Another Reason to Always Respond (or Hensel Phelps Wins One!)
September 16, 2019 —
Christopher G. Hill - Construction Law MusingsHere at Construction Law Musings, Hensel Phelps Construction Co. is best known as the company that got whipsawed between indemnity rules and the lack of a statute of limitations for state agencies. However a recent case out of the Federal District Court for the Eastern District of Virginia gave them a win and illustrates, once again, that failing to appear or respond is never a good option.
In Hensel Phelps Construction Co. v. Perdomo Industrial LLC, the Alexandria, VA federal court looked at an arbitration award entered for Hensel Phelps and against Perdomo under the Federal Arbitration Act. The facts of the case showed that Perdomo “double dipped” into the deep end of refusal or failure to respond. First of all, the contract required arbitration and any award was enforceable in any state or federal court having jurisdiction. Based upon this language, Hensel Phelps filed a demand for arbitration with the American Arbitration Association against Perdomo and its surety, AAA sent notice to both Perdomo and Surety, and. . . neither responded or appeared at what was ultimately 8 days of hearings. After hearing Hensel Phelp’s evidence and the total lack of defenses from Perdomo and Surety, the panel issued an award in favor of Hensel Phelps, finding Perdomo LLC in default and holding Perdomo LLC and Allied World jointly and severally liable in the amount of $2,958,209.71 and Perdomo LLC individually liable in the amount of $7,917,666.30 plus interest.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Keeping KeyArena's Landmark Lid Overhead at Climate Pledge Arena Redevelopment Is A 22,000-Ton Balancing Act
November 30, 2020 —
Nadine M. Post - Engineering News-RecordMost contractors would jump at the chance to have a roof overhead during a major rebuild. But for the team turning earthquake-prone Seattle’s 411,000-sq-ft KeyArena into the 932,000-sq-ft Climate Pledge Arena, the city-owned facility’s historic helmet has been a 44-million-lb design and construction headache.
Reprinted courtesy of
Nadine M. Post, Engineering News-Record
Ms. Post may be contacted at postn@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Fannie-Freddie Elimination Model in Apartments: Mortgages
April 08, 2014 —
Sarah Mulholland – BloombergThe apartment-lending units of Fannie Mae (FNMA) and Freddie Mac were among their few money makers after the U.S. housing collapse. Now they should help transform the U.S. mortgage industry.
Lawmakers seeking to eliminate the two government lenders, which were seized by regulators during the 2008 credit crisis, see an antidote to the reckless lending that blew up the U.S. housing market in the structure of the firms’ multifamily operations, which share risks with lenders.
Senate Banking Committee Chairman Tim Johnson and Republican Mike Crapo are proposing legislation to create a new government-backed reinsurer of mortgage bonds that would require private investors to bear losses on the first 10 percent of capital. The model for the provision mirrors Fannie Mae and Freddie Mac (FMCC)’s multifamily lending operations, requiring lenders to shoulder some of the risk on loans they originate.
Read the court decisionRead the full story...Reprinted courtesy of
Sarah Mulholland, BloombergMs. Mulholland may be contacted at
smulholland3@bloomberg.net
Former UN General Assembly President Charged in Bribe Scheme
October 21, 2015 —
Patricia Hurtado & Greg Farrell – BloombergA former president of the United Nations General Assembly and a billionaire Macau developer were accused of taking part in a four-year corruption scheme that included bribes to help fund a campaign for the post at the organization in exchange for the promotion of Chinese businesses.
John Ashe, president of the UN General Assembly from September 2013 to September 2014, accepted more than $1 million in payoffs from developer Ng Lap Seng and an associate to help persuade the international body to build a multibillion-dollar conference center in Macau and promote Chinese businesses, including a bank, in Antigua, according to the U.S.
The new charges, announced Tuesday, relate to an earlier case against Ng, 68, who has a personal net worth of about $1.8 billion. He’s been held in a federal jail in Manhattan since he was arrested Sept. 19, accused of bringing $4.5 million into the country and lying about its purpose to U.S. authorities.
Reprinted courtesy of
Patricia Hurtado, Bloomberg and
Greg Farrell, Bloomberg
Read the court decisionRead the full story...Reprinted courtesy of
New York Appellate Court Restores Insurer’s Right to Seek Pro Rata Allocation of Settlements Between Insured and Uninsured Periods
March 28, 2022 —
Patricia B. Santelle & Frank J. Perch, III - White and Williams LLPIn Liberty Mut. Ins. Co. v. Jenkins Bros., 2022 N.Y. App. Div. LEXIS 1846 (App.Div. 1st Dept. March 22, 2022), the New York Supreme Court, Appellate Division, First Department, issued a ruling reversing the trial court and holding that an insurer was entitled to allocate a portion of asbestos claim settlements it negotiated to time periods when its dissolved insured was without coverage.
The decision overturns a trial court ruling that the insurer was barred from denying liability for the full amount of the settlements because the insurer had become the “real party in interest” as a result of a prior court order directing it to accept service of process on behalf of a dissolved insured. The trial court held that the insurer stood in the shoes of the insured for all purposes by accepting service and negotiating settlements, and was therefore estopped from denying liability for the full amount of the settlements.
Reprinted courtesy of
Patricia B. Santelle, White and Williams LLP and
Frank J. Perch, III, White and Williams LLP
Ms. Santelle may be contacted at santellep@whiteandwilliams.com
Mr. Perch may be contacted at perchf@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of
Anti-Concurrent Causation Clause Bars Coverage for Pool Damage
February 23, 2016 —
Tred R. Eyerly – Insurance Law HawaiiRelying upon the policy's anti-concurrent causation clause, the Illinois Court of Appeals affirmed the trial court's ruling that there was no coverage for a pool that popped out of the ground. Bozek v. Erie Ins. Group, 2015 Ill. App. LEXIS 940 (Ill. Ct. App. Dec. 17, 2015).
Following a rainstorm, the insureds reported damage to the swimming pool to Erie. An investigation determined that the heavy rain saturated soils around the pool. This created a significant uplift hydrostatic pressure. The weight of the water in the pool typically prevented the uplift forces, but the pool had been emptied to clean debris making it susceptible to uplift. The pool had a pressure relief valve to prevent uplift, but it was not working properly.
As a result, the pool was damaged to the point that it had to be replaced in its entirety. The heaving of the pool also damaged the concrete slab around the pool, which also had to be replaced.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
How Will Today’s Pandemic Impact Tomorrow’s Construction Contracts?
October 26, 2020 —
Levi W. Barrett, Nathan A. Cohen & Mark A. Snyder - Peckar & AbramsonThe emergence of COVID-19 has created a new set of challenges in the already complex world of negotiating construction contracts. In the pre-COVID-19 era, general contractors, construction managers and those negotiating on their behalf, needed to balance a variety of fairly well-established legal risks and exposures and commercial realities with the need to maintain a positive relationship with their counterparty. While many are rightfully concerned with addressing the impacts of COVID-19 to their on-going projects, those negotiating new contracts now are undoubtedly cognizant that they are negotiating in the midst of an unpredictable future that is tipping the historical negotiating balance. The following presents some crucial areas to focus on when negotiating and drafting your contracts in this new era.
Contract Terms Through the COVID-19 Lens
Contractors should examine proposed new contracts carefully to identify rights that afford COVID-19 protections and identify contractual obligations that create COVID-19 commercial risks.
Specific attention should be paid to those sections relating to force majeure/excusable delay, emergencies, changes (including changes in law), contingency, suspension and termination, site investigation as well as all representations and warranties. The paramount concern in examining these provisions is to ensure that they not only entitle the contractor to relief for those unknown events, emergencies and changes, but that they also contain sufficient entitlement for the contractor to obtain both time extensions and financial compensation for unknown impacts of a known event – the COVID-19 pandemic.
Reprinted courtesy of
Levi W. Barrett, Peckar & Abramson, P.C.,
Nathan A. Cohen, Peckar & Abramson, P.C.and
Mark A. Snyder, Peckar & Abramson, P.C.
Mr. Barrett may be contacted at lbarrett@pecklaw.com
Mr. Cohen may be contacted at ncohen@pecklaw.com
Mr. Snyder may be contacted at msnyder@pecklaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Venue for Miller Act Payment Bond When Project is Outside of Us
December 02, 2019 —
David Adelstein - Florida Construction Legal UpdatesThe proper venue for a Miller Act payment bond claim is “in the United States District Court for any district in which the contract was to be performed and executed, regardless of the amount in controversy.” 40 U.S.C. s. 3133(b)(3)(B).
Well, there are a number of federal construction projects that take place outside of the United States. For these projects, where is the correct venue to sue a Miller Act payment bond if there is no US District Court where the project is located? A recent opinion out of the Southern District of Florida answers this question.
In U.S. ex. rel. Salt Energy, LLC v. Lexon Ins. Co., 2019 WL 3842290 (S.D.Fla. 2019), a prime contractor was hired by the government to design and construct a solar power system for the US Embassy’s parking garage in Burkina Faso. The prime contractor hired a subcontractor to perform a portion of its scope of work.
The subcontractor remained unpaid in excess of $500,000 and instituted a Miller Act payment bond claim against the payment bond surety in the Southern District of Florida, Miami division. The surety moved to transfer venue to the Eastern District of Virginia arguing that the Southern District of Florida was an improper venue. The court agreed and transferred venue. Why?
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com