Party Cannot Skirt Out of the Very Fraud It Perpetrates
January 09, 2023 —
David Adelstein - Florida Construction Legal UpdatesAn interesting case came out of Florida’s Fourth District Court of Appeal that touches upon two important points.
First, the
independent tort doctrine does not apply when there is not a contract between the parties.
Second, an officer cannot escape fraud simply by claiming his or her actions were done as an officer of the company when he or she actively participated in the fraud.
Both of these points are best explained by initially going into the facts of this case. As you will see, the Court’s rationale relates to the premise that a party should not be able to skirt out of the very fraud it perpetrates.
Factual Background
Costa Investors, LLC v. Liberty Grande, LLC, 48 Fla.L.Weekly D7b (Fla. 4th DCA 2022) involved the ultimate development and construction of four adjacent properties into the Costa Hollywood Hotel. The properties were purchased by a company called Liberty Grande. Its president / manager was also the president of Liberty Grande’s wholly owned subsidiary called Costa Hollywood Property. Liberty Grande transferred the properties to Costa Hollywood Property and the deed was signed by the president / manager.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Don’t Assume Your Insurance Covers A Newly Acquired Company
February 19, 2019 —
Patrick M. McDermott & Michael S. Levine - Hunton Insurance Recovery BlogThe Supreme Court of Virginia’s decision yesterday finding no coverage for fire damage to a building is a cautionary tale for companies acquiring other companies. Erie Ins. Exch. v. EPC MD 15, LLC, 2019 WL 238168 (Va. Jan. 17, 2019). In that case, Erie Insurance issued a property insurance policy to EPC. The policy covered EPC only and did not cover any subsidiaries of EPC. EPC then acquired the sole member interest in Cyrus Square, LLC. Following the acquisition, fire damaged a building that Cyrus Square owned.
EPC sought coverage under its property insurance policy. Because the policy did not cover Cyrus Square, EPC argued that a provision extending coverage to “newly acquired buildings” applied, contending that EPC had newly acquired Cyrus Square’s building by virtue of becoming the sole member interest in the LLC. Based on the law relative to LLCs and its interpretation of the policy, the Supreme Court of Virginia ruled against EPC. It found that although EPC had acquired Cyrus Square, it had not “newly acquired” the building and so the “newly acquired buildings” coverage extension did not apply.
Reprinted courtesy of
Patrick M. McDermott, Hunton Andrews Kurth and
Michael S. Levine, Hunton Andrews Kurth
Mr. McDermott may be contacted at pmcdermott@HuntonAK.com
Mr. Levine may be contacted at mlevine@HuntonAK.com
Read the court decisionRead the full story...Reprinted courtesy of
Legislative Update: Bid Protest Law Changes to Benefit Contractors
November 24, 2019 —
Brett M. Hill - Ahlers Cressman & Sleight PLLCA new statute became effective July 28, 2019 that benefits contractors who have bid protests in Washington. A bid protest is the only way for disappointed bidders to challenge irregularities in the public bidding process on public works projects. Bid protests ensure the integrity of the public bidding system and are the contractor’s only remedy if its bid is improperly rejected or the winning bidder has errors in its bid that render it nonresponsive.
Under the old law, a contractor was required to submit their bid protest within 2 days after the bid opening. The problem was that a contractor often does not know the basis to protest an award without seeing the other bids to determine whether the winning bid was responsive. Many owners provide copies of the bids if requested at the bid opening, but some contractors found that owners were refusing to provide copies of the other bids until after the 2-day protest period expired.
The new law, which passed this last Legislative session[1], states that a contractor has two days after the bid opening to either submit a written protest or request copies of the competing bids. If the contractor requests copies of the competing bids from the owner, the contractor then has until 2 days after the competing bids are provided by the owner before the contractor is required to submit its bid protest.
Read the court decisionRead the full story...Reprinted courtesy of
Brett M. Hill, Ahlers Cressman Sleight PLLCMr. Hill may be contacted at
brett.hill@acslawyers.com
When Employer’s Liability Coverage May Be Limited in New York
June 28, 2021 —
Robert S. Nobel & Craig Rokuson - Traub LiebermanNew York recognizes that coverage under Workers’ Compensation (“WC”) and Employer’s Liability (“EL”) policies is generally unlimited. See Tully Const. Co. v. Illinois Nat. Ins. Co., 131 A.D.3d 598 (2d Dept. 2015); Oneida Ltd. v. Utica Mut. Ins. Co., 263 A.D.2d 825, 694 N.Y.S.2d 221 (3d Dept. 1999). However, there is case holding that EL coverage may be limited in certain instances, such as when the primary EL carrier is listed as scheduled underlying insurance on an excess policy.
In Liberty Mut. Ins. Co. v. Ins. Co. of State of Pennsylvania, 43 A.D.3d 666, 841 N.Y.S.2d 288 (1st Dept. 2007), an employee of General Industrial Service Corporation (“General”), a subcontractor on a construction project, sought to recover under New York’s Labor Law against the project’s owner and construction manager. Those defendants, in turn, brought a third-party action for indemnification against General. The employee’s personal injury claim was ultimately settled for $2.5 million. After the settlement, the excess insurer, Liberty, filed suit against the primary employer’s liability insurers, The Insurance Company of the State of Pennsylvania and American International Group of Companies (collectively, “AIG”), which had refused to participate in the defense or settlement of the underlying personal injury litigation. Although the issue of whether the plaintiff in the underling action had sustained a “grave injury” (necessary to support the common law indemnity claim against General and trigger coverage under the Employer’s Lability policy) had not yet been determined, the court held that “[i]n the event the existence of a grave injury is proven, AIG’s liability will be limited to $1 million.”
Reprinted courtesy of
Robert S. Nobel, Traub Lieberman and
Craig Rokuson, Traub Lieberman
Mr. Nobel may be contacted at rnobel@tlsslaw.com
Mr. Rokuson may be contacted at crokuson@tlsslaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Duty to Defend Construction Defect Case Triggered by Complaint's Allegations
August 20, 2014 —
Tred R. Eyerly – Insurance Law HawaiiThe subcontractor's insurer could not escape contributing to defense costs of its insured when coverage was possible based upon the underlying complaint's allegations. Seneca Ins. Co. v. James River Ins. Co., 2014 U.S. Dist. LEXIS 97156 (D. Ore. July 17, 2014).
The underlying action alleged construction defects in a 60-unit complex located in Seaside, Oregon. S.D. Deacon Corp. was the general contractor and contracted with the owners association to reconstruct portions of the building, including the curtain wall. Deacon subcontracted with Superwall Design, LLP for work on the curtain wall renovation.
At some point not specified in the underlying complaint, the Association notified Deacon of construction defects in the curtain wall renovation. Deacon investigated and concluded that the alleged property damage was the result of inadequate usage of materials, violations of state and local building codes, and violations of relevant industry standards relating to the work performed by Superwall. Deacon contended that the problems were caused by Superwall's faulty workmanship.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Avoiding Disaster Due to Improper Licensing
February 18, 2019 —
Candace Matson - Construction & Infrastructure Law BlogIT’S NOT ENOUGH FOR A CONTRACTOR TO BE LICENSED . . . it must be properly licensed.
We are reminded of this by the recent case of JMS Air Conditioning and Appliance Service, Inc. v. Santa Monica Community College District, Bernards Bros., Inc., 30 Cal. App. 5th 945 (2018). In that case, JMS entered into an $8.2M subcontract with Bernards to install an HVAC system in a new facility being built for the District. JMS held a C-20 warm-air heating, ventilating and air-conditioning license. A year into the project, Bernards sought permission from the District to substitute another subcontractor for JMS (as required under Public Contract Code Section 4107 for listed subcontractors on public works of improvement). Among other things, Bernards contended that JMS was not properly licensed to perform that portion of the work which consisted of hydronic plumbing and hydronic boiler work. JMS countered that this work was an integral part of installing an HVAC system, and relied on Business & Profession Code Section 7059, which permits work that is “incidental and supplemental to the performance of the work for which the specialty contractor is licensed,” and a California State Licensing Board regulation which defines “incidental and supplemental” as meaning “essential to accomplish the work in which the contractor is classified.” (Cal. Code Regs., tit. 16, §831.)
Read the court decisionRead the full story...Reprinted courtesy of
Candace Matson, Sheppard MullinMs. Matson may be contacted at
cmatson@sheppardmullin.com
Chambers USA 2021 Ranks White and Williams as a Leading Law Firm
June 07, 2021 —
White and Williams LLPWhite and Williams is once again recognized by Chambers USA as a leading law firm in Pennsylvania for achievements and client service in the areas of insurance law, real estate finance and banking and finance law. The firm has also been recognized for achievements and client service in banking and finance law in Philadelphia and the surrounding area. In addition, five lawyers received individual honors – two for their work in insurance, one for his work in real estate finance, another for her work in bankruptcy and restructuring and one for his work in commercial litigation.
White and Williams is acknowledged for our renowned practice offering exceptional representation to insurers and reinsurers across an impressive range of areas including coverage, bad faith litigation and excess liability. The firm is recognized for notable strength in transactional and regulatory matters, complemented by the team's adroit handling of complex alternative dispute resolution proceedings. Chambers USA also acknowledged the firm's broad trial capabilities, including handling data privacy, professional liability, toxic tort coverage claims, and experience in substantial claims arising from bodily injury and wrongful death suits. White and Williams' cross-disciplinary team is also highlighted, as one source commented that "all advice was reasoned and respectful. They worked well together and provided exceptional representation."
Read the court decisionRead the full story...Reprinted courtesy of
White and Williams LLP
ACEC Research Institute Releases New Engineering Industry Forecast
December 13, 2021 —
American Council of Engineering CompaniesWashington, DC, Dec. 09, 2021 (GLOBE NEWSWIRE) -- Today, the ACEC Research Institute released two new reports on the Engineering and Design Services industry: the 2021 Economic Assessment of the Engineering and Design Services Industry and a new Engineering Business Sentiment report for Q4 2021.
The data shows the industry has rebounded from project postponements due to COVID, though firms identify a tight labor market and lack of qualified workers as continued barriers to growth across public and private markets.
This is the second annual release of the Engineering and Design Services industry assessment, which tracks the industry's economic contributions, analyzes key economic drivers, and forecasts industry growth.
Snapshot of the Engineering and Design Services Industry:
1.5 million direct full- and part-time jobs
$97,300 average yearly wages
$338 billion in industry sales
$198 billion direct economic contribution
$105 billion collected in total federal, state & local tax
Both reports, the 2021 Economic Assessment of the Engineering and Design Services Industry and the Engineering Business Sentiment report for Q4 2021, are available for download by clicking
here.
###
The ACEC Research Institute is the research arm of the American Council of Engineering Companies – the business association of the nation's engineering industry. The ACEC Research Institute's mission is to deliver knowledge and business strategies that guide and elevate the engineering industry and to be the leading source of knowledge and thought leadership for creating a more sustainable, safe, secure and technically advanced built environment. For more information, go to www.acecresearchinstitute.org.
Read the court decisionRead the full story...Reprinted courtesy of