Lien Attaches To Landlord’s Interest When Landlord Is Party To Tenant Improvement Construction Contract
January 03, 2022 —
David Adelstein - Florida Construction Legal UpdatesIf you are a landlord / lessor, then you want to maximize the protections afforded to you under Florida’s Lien Law in Florida Statute s. 713.10. These protections are designed to protect your property from liens for improvements performed by your tenant / lessee. The intent is that if you comply with s. 713.10, then a tenant improvement contractor’s recourse is against the leasehold interest, and NOT against the interest of the real property (or your interest as the landlord / lessor). Needless to say, it is imperative that a landlord / lessor make efforts to comply with this section when a tenant is performing tenant improvements, even when the landlord is contributing money to those improvements.
Section 713.10 provides in material part:
(1) Except as provided in s. 713.12, a lien under this part shall extend to, and only to, the right, title, and interest of the person who contracts for the improvement as such right, title, and interest exists at the commencement of the improvement or is thereafter acquired in the real property. When an improvement is made by a lessee in accordance with an agreement between such lessee and her or his lessor, the lien shall extend also to the interest of such lessor.
(2)(a) When the lease expressly provides that the interest of the lessor shall not be subject to liens for improvements made by the lessee, the lessee shall notify the contractor making any such improvements of such provision or provisions in the lease, and the knowing or willful failure of the lessee to provide such notice to the contractor shall render the contract between the lessee and the contractor voidable at the option of the contractor.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Unlicensed Contractors Caught in a Sting Operation
March 19, 2015 —
Beverley BevenFlorez-CDJ STAFFSeven suspects were cited for contracting without a license after being caught by the Contractors State License Board (CSLB), reported CBS local news, and eighty-five people may face criminal charges. The undercover sting operations occurred over a two day period in Rancho Mirage, California. A hearing is scheduled for June 3rd at Riverside County Superior Court.
CSLB Registrar Cindi A. Christenson told CBS, “Several of the suspects we targeted turned out to be repeat offenders and individuals with a criminal history and drug violations. If you knew their backgrounds, you'd never allow them near your home or family."
Read the court decisionRead the full story...Reprinted courtesy of
Insured's Jury Verdict Reversed After Improper Trial Tactics
October 09, 2018 —
Tred R. Eyerly - Insurance Law HawaiiThe appellate court reversed a jury verdict for the insured due to improper trial tactics by his attorney. Homeowners Choice Property and Cas. Ins. Co., Inc. v. Kuwas, 2018 Fla. Ct. App. LEXIS 9500 (Fla. Ct. App. July 5, 2018).
The insured sued Homeowners Choice (HCI) alleging breach of contract due to a denial of coverage for property damage as a result of water loss. During the trial, HCI raised objections to various questions posed by the insured's counsel during the testimony of HCI's litigation manager, as well as various closing arguments made by the insured. The jury entered a verdict for the insured for a substantial sum. HCI appealed.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Late Progress Payments on Local Public Works Projects Are Not a Statutory Breach of Contract
May 10, 2022 —
Ted Senet & Christopher Trembley - Gibbs GidenCalifornia local public agencies and their contractors should take note of a recent appellate decision pertaining to late progress payments on public works projects. In Clark Bros., Inc. v. North Edwards Water Dist., 2022 Cal. App. LEXIS 331, filed on April 22, 2022, the Court of Appeal for the Fourth Appellate District held that a local agency’s late progress payments to a general contractor did not constitute breach of contract under the prompt payment penalty statute, Public Contract Code § 20104.50. Notwithstanding this holding, the contractor recovered damages, interest, fees, and costs in excess of its contract amount.
In 2013, the North Edwards Water District awarded a $6.2 million contract to Clark Bros., Inc. to construct a water treatment facility. The District’s water contained excessive levels of arsenic, and the project was sponsored by the State of California with funds earmarked to provide safe drinking water. The State agreed to disburse funds to the District during construction upon the State’s review and approval of the contractor’s progress payment applications. The contract required completion of the work within one year following the District’s issuance of a notice to proceed to the contractor.
As a result of factors arguably outside the control of the contractor, including unforeseen site conditions and the failure of the District’s equipment supplier to meet delivery deadlines, the project was significantly delayed beyond the deadline for completion. The District nonetheless terminated the contractor, which in turn filed suit against the District and the State. The contractor asserted claims for breach of contract, including breach of contract for the District’s failure to pay the contractor’s progress payment applications within the time specified under Public Contract Code § 20104.50. Subsection (b) of the statute provides:
Any local agency which fails to make any progress payment within 30 days after receipt of an undisputed and properly submitted payment request from a contractor on a construction contract shall pay interest to the contractor equivalent to the legal rate set forth in subdivision (a) of Section 685.010 of the Code of Civil Procedure.
Reprinted courtesy of
Ted Senet, Gibbs Giden and
Christopher Trembley, Gibbs Giden
Mr. Senet may be contacted at tsenet@gibbsgiden.com
Mr. Trembley may be contacted at Ctrembley@gibbsgiden.com
Read the court decisionRead the full story...Reprinted courtesy of
Are Construction Contract Limitation of Liability Clauses on the Way Out in Virginia?
March 11, 2024 —
Christopher G. Hill - Construction Law MusingsRemember BAE Systems and Fluor? This post is the third here at Construction Law Musings relating to this case which is a seemingly never-ending source for content. In the prior post discussing this case, the Court found that Va. Code 1-4.1:1 which bars waiver of a right to payment before work is performed did not apply because Fluor had provided work before execution of the contract or any change orders.
In the most recent opinion in this long-running litigation, and after a motion to reconsider by Fluor that was granted, the Court re-examined this finding along with the contractual language found in the Limitation of Damages (LOD) clause and came to the opposite conclusion regarding certain change orders that remained unpaid by BAE.
The Court first looked to the language of the contract itself and specifically the language in the LOD provision that states “Except as otherwise provided in this Subcontract.” The Court then looked at the change order provision and its typical equitable adjustment language and the mandatory nature of the equitable adjustment language. The Court found that the LOD provisions did not apply to change orders both because price increases due to change orders are not “damages” and because of the exception language in the LOD provision itself.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Housing Starts in U.S. Little Changed From Stronger January
March 19, 2014 —
Jeanna Smialek – BloombergHousing starts in the U.S. were little changed in February after declining less than previously estimated a month earlier, indicating the home-building industry is stabilizing after bad winter weather curbed construction.
The 0.2 percent decrease to 907,000 homes at an annualized rate last month followed a revised 909,000 pace in January, figures from the Commerce Department in Washington showed today. The median estimate in a Bloomberg survey called for a 910,000 rate after a previously reported 880,000 in January.
Warmer temperatures, a pickup in demand during the spring selling season and limited housing supply may help fuel further gains in new residential construction. The outlook for the industry later this year depends on whether hiring picks up enough to overcome higher mortgage rates and home prices.
Read the court decisionRead the full story...Reprinted courtesy of
Jeanna Smialek, BloombergMs. Smialek may be contacted at
jsmialek1@bloomberg.net
Homeowners Sue Over Sinkholes, Use Cash for Other Things
January 06, 2012 —
CDJ STAFFQuoting one homeowner as saying that his house “can fall in the ground for all I care, I made my money,” the Tampa Bay Times looks at the issue of sinkhole claims in Florida. Homeowners “have paid off mortgages, put in pools, replaced roofs, or otherwise used money from sinkhole claims to do something besides fix sinkhole damage.
It’s been tough for insurance companies. Citizens Property Insurance took in $32 million in premiums for sinkhole coverage in 2010, but paid out $245 million in sinkhole claims. The Tampa Bay Times notes that some of those claims come from settling problems caused by their repairs, including one settlement of $350,000 for repairs to a house worth $39,000.
One couple, after receiving $217,000 from Citizens, sold the house to a company that bought unrepaired sinkhole homes for $190,000. The home has been sold since and remains unrepaired.
Sometimes the preferred solution by the insurance company isn’t the cheapest either. One couple was informed that Citizens was going to spend $150,000 to have the hole filled with grout. After they settled with the insurance company, they fixed the problem by installing steel piers, at a cost of about $45,000.
Read the full story…
Read the court decisionRead the full story...Reprinted courtesy of
Tall Mass Timber Buildings Now Possible Under 2021 IBC Code Changes
February 03, 2020 —
Kenneth Bland - Construction ExecutiveThe International Code Council (ICC) has approved 17 changes to the 2021 editions of the International Building Code (IBC) and International Fire Code, allowing for mass timber buildings up to 18 stories. With the addition of three new mass timber construction types (Type IV-A, IV-B, and IV-C), this is the first time in the history of the modern building code that significantly new construction types have been added to the code.
Building Materials
The primary building material that makes tall mass timber (TMT) buildings possible is cross-laminated timber (CLT). CLT is manufactured from dimension lumber (nominal 2x lumber) laid side-by-side or mass plywood panels of a specified width. Laminations of lumber are typically laid perpendicular to each other to form panels of various thicknesses that are bonded together using heat resistant adhesives that cure in large hydraulic presses. CLT commonly consists of an odd number of laminations.
These solid wood panels can be anywhere from 6 inches to 20 inches nominal thickness and 60 feet long. Typical CLT panels will be 6 inches to 14 inches nominal thickness. The panels are fabricated off site, transported onto the construction site and assembled in a manner that is efficient and remarkably fast. CLT panels can be used as floor, wall, or roof building elements supported by glued-laminated beams and columns.
Reprinted courtesy of
Kenneth Bland, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of