Colorado SB 15-177 UPDATE: Senate Business, Labor, & Technology Committee Refers Construction Defect Reform Bill to Full Senate
April 01, 2015 —
Derek J. Lindenschmidt – Higgins, Hopkins, McLain & Roswell, LLCOn March 18th, following a lengthy hearing with testimony and questioning for and against Senate Bill 15-177, the Senate Business, Labor & Technology Committee voted 6 to 2 to refer the bill, with new amendments, to the full Senate.
While the main points of the bill remain strongly intact (check here for Senate Bill 177’s particulars), bill sponsors Senators Scheffler and Ulibarri offered four amendments, designed to bring additional compromise and clarity to the bill. The committee ultimately adopted these amendments, described below.
Amendment 16 removed a prior prohibition in the bill that would have prevented attorneys from assisting in the preparation of the notice required to be provided to all homeowners before the commencement of a construction defect claim. Amendment 19 complemented 16 by providing further clarification regarding the contents and specificities required in said notice, including a disclosure of projected attorneys’ fees, costs, duration, and financial impact of pursuing construction defect claims. Amendment 17 permitted homeowners to approve the pursuit of construction defect claims through written consent. Lastly, Amendment 18 provided clarification regarding the bill’s requirement that mediators and arbitrators be selected and approved through mutual agreement of the parties.
Read the court decisionRead the full story...Reprinted courtesy of
Derek J. Lindenschmidt, Higgins, Hopkins, McLain & Roswell, LLCMr. Lindenschmidt may be contacted at
lindenschmidt@hhmrlaw.com
Construction Defects Claims Can Be Limited by Contract Says Washington Court
February 11, 2013 —
CDJ STAFFThe firm Lane Powell has issued a construction law update on the recent Washington Supreme Court decision in Washington State Major League Baseball Public Facility District v. The Baseball Club of Seattle, LP. In the underlying construction defect claim, the Public Facility District found defects in the structural steel at Seattle’s Safeco Field. The contractor, Huber, Hunt & Nichols-Kiewit Construction Company claimed that construction claims could not be made, as it was barred by the statue of repose.
Washington State has a six-year limitation on its statute of repose, however, the court noted that the contract contained a clause that, as noted by Lane Powell, “any alleged causes of action automatically accrue at substantial contemplation,” instead of within six years of substantial completion. The court concluded that the statue of repose could be rendered inoperative by contract. Further, the court found that these contract clauses pertained to subcontractors as well.
Nevertheless, as PFD is a subdivision of the state, the court found that no statue of limitations could be appled.
Read the court decisionRead the full story...Reprinted courtesy of
The Coverage Fun House Mirror: When Things Are Not What They Seem
December 14, 2020 —
Randy J. Maniloff - White and Williams LLPWhen it comes to commercial general liability coverage, sometimes things are not what they seem. Some policy language looks like it has a clear meaning. But it turns out that there is more than meets the eye. To see this, you need not look further than the first page of the commercial general liability form. Take its insuring agreement. Its words are by now etched in stone tablets. But even so.
Any potential coverage is tied, in part, to damages because of “bodily injury.” Everyone knows what “bodily injury” is. The blood and broken bones are hard to miss. But is emotional injury bodily injury? Or what about hair loss, weight loss, fragile fingernails, loss of sleep, crying or a knot in your stomach? Courts have been required to address whether all of these are “bodily injury.”
And was that “bodily injury” caused by an “occurrence?” as required by the CGL insuring agreement? An “occurrence” is defined as an accident. Of course everyone knows what an accident is. Then why is it the oldest and most litigated coverage question of them all, with courts struggling with it for about 150 years?
Read the court decisionRead the full story...Reprinted courtesy of
Randy J. Maniloff, White and Williams LLPMr. Maniloff may be contacted at
maniloffr@whiteandwilliams.com
In a Win for Design Professionals, California Court of Appeals Holds That Relation-Back Doctrine Does Not Apply to Certificate of Merit Law
December 20, 2017 —
Garret Murai - California Construction Law BlogThe year was 1995. The old guard was still in power in Sacramento. “Button-Down” Pete Wilson was Governor. Willie Brown, the self-nicknamed “Ayatollah of the Assembly,” was Speaker of the Assembly. And Bill “Huggy” Lockyer was Senate Pro Tem. Names that, for many reasons as of late, seem . . . well . . . let’s just say, “quaint.”
Their time, however, was coming to an end. Three years earlier, California voters approved Proposition 140, which instituted term limits for the first time in California. And by 1996, the first slate of legislators would be “termed out.” The immediate impact: It was the time for making deals because you didn’t know who would be keeping house next.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel, Rosen, Black, Dean LLPMr. Murai may be contacted at
gmurai@wendel.com
Trump, Infrastructure and the Construction Industry
March 01, 2017 —
Garret Murai – California Construction Law BlogIt’s been a whirlwind since Donald Trump became President. Some might even say a tornado.
Many believed (including myself) that he couldn’t win. I was wrong. Some also believed (again, including myself) that he wouldn’t make good on his campaign promises. So far, he has.
While I usually don’t like being wrong, if there’s one thing I couldn’t be happier being wrong about, it’s President Trump’s promises to rebuild the nation’s infrastructure.
So, what can the construction industry expect under our first developer-turned-POTUS, Donald Trump, who is arguably the most exciting President for the construction industry since FDR?
Where We Are Today
The American Society of Engineers, in its oft-cited infrastructure “Report Card,” gave nation’s infrastructure an overall grade of D+, with an estimated investment infusion of $3.6 trillion needed by 2020 just to keep the nation’s infrastructure in “good” (note, not “great”) repair.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel Rosen Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com
Is Performance Bond Liable for Delay Damages?
October 20, 2016 —
David Adelstein – Florida Construction Legal UpdatesThere is an argument that a performance bond is not liable for delay damages UNLESS the bond specifically allows for the recovery of such damages. Keep this in mind when requiring a performance bond so that the bond covers the associated risks (and damages) you contemplate when requiring the bond. This argument is supported by the Florida Supreme Court’s 1992 decision in American Home Assur. Co. v. Larkin General Hosp., Ltd., 593 So.2d 195, 198 (Fla. 1992):
The language in the performance bond, construed together with the purpose of the bond, clearly explains that the performance bond merely guaranteed the completion of the construction contract and nothing more. Upon default, the terms of the performance bond required American [performance bond surety] to step in and either complete construction or pay Larkin [obligee] the reasonable costs of completion. Because the terms of the performance bond control the liability of the surety, American’s liability will not be extended beyond the terms of the performance bond. Therefore, American cannot be held liable for delay damages.
However, the Eleventh Circuit in National Fire Ins. Co. of Hartford v. Fortune Const. Co., 320 F.3d 1260(11th Cir. 2003), also analyzing an issue relating to the recoverability of delay-type damages against a performance bond, did not narrowly interpret the Florida Supreme Court’s decision in Larkin General Hospital.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Katz, Barron, Squitero, Faust, Friedberg, English & Allen, P.A.Mr. Adelstein may be contacted at
dma@katzbarron.com
Fine Art Losses – “Canvas” the Subrogation Landscape
February 26, 2024 —
William L. Doerler - The Subrogation StrategistIf a fire or flood destroys a high-net-worth client’s fine art collection, an insurer who pays out a claim related to the loss has an incentive to pursue subrogation. This article explores some of the issues an insurer should “canvas” before pursuing subrogation for these types of claims.
Damage to fine art can occur in a number of ways. For instance, fine art may be damaged in a natural disaster – such as a flood or a wildfire. Artwork may also be accidentally damaged because of a transportation-related incident physically damaging the art. In addition, artwork may suffer fire or smoke damage from a fire within a building. Another possibility is that the artwork suffers damage because of renovations either to the insured’s home or a neighboring property. For example, a renovation contractor may damage artwork due to vibrations or leaking water. A construction worker, moreover, may turn with a tool in his hand, or trip and fall, damaging the artwork.
Read the court decisionRead the full story...Reprinted courtesy of
William L. Doerler, White and Williams LLPMr. Doerler may be contacted at
doerlerw@whiteandwilliams.com
Designed to Expose: Beware Lender Certificates
August 20, 2018 —
Jacob Goodelman - Gordon & Rees Construction Law BlogDanny the Developer wishes to build Greenacre, a large residential and retail condominium complex in downtown Boston. However, Danny’s lender – the Bank of Barbara – will not lend Danny the money to develop the complex unless Danny’s architect signs a lender certificate. Danny presents the lender certificate to Allie the Architect, the certificate is relatively short and simple, it states:
“Allie the Architect prepared plans and specifications relating to Greenacre. Allie the Architect certifies that the plans are in accordance with all applicable zoning, building, housing and other laws, ordinances, regulations including but not limited to the Federal Fair Housing Act, the Uniform Federal Accessibility Standards, and the Americans with Disability Act. The Plans do not encroach over, across or upon any such easements, rights-of-way, or subsurface rights and the like. Allie further certifies that the load bearing capacity of the soil is adequate to support the plans. The Bank of Barbara shall rely upon Allie the Architects certification in loaning money to Danny the Developer for Greenacre.”
Read the court decisionRead the full story...Reprinted courtesy of
Jacob Goodelman, Gordon Rees Scully MansukhaniMr. Goodelman may be contacted at
jgoodelman@grsm.com