Lost Productivity or Inefficiency Claim Can Be Challenging to Prove
May 02, 2022 —
David Adelstein - Florida Construction Legal UpdatesOne of the most challenging claims to prove is a lost productivity or inefficiency claim. There is an alluring appeal to these claims because there are oftentimes intriguing facts and high damages. But the allure of the presentation of the claim does not compensate for the actual burden of proof in proving the lost productivity or inefficiency claim, which will require an expert. And they really are challenging to prove.
Don’t take it from me. A recent Federal Claims Court opinion, Nova Group/Tutor-Saliba v. U.S., 2022 WL 815826, (Fed.Cl. 2022), that I also discussed in the preceding
article, exemplifies this point.
To determine lost productivity or inefficiency, the claimant’s expert tried three different methodologies.
First, the expert looked at industry standard lost productivity factors such as those promulgated by the Mechanical Contractor’s Association. However, the claimant was not a mechanical contractor and there is a bunch of subjectivity involved when using these factors. The expert decided not to use such industry standard factors correctly noting they provide value when you are looking at a potential impact prospectively, but once you incur actual damages and have real data, it is not an accurate measure.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
U.S. Housing Starts Exceed Estimates After a Stronger December
January 04, 2018 —
Sho Chandra - BloombergOriginally Published by CDJ on February 16, 2017
Builders started work on more U.S. homes than forecast in January after an upward revision to starts in the prior month, a sign construction was on a steady path entering 2017.
Residential starts totaled an annualized 1.25 million, easing from a 1.28 million pace in the prior month, a Commerce Department report showed Thursday. The median forecast of economists surveyed by Bloomberg was 1.23 million. Permits, a proxy for future construction, increased at the fastest pace since November 2015 on a pickup in applications for apartment building.
Read the court decisionRead the full story...Reprinted courtesy of
Sho Chandra, Bloomberg
A Court-Side Seat: NWP 12 and the Dakota Access Pipeline Easement Get Forced Vacations, while a Potential Violation of the Eighth Amendment Isn’t Going Anywhere
August 10, 2020 —
Anthony B. Cavender - Gravel2GavelHere’s a report on several new decisions made over the past few days.
U.S. SUPREME COURT
U.S. Army Corps of Engineers v. Northern Plains Resources Council
On July 8, 2020, the Court has issued a partial stay of the decision of the U.S. District Court for Montana, which had held that the nationwide use by the Corps of Engineers of its Nationwide Permit 12 to permit oil and gas pipelines must be vacated because the Corps, when it reissued these permits in 2012, failed to follow the requirements of the Endangered Species Act. The breadth of this ruling seems to have surprised and alarmed many past and perspective permittees of the Corps. The stay will not apply to the ongoing Ninth Circuit litigation.
FEDERAL COURTS OF APPEAL
Vega, et al. v. Semple (The U.S. Court of Appeals for the Second Circuit)
On June 29, 2020, the court refused to dismiss a putative class action by past and present inmates of Connecticut’s Garner Correctional Institution who alleged that state correctional officials exposed them to excessive amounts of radon gas in violation of the Eighth Amendment. These officials are alleged to have been “deliberately indifferent” to inmate safety. A 1993 Supreme Court decision, Helling v. McKiney, clearly established the law in this area, and the Garner facility opened in 1992. The defense clams of limited immunity as to federal law violations were rejected.
Read the court decisionRead the full story...Reprinted courtesy of
Anthony B. Cavender, PillsburyMr. Cavender may be contacted at
anthony.cavender@pillsburylaw.com
The Benefits of Incorporating AI Into the Construction Lifecycle
December 23, 2024 —
Ian Warner - Construction ExecutiveInterest in artificial intelligence has been spreading like wildfire over the past few years. AI is not a new term for Trimble, which has been capturing and leveraging construction data for decades. From hardware to software, the field to the office or among stakeholders, harnessing and making meaning out of data is the crux of Trimble’s business. Generative AI is simply a new set of tools that provide a richer narrative around data, making it more insightful and actionable.
As a company that helps connect stakeholders across the entire construction lifecycle—design, construction and operations/ maintenance—AI has been woven in and leveraged across a number of Trimble solutions to help contractors do more with less, while also giving them greater decision-making power and the ability to focus on other key challenges.
While the use cases for AI are diverse and ever-changing, below are a few key areas where Trimble has doubled down on AI, with the goal of making contractors’ jobs less cumbersome and repetitive, safer and more capable of being upskilled—efforts which will only continue to grow in the coming years.
Reprinted courtesy of
Ian Warner, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
No Damages for Delay May Not Be Enforceable in Virginia
January 08, 2024 —
Christopher G. Hill - Construction Law MusingsAnyone who reads Construction Law Musings with any regularity (thank you by the way) knows that the contract is king in most instances here in Virginia. Any commercial construction subcontractor in Virginia is likely also very familiar with so-called “no damages for delay” clauses in construction contracts. These clauses essentially state that a subcontractor’s only remedy for a delay caused by any factor beyond its control (including the fault of the general contractor), after proper notice to the general contractor, is an extension of time to complete the work. However, in 2015 the Virginia General Assembly passed a change in the law that precluded the diminishment of any right to claims for demonstrated additional costs prior to payment. This left open the question as to which types of “diminishment” would be barred by the statute.
The recent case out of the Eastern District of Virginia federal court, Strata Solar LLC v. Fall Line Construction LLC, added a bit of clarity.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
General Contractor/Developer May Not Rely on the Homeowner Protection Act to Avoid a Waiver of Consequential Damages in an AIA Contract
August 04, 2011 —
Higgins, Hopkins, McLain & Roswell, LLCRecently, in Caribou Ridge Homes, LLC v. Zero Energy, LLC, et al., Case No. 10CV1094, Boulder County District Court Judge Ingrid S. Bakke entered a ruling and order on the Plaintiff’s Motion for Determination of Question of Law Pursuant to C.R.C.P. 56(h) on Issue of Damages. The Order found that the Plaintiff was not a homeowner intended to be protected by the Homeowner Protection Act (the “HPA”) and thus could not pursue its claims for consequential damages against Defendant.
By way of background, on June 18, 2008, Plaintiff Caribou Ridge Homes, LLC (“Caribou”) entered into a Standard Form Agreement Between Owner and Contractor AIA Document A114-2001 (the “Contract”) with Defendant Zero Energy, LLC (“Zero Energy”). Plaintiff hired Zero Energy to serve as a general contractor for the construction of a single-family home in the Caribou Ridge subdivision in Nederland, Colorado. A provision in the contract contained a mutual waiver of consequential damages (“Waiver”).
Read the full story…
Reprinted courtesy Higgins, Hopkins, McLain & Roswell, LLC
Read the court decisionRead the full story...Reprinted courtesy of
Real Estate & Construction News Roundup (09/12/23) – Airbnb’s Future in New York City, MGM Resorts Suffer Cybersecurity Incident, and Insurance Costs Hitting Commercial Real Estate
October 30, 2023 —
Pillsbury's Construction & Real Estate Law Team - Gravel2Gavel Construction & Real Estate Law BlogIn our latest roundup, the FDIC handles the portfolio from Signature Bank, the U.S. Army Corps of Engineers funds a new center at Illinois, the Athletics take their next steps in their move to Las Vegas, and more!
- For those looking to rent an Airbnb for future travel to New York City, it just became much harder with new rules taking effect on September 5th. (Natalie Lung, The Washington Post)
- This past weekend MGM Resorts suffered a cybersecurity incident that affected some of the company’s systems with the extent of the incident still unknown. (ABC)
- Among issues such as rent increases and general inflation, commercial real estate is also having to contend with rising insurance costs due to climate change. (Justin Worland, Time)
Read the court decisionRead the full story...Reprinted courtesy of
Pillsbury's Construction & Real Estate Law Team
Rather Than Limit Decision to "That Particular Part" of Developer's Policy Necessary to Bar Coverage, 10th Circuit Renders Questionable Decision on Exclusion j(6)
September 06, 2021 —
William S. Bennett - Saxe Doernberger & Vita, P.C. The 10th Circuit Court of Appeals, applying Colorado law, recently extended Colorado’s broad application of the phrase “arising out of” in insurance interpretation, barring an insured real estate developer from receiving a defense to a suit alleging liability for construction of a defective retaining wall and associated resulting damage.1 The decision also included a questionable analysis of the commercial general liability (“CGL”) policy’s exclusion j(6), contradicting both the plain meaning of the exclusion as well as existing 10th Circuit case law.
The underlying dispute concerned a land developer, HT Services, LLC, who was sued by the homeowner’s association (“HOA”) of one of its developments. The HOA alleged that HT Services negligently designed and constructed a retaining wall in the community. HT Services had CGL policies from Western Heritage Insurance Company in place from 2010 to 2013 that insured it for liability associated with four acres of land that the community was built upon.
HT Services tendered the HOA’s lawsuit to Western Heritage, which declined to defend and indemnify HT Services. After that matter settled, HT Services sued Western Heritage, alleging breach of contract and bad faith. Western Heritage moved for summary judgment, asserting two exclusions, and the District Court granted the motion in Western Heritage’s favor. In upholding the District Court’s decision, the 10th Circuit discussed two exclusions that the District Court determined precluded coverage.
Read the court decisionRead the full story...Reprinted courtesy of
William S. Bennett, Saxe Doernberger & Vita, P.C.Mr. Bennett may be contacted at
wsb@sdvlaw.com