Finding Plaintiff Intentionally Spoliated Evidence, the Northern District of Indiana Imposes Sanction
March 14, 2018 —
Shannon M. Warren – The Subrogation Strategist On January 23, 2018, the Northern District of Indiana issued a decision that clarifies what constitutes spoliation of evidence under Indiana law. In
Arcelormittal Ind. Harbor LLC v. Amex Nooter, LLC, 2018 U.S. Dist. LEXIS 10141 (N.D. Ind.), the defendant filed a motion for sanctions, alleging that the plaintiff intentionally spoliated critical evidence. The defendant sought dismissal of the action, asserting that the plaintiff intentionally discarded and lost important physical evidence within hours of a fire that occurred while the defendant’s employees were performing work at its facility. The decision underscores the importance of taking immediate action to properly identify and secure potentially material evidence in order to satisfy ones duty to preserve pre-suit evidence and avoid any spoliation defenses and associated sanctions.
In
Arcelormittal, the court initially considered whether to apply state or federal law when analyzing a litigant’s duty to preserve pre-suit evidence and determine if that party committed spoliation. Since the case was brought in federal court based on diversity jurisdiction, the court held that Indiana state law governed the spoliation analysis.
As noted by the court, under Indiana state law, “the intentional destruction, mutilation, altercation, or concealment of evidence” is considered to be spoliation. Thus, under Indiana law, a party who knew or should have known that litigation was imminent “may not lose, destroy or suppress material facts or evidence.” The plaintiff argued that Indiana law requires a showing of improper purpose or bad faith to establish that a litigant spoliated evidence. The
Arcelormittal court rejected the plaintiff’s argument.
Read the court decisionRead the full story...Reprinted courtesy of
Shannon M. Warren, White and Williams LLPMs. Warren may be contacted at
warrens@whiteandwilliams.com
OSHA/VOSH Roundup
August 31, 2020 —
Christopher G. Hill - Construction Law MusingsIn an unusual flurry of occupational safety related activity, the Virginia courts decided two cases in the last week relating to either the review of occupational safety regulations themselves or their enforcement.
In Nat’l College of Business & Technology Inc. v. Davenport (.pdf), the Virginia Court of Appeals considered what constitutes a “serious” violation of the exposure to asbestos Virginia Occupational Safety & Health (VOSH) regulations. The facts found by the Salem, Virginia Circuit Court were that employees of the petitioner college were exposed to asbestos insulation when they were required to enter a boiler room to retrieve paper files. However, no evidence was presented regarding the length of time or level of exposure at the Circuit Court level. Despite the lack of evidence regarding the level or extent of exposure, the Circuit Court upheld the VOSH citation for exposure and the level of violation at a “serious” level with the attendant penalty.
The Virginia Court of Appeals disagreed with the second finding. The appellate court determined that the lack of evidence regarding the level of exposure (whether length or extent) made the serious level violation an error. The Court stated that merely presenting evidence that asbestos is a carcinogen is not enough given the number of carcinogenic materials in existence and then remanded the case back to Circuit Court to reconsider the penalty level.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
History of Defects Leads to Punitive Damages for Bankrupt Developer
March 01, 2012 —
CDJ STAFFThe South Carolina Court of Appeals has ruled that evidence of construction defects at a developer’s other projects were admissible in a construction defect lawsuit. They issued their ruling on Magnolia North Property Owners’ Association v. Heritage Communities, Inc. on February 15, 2012.
Magnolia North is a condominium complex in South Carolina. The initial builder, Heritage Communities, had not completed construction when they filed for bankruptcy protection under Chapter 11. The remaining four buildings were completed by another contractor. The Property Owners’ Association subsequently sued Heritage Communities, Inc. (HCI) alleging defects. The POA also sued Heritage Magnolia North, and the general contractor, BuildStar.
The trial court ruled that all three entities were in fact one. On appeal, the defendants claimed that the trial court improperly amalgamated the defendants. The appeals court noted, however, that “all these corporations share officers, directors, office space, and a phone number with HCI.” Until Heritage Communities turned over control of the POA to the actual homeowners, all of the POA’s officers were officers of HCI. The appeals court concluded that “the trial court’s ruling that Appellants’ entities were amalgamated is supported by the law and the evidence.”
Heritage also claimed that the trial court should not have allowed the plaintiffs to produce evidence of construction defects at other Heritage properties. Heritage argued that the evidence was a violation of the South Carolina Rules of Evidence. The court cited a South Carolina Supreme Court case which made an exception for “facts showing the other acts were substantially similar to the event at issue.” The court noted that the defects introduced by the plaintiffs were “virtually identical across all developments.” This included identical use of the same products from project to project. Further, these were used to demonstrate that “HCI was aware of water issues in the other projects as early as 1998, before construction on Magnolia North had begun.”
The trial case ended with a directed verdict. Heritage charged that the jury should have determined whether the alleged defects existed. The appeals court noted that there was “overwhelming evidence” that Heritage failed “to meet the industry standard of care.” Heritage did not dispute the existence of the damages during the trial, they “merely contested the extent.”
Further, Heritage claimed in its appeal that the case should have been rejected due to the three-year statute of limitations. They note that the first meeting of the POA was on March 8, 2000, yet the suit was not filed until May 28, 2003, just over three years. The court noted that here the statute of limitation must be tolled, as Heritage controlled the POA until September 9, 2002. The owner-controlled POA filed suit “approximately eight months after assuming control.”
The court also applied equitable estoppel to the statute of limitations. During the time in which Heritage controlled the board, Heritage “assured the unit owners the construction defects would be repaired, and, as a result, the owners were justified in relying on those assurances.” Since “a reasonable owner could have believed that it would be counter-productive to file suit,” the court found that also prevented Heritage from invoking the statute of limitations. In the end, the appeals court concluded that the even apart from equitable tolling and equitable estoppel, the statute of limitations could not have started until the unit owners took control of the board in September, 2002.
Heritage also contested the jury’s awarding of damages, asserting that “the POA failed to establish its damages as to any of its claims.” Noting that damages are determined “with reasonable certainty or accuracy,” and that “proof with mathematical certainty of the amount of loss or damage is not required,” the appeals court found a “sufficiently reasonable basis of computation of damages to support the trial court’s submission of damages to the jury.” Heritage also claimed that the POA did not show that the damage existed at the time of the transfer of control. The court rejected this claim as well.
Finally, Heritage argued that punitive damages were improperly applied for two reasons: that “the award of punitive damages has no deterrent effect because Appellants went out of business prior to the commencement of the litigation” and that Heritages has “no ability to pay punitive damages.” The punitive damages were upheld, as the relevant earlier decision includes “defendant’s degree of culpability,” “defendants awareness or concealment,” “existence of similar past conduct,” and “likelihood of deterring the defendant or others from similar conduct.”
The appeals court rejected all of the claims made by Heritage, fully upholding the decision of the trial court.
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
Aarow Equipment v. Travelers- An Update
January 16, 2024 —
Christopher G. Hill - Construction Law MusingsPreviously here at Musings, I discussed the application of pay if paid clauses and the Miller Act. The case that prompted the discussion was the Aarow Equipment & Services, Inc. v. Travelers Casualty and Surety Co. case in which the Eastern District of Virginia Federal Court determined that a “pay if paid” clause coupled with a proper termination could defeat a Miller Act bond claim. However, as I found out a couple of weeks ago at the VSB’s Construction Law and Public Contracts section meeting, the 4th Circuit Court of Appeals reversed and remanded this case in an unpublished opinion (Aarow Equipment & Services, Inc. v. Travelers Casualty and Surety Co.)
In it’s opinion, the 4th Circuit looked at some of the more “interesting” aspects of this case. One of these circumstances was that Syska (the general contractor) directed Aarow to construct sedimentary ponds and other water management measures around the project (the “pond work”), which both agreed was outside of the scope of the work defined in their subcontract. Syska asked that the government agree to a modification of the prime contract and asked Aarow to wait to submit its invoice for the pond work until after the government issued a modification to the prime contract and Syska issued a change order to the subcontract.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Court of Appeals Discusses the Difference Between “Claims-Made” and “Occurrence-Based” Insurance Policies
May 31, 2021 —
Garret Murai - California Construction Law BlogAs most contractors know, scope, price and time are the “big” three in any construction contract. Nearly as important, however, are the insurance provisions. Patricularly, when things go bad on a construction project. As the next case, Guastello v. AIG Specialty Insurance Company 61 Cal.App.5th 97 (2021) discusses, the difference between “claims-made” versus “occurrence-based” coverage can be extremely important.
The Guastello Case
In 2003 and 2004, subcontractor C.W. Poss Inc. built retaining walls in the Pointe Monarch housing development in Dana Point, California. Poss performed all related excavation, ground and grading work.
In 2006, Thomas Guastello purchased a home in the development, and in January 2010, a retaining wall close to his lot suffered a massive failure that causing over $700,000 in damages.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
NYPD Investigating Two White Flags on Brooklyn Bridge
July 23, 2014 —
Chris Dolmetsch – BloombergThe New York City Police Department is trying to figure out who replaced the American flags that fly atop the Brooklyn Bridge with white banners.
The replacement flags were discovered this morning on the towers at opposite ends of the bridge, where the Stars and Stripes are normally displayed, and were removed, police said.
The NYPD’s Counterterrorism Bureau and Emergency Service Unit are probing the incident and reviewing surveillance video to determine who replaced the flags and when the act took place, police said.
Read the court decisionRead the full story...Reprinted courtesy of
Chris Dolmetsch, BloombergMr. Dolmetsch may be contacted at
cdolmetsch@bloomberg.net
Toronto Skyscraper With $1.2 Billion of Debt Has Been Put in Receivership
November 16, 2023 —
Ari Altstedter - BloombergA landmark condominium project in one of Toronto’s ritziest neighborhoods has been put into receivership after construction delays and cost overruns.
Construction of the 85-story tower will be taken over by a court-appointed receiver after its owners, developer Sam Mizrahi and investor Jenny Coco, defaulted on part of the project’s nearly C$1.7 billion in debt ($1.2 billion), according to a Wednesday order from the Ontario Superior Court of Justice.
Two funds run by South Korea-based IGIS Asset Management Co. applied for the receivership. Another IGIS fund will extend at least another C$315 million to continue work on the project, court documents said.
Read the court decisionRead the full story...Reprinted courtesy of
Ari Altstedter, Bloomberg
Is Privity of Contract with the Owner a Requirement of a Valid Mechanic’s Lien? Not for GC’s
July 05, 2021 —
Christopher G. Hill - Construction Law MusingsAs any reader of this construction law blog knows, mechanic’s liens make up much of the discussion here at Construction Law Musings. A recent case out of Fairfax County, Virginia examined the question of whether contractual privity between the general contractor and owner of the property at issue is necessary. As a reminder, in most situations, for a contract claim to be made, the claimant has to have a direct contract (privity) with the entity it sues. Further, for a subcontractor to have a valid mechanic’s lien it would have to have privity with the general contractor or with the Owner.
The Fairfax case, The Barber of Seville, Inc. v. Bironco, Inc., examined the question of whether contractual privity is necessary between the general contractor and the Owner. In Bironco, the claimant, Bironco, performed certain improvements for a barbershop pursuant to a contract executed by the two owners of the Plaintiff. We wouldn’t have the case here at Musings if Bironco had been paid in full. Bironco then recorded a lien against the leasehold interest of The Barber of Seville, Inc., the entity holding the lease. The Plaintiff filed an action seeking to have the lien declared invalid because Brionco had privity of contract with the individuals that executed the contract, but not directly with the corporate entity.
Read the court decisionRead the full story...Reprinted courtesy of