When is a “Notice of Completion” on a California Private Works Construction Project Valid? Why Does It Matter for My Collection Rights?
January 27, 2020 —
William L. Porter - Porter Law GroupWhat is a Notice of Completion?
A “notice of completion” is a document recorded by the owner of property where construction work was performed. Specifically, it is recorded at the Office of the County Recorder in the County where the work was performed. The notice of completion tells the world at large that the construction project is complete. It also triggers the deadlines for those who have not been paid to make their claims for payment.
Is an Owner of a California Private Works Project Required to Record a Notice of Completion?
No, there is no requirement that an owner of a California private works construction project record a Notice of Completion. However, there are consequences which depend on whether an Owner elects to record the notice or not.
For My Collection Rights, Why Does it Matter Whether a Notice of Completion Has Been Recorded?
The date of recording of a valid notice of completion sets the deadline for those who have not been paid for work performed and materials supplied to a California construction project to pursue such important collection remedies as the “mechanics lien”, the “stop payment notice” and the “payment bond claim.” These are very powerful collection remedies for those who have not been paid. If the deadline to pursue these remedies is missed by a claimant, then the claimant’s right to pursue these remedies is also missed. One of these remedies, the mechanics lien, will enable the claimant to sell the owner’s property where the work was performed in order to get paid.
Read the court decisionRead the full story...Reprinted courtesy of
William L. Porter, Porter Law GroupMr. Porter may be contacted at
bporter@porterlaw.com
So, You Have a Judgment Against a California Contractor or Subcontractor. What Next? How Can I Enforce Payment?
May 04, 2020 —
William L. Porter - Porter Law GroupThe Contractors’ State License Board (“CSLB”) represents the interests of the public in California construction matters. In the field of California construction, the CSLB is all powerful. The agency has the right to suspend the license of any contractor or subcontractor who does not pay on a construction related judgment against it. If you are successful in obtaining a court judgment against a contractor or a subcontractor in a construction-related case, you can utilize the services of the CSLB to suspend the contractors’ license of that contractor or subcontractor until the judgment has been paid. Once the license is suspended, the contractor or subcontractor has no legal right to work as a contractor or subcontractor and can even be arrested for doing so. Details on using the CSLB to suspend the license of a contractor or subcontractor who has a construction-related judgment against it can be accessed at this particular CSLB link:
CSLB – Judgment.
On receipt of notice of the construction-related judgment, the CSLB will either suspend the contractors’ license of any contractor or subcontractor who does not pay on the judgment or who does not appeal the judgment to the Court of Appeals or file bankruptcy within 90 days. There also exists an opportunity for the licensed debtor to file a bond with the CSLB. The bond will either have to be renewed annually or the judgment paid, whichever comes first.
Read the court decisionRead the full story...Reprinted courtesy of
William L. Porter, Porter Law GroupMr. Porter may be contacted at
bporter@porterlaw.com
Courthouse Reporter Series: Two Recent Cases Address Copyright Protection for Architectural Works
January 16, 2024 —
Stu Richeson - The Dispute ResolverRecent decisions by the Seventh Circuit and the Eight Circuit have addressed the scope of protection afforded to architectural works under copyright law. The Seventh Circuit case of Design Basics, LLC v. Signature Constr., Inc., 994 F.3d 879 (7th Cir. 2021), took a somewhat narrow view of the copyright protection afforded to the design of an “affordable, multipurpose, suburban, single-family home.” In Designworks Homes, Inc. v. Columbia House of Brokers Realty, Inc., 9 F.4th 803 (8th Cir. 2021), cert. denied, 142 S. Ct. 2888, 213 L. Ed. 2d 1103 (2022) the Eight Circuit held that the publication of floor plans of a house in a real estate listing was not protected from claims of copyright infringement.
Design Basics, LLC v. Signature Constr., Inc., involved a plaintiff that the court described as holding registered copyrights in thousands of floor plans for suburban, single-family homes that are basic schematic designs, largely conceptual in nature, and depict layouts for one- and two-story single-family homes that include the typical rooms: a kitchen, a dining area, a great room, a few bedrooms, bathrooms, a laundry area, a garage, stairs, assorted closets, etc. The court described the plaintiff as a “copyright troll” and noted that litigation proceeds had become the principal revenue stream for the plaintiff. The plaintiff sued a contractor and related businesses contending hat the defendants had infringed plaintiff’s copyrighted floor plans.
Read the court decisionRead the full story...Reprinted courtesy of
Stu Richeson, PhelpsMr. Richeson may be contacted at
stuart.richeson@phelps.com
Over a Hundred Thousand Superstorm Sandy Cases Re-Opened
March 12, 2015 —
Beverley BevenFlorez-CDJ STAFFThe Federal Emergency Management Agency (FEMA) announced yesterday that they will be reopening 144,000 flood insurance claims, reported the New Jersey Law Journal.
The announcement comes weeks after reports that “some insurance companies denied thousands of claims after fraudulently altering engineering reports, as well as complaints that insurance companies systematically underpay on claims because they fear a backlash from FEMA.”
Read the court decisionRead the full story...Reprinted courtesy of
Traub Lieberman Team Obtains Summary Judgment in Favor of Client Under Florida’s Newly Implemented Summary Judgment Standard
August 23, 2021 —
Heather Fleming & Gregory H. Lercher - Traub LiebermanOn July 27, 2021, the Circuit Court of the Ninth Judicial Circuit in and for Osceola County, Florida granted summary judgment in favor of a client insurer defended by Traub Lieberman Partner Heather M. Fleming and Associate Gregory H. Lercher in connection with a first party property lawsuit arising from Hurricane Irma that involved multiple, comingled claims, in part resolved via prior appraisal.
As of May 1, 2021, Florida state courts have applied a new summary judgment standard after Florida’s longstanding rule was amended by the Supreme Court of Florida. The amendment aligns Florida’s standard with that of the federal courts and the supermajority of states that have already adopted the federal summary judgment standard codified in Rule 56 of Federal Rules of Civil Procedure. The Supreme Court of Florida’s stated goal in adopting the new standard across the Sunshine State was to improve the fairness and efficiency of Florida's civil justice system, to relieve parties from the expense and burdens of meritless litigation, and to save the work of juries for cases where there are real factual disputes that need resolution.
Reprinted courtesy of
Heather Fleming, Traub Lieberman and
Gregory H. Lercher, Traub Lieberman
Ms. Fleming may be contacted at hfleming@tlsslaw.com
Mr. Lercher may be contacted at glercher@tlsslaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Wake County Justice Center- a LEED Silver Project done right!
October 01, 2014 —
Melissa Dewey Brumback – Construction Law in North CarolinaYesterday evening, I had the privilege of attending the Triangle USGBC’s “Talk & Walk” at the Wake County Justice Center. The 576,996 square foot Justice Center was completed 6 months early and over 30 million under budget. (The final cost, including soft costs, came in at ~$141,000,000). Now that’s what I call a LEED project done right!
Interestingly, the County did not endeavor for a LEED Silver rating– the plan was to aim for a Certification. However, as the process unfolded, the Team kept meeting the goals and points for a Silver certification without any appreciable additional costs.
The end result? An “iconic but energy efficient building,” according to Tim Ashby, current Wake County Facilities Project Manager. Tim was initially involved in the Project while working at O’Brien Atkins, which served as the architecture firm for the Project under the direction of Architect Andrew Zwiacher.
Read the court decisionRead the full story...Reprinted courtesy of
Melissa Dewey Brumback, Construction Law in North CarolinaMs. Brumback may be contacted at
mbrumback@rl-law.com
Construction Slow to Begin in Superstorm Sandy Cases
March 12, 2014 —
Beverley BevenFlorez-CDJ STAFFU.S. Senator Robert Mendendez of New Jersey, “has called on government officials to speed up the way home rebuilding aid is reaching thousands of New Jersey victims of Superstorm Sandy,” according to CBS New York. Mendendez stated that out of the 12,000 people who have received “preliminary approval for aid” under New Jersey’s “Reconstruction, Elevation and Mitigation program,” only “2,700 have been told they can begin construction.” The storm occurred more than sixteen months ago.
“Part of the problem,” Mendendez told CBS New York, “has been that state officials have placed federally required environmental and historic preservation reviews at the end of the lengthy aid application process. That delays rebuilding because federal rules allow reconstruction work to begin once those reviews are completed.”
CBS New York reported that the state announced that those “using their own contractors to rebuild homes can request 50 percent of their grant in advance under the change, which went into effect Monday.”
Read the court decisionRead the full story...Reprinted courtesy of
Where Do We Go From Here?
March 21, 2022 —
Christopher G. Hill - Construction Law MusingsGreen Builder CoalitionFor this week’s Guest Post Friday, I welcome an old friend and past Guest Post Friday contributor, Mike Collignon. Mike is the Co-Founder and Executive Director of the Green Builder® Coalition. He engages in national and state-level advocacy and publishes regular content for Green Builder® Media. Mike is also the Chair of the WERS Development Group and has served as the moderator or host for Green Builder® Media’s Impact Series webinars from 2012– present.
This post originally appeared on Green Builder® Media’s Code Watcher.
Do you ever have a line from a song just pop into your head? I get that… a lot. It’s probably due to my lifelong love of music. Anyway, while I was researching this column, the line that cites the title of “Where Do We Go From Here?” by Filter started playing between my ears. You’ll see why in a couple of minutes.
In case you didn’t
read about it here or elsewhere, the IECC development process has undergone an overhaul. It is now following a standards process, yet it retains the word “code” in the name. The residential committee (which is the scope of this column) is now a consensus committee and has been greatly expanded. Proposals are still submitted, reviewed and voted on by the committee. On the surface, it doesn’t sound like much has changed. As they say, the devil is always in the details.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com