story...Reprinted courtesy of
Cameron Sheldon, Ahlers Cressman & Sleight PLLCMs. Sheldon may be contacted at
cameron.sheldon@acslawyers.com
Back to Basics: What is a Changes Clause?
July 18, 2018 —
J. Cole Phillips – Smith CurrieThe Changes Clause is one of the most important, perhaps the most important, provision in any construction contract. Project designs are rarely perfect. A Changes Clause provides a mechanism for dealing with such imperfections as well as allowing project owners the flexibility to update a project’s design as the project progresses. A good Changes Clause specifies when an owner can change the original scope of the contract, how the parties should resolve the value of the changed scope and when payment should be made to the contractor or a credit given to the owner. A good Changes Clause will also provide a mechanism for the contractor to notify the owner when it believes a change order is due and specify the time within which such notice must be given. For the contractor, failure to pay attention to the requirements of the Changes Clause can lead to forfeiture of the right to seek an adjustment to the contract value or contract completion date. For an Owner, failure to pay attention to and enforce the requirements of the Changes Clause can result in unnecessary payments to the Contractor.
Read the court decisionRead the full story...Reprinted courtesy of
J. Cole Phillips, Smith CurrieMr. Phillips may be contacted at
jcphillips@smithcurrie.com
Ten Newmeyer & Dillion Attorneys Selected to the Best Lawyers in America© 2019
September 17, 2018 —
Newmeyer & DillionNEWPORT BEACH, Calif. – AUGUST 15, 2018 – Prominent business and real estate law firm Newmeyer & Dillion LLP is pleased to announce that ten of the firm's Newport Beach attorneys were recently recognized in their respective practice areas in The Best Lawyers in America© 2019.
Attorneys named to The Best Lawyers in America, include:
Jason M. Caruso
Personal Injury Litigation - Plaintiffs
Product Liability Litigation – Plaintiffs
Michael S. Cucchissi
Real Estate Law
Jeffrey M. Dennis
Insurance Law
Gregory L. Dillion
Commercial Litigation
Construction Law
Insurance Law
Litigation - Construction
Litigation - Real Estate
Joseph A. Ferrentino
Litigation - Construction
Litigation - Real Estate
Thomas F. Newmeyer
Commercial Litigation
Litigation - Real Estate
John O'Hara
Litigation - Construction
Bonnie T. Roadarmel
Insurance Law
Jane Samson
Real Estate Law
Carol Sherman Zaist
Commercial Litigation
Best Lawyers is the oldest peer-review publication within the legal profession with a history of over 35 years. Attorneys are selected through exhaustive peer-review surveys in which leading lawyers confidentially evaluate their professional peers. Their listings are published in 75 countries worldwide and are recognized for their reliable and unbiased selections.
Newmeyer & Dillion is immensely proud of these lawyers and looks forward to their continued contributions to the firm, and the Orange County community as a whole.
About Newmeyer & Dillion
For almost 35 years, Newmeyer & Dillion has delivered creative and outstanding legal solutions and trial results for a wide array of clients. With over 70 attorneys practicing in all aspects of cybersecurity and privacy, corporate, employment, real estate, construction, insurance law and trial work, Newmeyer & Dillion delivers legal services tailored to meet each client's needs. Headquartered in Newport Beach, California, with offices in Walnut Creek, California and Las Vegas, Nevada, Newmeyer & Dillion attorneys are recognized by The Best Lawyers in America©, and Super Lawyers as top tier and some of the best lawyers in California, and have been given Martindale-Hubbell Peer Review's AV Preeminent® highest rating. For additional information, call 949.854.7000 or visit www.ndlf.com.
Read the court decisionRead the full story...Reprinted courtesy of
Warning! Danger Ahead for Public Entities
July 30, 2019 —
Michael J. Baker - Snell & Wilmer Under Construction BlogPublic entities are known to assert False Claims actions “to up the ante” to intimidate and aggressively address contractor construction claims. This strategy in the case of John Ross of Industrial Sheet Metal, Inc. (JRI) V. City of Los Angeles Department of Airports (LAWA), 29 Cal. App. 5th 378 (2018), backfired on the public entity, LAWA, in a big way and should serve as a warning to public entities about expanding claims to include False Claim actions. In this case, LAWA was awarded $1 in contract damages, its California False Claims Act (CFCA) claim was rejected by the jury as were JRI’s claims against LAWA. Despite losing on the substantive contract claims, the trial court found that JRI “prevailed in the action” under the relevant CFCA fee provision, Government Code 12652, subd. (g)(9)(B), regardless of JRI’s failure to prevail in the action as a whole. The California Appellate Court (hereinafter “Court”) affirmed the trial court’s finding.
The CFCA is analogous to the federal False Claims Act (FFCA; 31 U.S.C. 3729 et seq.). Since the CFCA is patterned on similar federal legislation, it was appropriate for the Court to look to precedent construing this similar federal act in interpreting the CFCA provisions. Accordingly, the Court looked at the False Claims Act cases for guidance in upholding the trial court’s decision in its determination that JRI was the “prevailing party” for determining an attorney’s fees award against LAWA.
Read the court decisionRead the full story...Reprinted courtesy of
Michael J. Baker, Snell & WilmerMr. Baker may be contacted at
mjbaker@swlaw.com
Court of Appeal Holds Only “Named Insureds” May Sue for Bad Faith Under California FAIR Plan Policy
May 10, 2021 —
Valerie A. Moore & Kathleen E.M. Moriarty - Haight Brown & Bonesteel LLPIn Wexler v. California Fair Plan Association (No. 303100, filed 4/14/21), Brooke Wexler’s parents insured their residence, which was located in a mountainous high-fire risk area, with a California FAIR Plan Association owner-occupied dwelling policy. The policy only listed Wexler’s parents and did not name Wexler, their adult child, under the policy’s “Insured Name” section. The FAIR Plan expressly disclaimed coverage for “unnamed people,” referred to by the court as the “no-coverage-for-unnamed-persons clause.”
FAIR Plan was created by the Legislature in 1968 and is a joint reinsurance association created to give homeowners in high risk areas access to basic property insurance and is a self-described “insurer of last resort.”
Reprinted courtesy of
Valerie A. Moore, Haight Brown & Bonesteel LLP and
Kathleen E.M. Moriarty, Haight Brown & Bonesteel LLP
Ms. Moore may be contacted at vmoore@hbblaw.com
Ms. Moriarty may be contacted at kemoriarty@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
US Proposes Energy Efficiency Standards for Federal Buildings
January 04, 2023 —
James Leggate - Engineering News-RecordThe U.S. government is looking to its own buildings as a source for cutting carbon emissions with a new energy and climate performance standard. Additionally, federal officials announced a proposed rule that would eliminate energy-related emissions from new and renovated federal buildings.
Reprinted courtesy of
James Leggate, Engineering News-Record
Mr. Leggate may be contacted at leggatej@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Court Reminds Insurer that the Mere Possibility Of Coverage at the Time of Tender Triggers a Duty to Defend in a Defect Action
October 04, 2021 —
Jatin Patel - Newmeyer DillionIt has long been the law in California that an insurer’s duty to defend is broader than the duty to indemnify and that the mere possibility of coverage triggers a duty to defend. Nevertheless, insurers still periodically ignore this clear principle and attempt to narrow the scope of the duty to defend. Recently, a Federal District Court issued a reminder to a wayward insurer.
In Pacific Bay Masonry, Inc., v. Navigators Specialty Insurance Company, (N.D. Cal., Sept. 16, 2021, No. C 20-07376 WHA, 2021 WL 4221747 (“Pacific”)), the Court was asked to assess whether a tender of defense by a concrete masonry subcontractor to its insurer for a construction defect action required a defense. Pacific Bay Masonry, Inc. (“PBM”) installed concrete masonry units (also known as “CMUs”) at a new retail shopping center in Oakland, California. The subsequent owner of the retail center filed suit against the general contractor for alleged construction defects, including “efflorescence of roof deck at CMU wall” and “improper waterproofing and flashing of the CMU block wall." The general contractor filed a cross-complaint against PBM.
PBM tendered the defense of the case to Navigators Specialty Insurance Company (“Navigators”) along with copies of a preliminary defect list, a description of defects, interrogatory responses and an expert witness damage analysis. Navigators denied coverage and a duty to defend citing to the work product exclusion of the policy. PBM asked Navigators to reconsider. Navigators held firm on its denial. Two years later, PBM filed suit.
Read the court decisionRead the full story...Reprinted courtesy of
Jatin Patel, Newmeyer DillionMr. Patel may be contacted at
jatin.patel@ndlf.com
Viewpoint: A New Approach to Job Site Safety Reaps Benefits
June 30, 2016 —
Jimmy Morgan & Eric Pfeiffer – Engineering News-RecordEvery organization that participates in the construction and manufacturing industries understands that safety is critical to success and strives to end each day injury-free and incident-free.
Read the court decisionRead the full story...Reprinted courtesy of
Jimmy Morgan & Eric Pfeiffer, Engineering News-RecordComments or questions regarding this story may be submitted to
ENR.com@bnpmedia.com