Not All Design-Build Projects are Created Equal
June 28, 2021 —
Nicole Markowitz & Richard Robinson - Peckar & Abramson, P.C.As the need for faster and more efficient construction increases, design-build agreements are growing in popularity. Design-build projects may account for 44% of nonresidential building in the United States this year. However, contractors who venture into a “design builder” role may unexpectedly become liable for design errors/omissions that are not covered by their insurance policies. In turn, they may expose themselves to liability and insurance risks that are neither insured nor managed.
In this article, we’ll discuss how the contractor who becomes a design-builder, or performs design-related work through subcontractors, faces potentially unmanaged risk. We will also explore indemnity, warranty, and insurance traps by paying attention to contract language in both traditional design-build and design-assist scenarios.
Reprinted courtesy of
Nicole Markowitz, Peckar & Abramson, P.C. and
Richard Robinson, Peckar & Abramson, P.C.
Ms. Markowitz may be contacted at nmarkowitz@pecklaw.com
Mr. Robinson may be contacted at rrobinson@pecklaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Brookfield Wins Disputed Bid to Manage Manhattan Marina
January 28, 2015 —
Martin Z Braun – Bloomberg(Bloomberg) -- Brookfield Property Partners won a bid to run a marina in New York’s Battery Park City neighborhood over the objections of residents backing a local businessman who operated the facility and a popular sailing club and school.
The state’s Battery Park City Authority voted Thursday to approve a 10-year agreement with Brookfield, which owns an adjacent 8 million-square-foot office and retail complex. Brookfield is bringing in billionaire real estate investor Andrew Farkas’s Island Global Yachting to manage the North Cove Marina.
Read the court decisionRead the full story...Reprinted courtesy of
Martin Z Braun, BloombergMr. Braun may be contacted at
mbraun6@bloomberg.net
Factor the Factor in Factoring
May 03, 2017 —
David Adelstein - Florida Construction Legal UpdatesWhat is factoring? Have you heard this term used in the business context? Factoring is not uncommon in the business world. It comes up when a business is in need of cash (immediate cash flow) and sells/assigns money owed under accounts receivable to a third party known as a factor. The factor purchases the accounts receivable at a discount in consideration of an assignment of the full value of the accounts receivable from the debtor (the entity that owes the money under the accounts receivable). The factoring arrangement is a recognized relationship, implicates Florida’s Uniform Commercial Code, and places obligations on the debtor to pay the factor directly for the accounts receivable upon notice of the assignment.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Florida Construction Legal UpdatesMr. Adelstein may be contacted at
Dadelstein@gmail.com
Reminder: Your Accounting and Other Records Matter
July 30, 2015 —
Christopher G. Hill – Construction Law MusingsRecently, I’ve posted on mechanic’s lien changes, mediation and other more “legal” topics here at Construction Law Musings. Today’s post is a practical one and one that will help your friendly neighborhood construction attorney greatly should a dispute arise.
The tip for this week? Keep clean accounting and other records by construction job and in an organized fashion. This tip seems like a simple one, but I run into situations where the accounting on jobs, contracts, invoices and other key documents for a project are either missing or haphazardly kept. In the best of these cases, I have to spend additional time (read attorney fees) to attempt a recreation of the job costs and flow of the project. In the worst, I have had to either release or avoid filing what could have been a valid mechanic’s lien because timing could not be determined from the records. I also thank my friend Craig Martin for another unfortunate horror story of poor accounting that should be a warning to us all.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, Law Office of Christopher G. Hill, PCMr. Hill may be contacted at
chrisghill@constructionlawva.com
New York Court of Appeals Finds a Proximate Cause Standard in Additional Insured Endorsements
June 15, 2017 —
Geoffrey Miller - Saxe Doernberger & Vita, P.C.In The Burlington Insurance Company v. NYC Transit Authority, et al., No. 2016-00096, the New York Court of Appeals issued a landmark decision with regard to the meaning of “caused, in whole or in part, by” in the additional insured context. In a split decision, the court rejected Burlington Insurance Company’s argument that the language implied a “negligence” standard, but held that coverage was provided to the additional insured only where the named insured’s acts or omissions were the proximate cause of the injury:
While we [the majority] agree with the dissent that interpreting the phrases differently does not compel the conclusion that the endorsement incorporates a negligence requirement, it does compel us to interpret ‘caused, in whole or in part’ to mean more than ‘but for’ causation. That interpretation, coupled with the endorsement’s application to acts or omissions that result in liability, supports our conclusion that proximate cause is required here.[1]
Read the court decisionRead the full story...Reprinted courtesy of
Geoffrey Miller, Saxe Doernberger & Vita, P.C.Mr. Miller may be contacted at
gjm@sdvlaw.com
A General Contractor’s Guide to Additional Insured Coverage
August 10, 2017 —
Gregory D. Podolak - Saxe Doernberger & Vita, P.C.LAW360.com recently surveyed attorneys to offer tips for what general contractors should – and shouldn’t – do when pursuing additional insured coverage. According to the article, “With the broad array of risks present on a typical construction site, one of a general contractor’s top options to shield itself from liability for property damage and bodily injury claims is to secure expansive “additional insured” coverage through its subcontractors.”
In the piece, Greg Podolak discussed techniques for avoiding potential gaps in coverage:
“Carriers will try to say in the additional insured endorsement that they will only be responsible to provide limits for what is required in the trade contract,” said Greg Podolak, managing partner of Saxe Doernberger & Vita PC’s southeast office. “If it turns out the trade contract requires lower limits than the policy, the insurer will likely say it only wants to be responsible for those lower limits.”
Read the court decisionRead the full story...Reprinted courtesy of
Gregory D. Podolak, Saxe Doernberger & Vita, P.C.Mr. Podolak may be contacted at
gdp@sdvlaw.com
Recovering For Inflation On Federal Contracts: Recent DOD Guidance On Economic Price Adjustment Clauses
October 24, 2022 —
Amanda L. Marutzky - ConsensusDocsSince October 2020, inflation in the United States has seen its fastest increase in more than 30 years. In the last year alone, inflation has remained as high as 8.6%. This hike has impacted everything from diesel to steel. In the construction industry, the higher prices of goods and services directly affect how contractors draft their construction contracts.
The Department of Defense (DoD) has taken note of this dramatic price increase and recently issued guidance to its commanding officers and the procurement community. On May 5, 2022, DoD issued a memorandum titled “Guidance on Inflation and Economic Price Adjustments.” The stated purpose of the memo is “to assist COs to understand whether it is appropriate to recognize cost increases due to inflation under existing contracts as well as offer considerations for the proper use of EPA when entering into new contracts.” DoD’s memo responds to contractor and contracting officer concerns about the sudden and unexpected cost increases in labor and materials.
Economic Price Adjustments, or EPAs, are adjustments to a stated contract price upon the occurrence of certain contingencies. FAR 16.203-1. They are of three general types – (1) adjustments based on established prices, (2) adjustments based on actual costs of labor or material, or (3) adjustments based on cost indexes of labor or material. Id. Because EPAs allow for adjustments in a contract price, EPA clauses allow a contractor to recover unanticipated increases in its project costs. For example, FAR 52.216-4, Economic Price Adjustment-Labor and Material, authorizes a contractor to recover for increases in the cost of material or labor. Such recovery is available when costs increase more than 3%, with a maximum recovery of 10% of the original contract price. See also FAR 52.216-2 through FAR 52.216-4. These EPA clauses provide contractors with relief and protection from issues such as dramatic inflation. EPA clauses, however, are not included in all contracts.
Read the court decisionRead the full story...Reprinted courtesy of
Amanda L. Marutzky, Watt, Tieder, Hoffar, & Fitzgerald, LLP (ConsensusDocs)Ms. Marutzky may be contacted at
amarutzky@watttieder.com
Real Estate & Construction News Roundup (1/16/24) – Algorithms Affect the Rental Market, Robots Aim to Lower Construction Costs, and Gen Z Struggle to Find Their Own Space
February 12, 2024 —
Pillsbury's Construction & Real Estate Law Team - Gravel2Gavel Construction & Real Estate Law BlogIn our latest roundup, New York’s Prompt Payment Act comes into question, vacancy rates rise in commercial office space, the Biden administration applies project labor agreements on certain federal construction projects, and more!
Read the court decisionRead the full story...Reprinted courtesy of
Pillsbury's Construction & Real Estate Law Team