$24 Million Verdict Against Material Supplier Overturned Where Plaintiff Failed to Prove Supplier’s Negligence or Breach of Contract Caused an SB800 Violation
March 16, 2017 —
Jon A. Turigliatto, Esq. & Chelsea L. Zwart, Esq. – Chapman Glucksman Dean Roeb & Barger BulletinAcqua Vista Homeowners Assoc. v. MWL Inc. (2017) 2017 WL 371379
COURT OF APPEAL EXTENDS GREYSTONE HOMES, INC. v. MIDTEC, INC., HOLDING THAT CIVIL CODE §936 CREATES A NEGLIGENCE STANDARD FOR CLAIMS AGAINST MATERIAL SUPPLIERS BROUGHT UNDER SB800.
The Fourth District California Court of Appeal recently published its decision Acqua Vista Homeowners Assoc. v. MWI, Inc. (2017) 2017 WL 371379, holding that claims against a material supplier under SB800 (Civil Code §895 and §936) require proof that the SB800 violation was caused by the supplier's negligence or breach of contract.
Civil Code §936 states in relevant part, that it applies "to general contractors, subcontractors, material suppliers, individual product manufacturers, and design professionals to the extent that the general contractors, subcontractors, material suppliers, individual product manufacturers, and design professionals caused, in whole or in part, a violation of a particular standard as the result of a negligent act or omission or a breach of contract .... [T]he negligence standard in this section does not apply to any general contractor, subcontractor, material supplier, individual product manufacturer, or design professional with respect to claims for which strict liability would apply."
Acqua Vista Homeowners Association (the "HOA") sued MWI, a supplier of Chinese pipe used in the construction of the Acqua Vista condominium development. The HOA's complaint asserted a single cause of action for violation of SB800 standards, and alleged that defective cast iron pipe was used throughout the building. After trial, the trial court entered a judgment against MWI in the amount of $23,955,796.28, reflecting the jury's finding that MWI was 92% responsible for the HOA's damages.
MWI filed a motion for a directed verdict and motion for judgment notwithstanding the verdict on the grounds that the HOA had failed to present any evidence that MWI had caused an SB800 violation as a result of its negligence or breach of contract, and had therefore failed to prove negligence and causation as required by SB800, citing to Greystone Homes, Inc. v. Midtec, Inc.(2008) 168 Cal.App.4th 1194. The trial court denied both motions, relying on the last sentence of Civil Code §936, which states in part, "[T]he negligence standard in this section does not apply to any ... material supplier ... with respect to claims for which strict liability would apply."
The Court of Appeal reversed and ordered the trial court to enter judgment in favor of MWI. The Court of Appeal relied on the legislative history of S8800 and Greystone, which held that the first sentence of Civil Code §936 contains an "explicit adoption of a negligence standard" for S8800 claims against product manufacturers. The Court of Appeal reasoned that since §936 treats product manufacturers and material suppliers identically, the holding of Greystone must equally apply to material suppliers.
Because the complaint did not state a common law cause of action for strict liability, the HOA was required to prove that the damages were caused by MWI' s negligence or breach of contract. Although, the Court of Appeal found that while the HOA's evidence may have supported a finding that the manufacturer of the leaking pipes was negligent, the HOA had not provided any evidence that MWI, the supplier, had failed to supply the type of pipe ordered, acted unreasonably in failing to detect any manufacturing defects present in the pipe, or damaged it during transportation. Accordingly, the HOA could not prove that the alleged S8800 violation was caused, in whole or in part, by MWI' s negligence, omission, or breach of contract.
In light of the decision, homeowner and associations that allege only violations of SB800 standards without asserting a common law cause of action for strict liability cannot prevail by simply producing evidence of a violation, and are required to prove that violation was caused by the negligent act or omission, or breach of contract, of the defendant contractor, material supplier, and/or product manufacturer.
Reprinted courtesy of
Jon A. Turigliatto, Esq, Chapman Glucksman Dean Roeb & Barger and
Chelsea L. Zwart, Esq., Chapman Glucksman Dean Roeb & Barger
Mr. Turigliatto may be contacted at jturigliatto@cgdrblaw.com
Ms. Zwart may be contacted at czwart@cgdrblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
While Construction Permits Slowly Rise, Construction Starts and Completions in California Are Stagnant
December 05, 2022 —
John Kazanovicz & Jason Feld - Kahana FeldThere is an interesting phenomenon happening in the California construction market since the Summer of 2022. There is a steady but slow rise in the construction building permits being issued throughout California. According to the U.S. Census and the U.S. Department of Housing and Urban Development’s joint announcement (https://www.census.gov/construction/nrc/pdf/newresconst.pdf) of new residential construction statistics for September 2022, privately‐owned housing units authorized by building permits in September were at a seasonally adjusted annual rate of 1,564,000. This is 1.4 percent above the revised August rate of 1,542,000. While this is slightly lower than a year ago (3.2 percent below the September 2021 rate of 1,615,000), the trend for obtaining new home permits was reportedly ahead of the projected rates given the market conditions and inflation throughout the country. Interestingly, single‐family authorizations in September were at a rate of 872,000 which was also 3.1 percent below the revised August 2022 figure of 900,000. Authorizations of units in buildings with five units or more were at a rate of 644,000 in September. Overall, while slowly recovering from the record lows during the height of the pandemic, the economic forecast for new home construction in California is positive, but cautious.
The flip side of this coin is the construction starts in California, which continue to remain stagnant despite additional building permits being issued. Privately‐owned housing starts in September were at a seasonally adjusted annual rate of 1,439,000. This is 8.1 percent (±14.9 percent) below the revised August estimate of 1,566,000 and is 7.7 percent (±11.5 percent) below the September 2021 rate of 1,559,000. Single‐family housing starts in September were at a rate of 892,000; this is 4.7 percent (±10.7 percent) below the revised August figure of 936,000. The September rate for units in buildings with five units or more was 530,000.
Reprinted courtesy of
John Kazanovicz, Kahana Feld and
Jason Feld, Kahana Feld
Mr. Kazanovicz may be contacted at jkazanovicz@kahanafeld.com
Mr. Feld may be contacted at jfeld@kahanafeld.com
Read the court decisionRead the full story...Reprinted courtesy of
Bidders Shortlisted as Oroville Dam Work Schedule is Set
April 13, 2017 —
JT Long - Engineering News-RecordIn a race to fix the damaged Oroville Dam’s main spillway by November, the California Dept. of Water Resources, the operator of the country’s tallest dam, is going to bid with a 65%-complete design that breaks recovery efforts into three parts, with an ultimate goal of doubling the main spillway’s release capacity to 270,000 cu ft per second.
Read the court decisionRead the full story...Reprinted courtesy of
JT Long, ENRENR may be contacted at
ENR.com@bnpmedia.com
A New Perspective on Mapping Construction Sites with the Crane Camera System
November 10, 2016 —
Aarni Heiskanen – AEC BusinessIn this interview, Julian Norton, Business Development Manager of Pix4D, talks about the company’s innovative mapping system for construction sites. Pix4D has just launched an early adopter program and is looking for test users.
Can you say a few words about your company’s background and mission?
Pix4D was founded in 2011 as a spinoff of EPFL, a leading Swiss tech university. The years of leading scientific research in photogrammetry and computer vision done by our founders was applied to drones long before drone mapping became a “thing.” Fast forward through more years of hard work to now, and you’ll see Pix4D specialized in professional drone mapping software to produce orthomosaics, 3D models, digital surface models, point clouds and more, all from images.
Our solutions are purposed towards four main industries: surveying, agriculture, real estate and construction. We want our professional clients to benefit from our unique hybrid approach, which combines mobile data capture with cloud and desktop hardware, to conduct mapping in a way that fits them best.
Read the court decisionRead the full story...Reprinted courtesy of
Aarni Heiskanen, AEC BusinessMr. Heiskanen may be contacted at
aarni@aepartners.fi
Do Construction Contracts and Fraud Mix After All?
October 27, 2016 —
Christopher G. Hill – Construction Law MusingsOn several occasions here at Construction Law Musings, I’ve discussed the fact that, with a few exceptions, fraud claims and written construction contract based claims do not mix. One of the exceptions to the so called “economic loss rule” that would seem to preclude both fraud and contract claims in the same lawsuit is where fraud is used to induce the contract in the first place. This exception would only apply where an independent duty, wholly outside of the duties created by the contract, is properly plead and proven to the court. For the same reason, namely a separate duty outside of the contract, the Virginia Consumer Protection Act (“VCPA”) may allow for an exception that would allow a cause of action under this statute.
Up until recently, the courts of Virginia have used these exceptions sparingly. However, the recent Loudoun County, VA Circuit Court opinion in Interbuild, Inc. v. Sayers (opinion also found at Virginia Lawyers Weekly) may signal a broadening of these exceptions. In the Interbuild case, the Court considered a claim for fraud in the inducement and breach of the VCPA. The basic facts plead by the plaintiffs were that Interbuild induced them into the contract through statements that it had been an established business since 1981, the project did not require a building permit, it had obtained all necessary subcontractor prices and would provide full-time project supervision, the project would be completed within 16 weeks, 4000 PSI concrete would be used for the project and that the project would be located in the agreed-upon area depicted and that they reasonably relied on these representations in deciding to enter into the contract to build their recreational facility.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, The Law Office of Christopher G. Hill, PCMr. Hill may be contacted at
chrisghill@constructionlawva.com
Arizona Supreme Court Clarifies Area Variance Standard; Property Owners May Obtain an Area Variance When Special Circumstances Existed at Purchase
October 19, 2017 —
Nick Wood, Adam Lang, Noel Griemsmann, & Brianna Long – Snell & Wilmer Real Estate Litigation BlogIn Pawn 1st v. City of Phoenix, the Arizona Supreme Court rejected a Court of Appeals rule that would have unduly restrained alienation of property in Arizona. The Court of Appeals found that the City of Phoenix Board of Adjustment acted beyond its authority when it granted an area variance to a pawn shop where the special circumstances causing a need for the variance existed before the pawn shop purchased the property. Under Arizona law, boards of adjustment cannot grant an area variance where the special circumstances requiring the variance are self-imposed. The Court of Appeals adopted a rule that knowledge of special circumstances at the time of purchase made the special circumstances self-imposed, foreclosing the purchaser’s ability to obtain a variance. This rule would have severely restricted property purchasers’ ability to obtain area variances in Arizona and by extension likely strained property transactions.
The underlying case involved a pawn shop that was proposed in southeast Phoenix. After the property purchaser obtained approval for a required use permit (for a pawn shop) and a variance (for a 500 foot residential setback) from the City of Phoenix Board of Adjustment, a competing pawn shop filed a special action arguing that the variance was a use variance, not an area variance, beyond the board of adjustment’s authority.
Reprinted courtesy of Snell & Wilmer attorneys
Nick Wood,
Adam Lang,
Noel Griemsmann and
Brianna Long
Mr. Wood may be contacted at nwood@swlaw.com
Mr. Lang may be contacted at alang@swlaw.com
Mr. Noel may be contacted at ngriemsmann@swlaw.com
Ms. Brianna may be contacted at bllong@swlaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Contractors Set to Implement Air Quality Upgrades for Healthier Buildings
April 12, 2021 —
Nate Echtenkamp - Construction ExecutiveAs people spend more time in offices, stores and other buildings, and colder weather forces many outdoor activities to be held indoors during the COVID-19 pandemic, construction contractors are increasingly being asked by building owners and operators to provide various mitigation strategies to improve indoor air quality to help occupants avoid being exposed to lingering airborne viral particles.
Lowering the concentration of SARS-CoV-2 and other pathogens in enclosed public spaces is of the utmost importance nowadays given that Americans, on average, spend nearly 90% of their time indoors, according to the EPA.
It’s fairly common knowledge that the best way to avoid infection is to follow guidelines issued by the Centers for Disease Control and Prevention that include:
- wearing masks or other face coverings;
- frequent hand-washing;
- physical distancing of at least six feet; and
- deep-cleaning procedures.
Reprinted courtesy of
Nate Echtenkamp, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Mississippi Floods Prompt New Look at Controversial Dam Project
March 16, 2020 —
Autumn Cafiero Giusti - Engineering News-RecordFlooding from the Pearl River in Mississippi has created a renewed sense of urgency for regional flood prevention efforts, with officials set to decide in six months whether to approve a controversial flood control plan, says an attorney for the region’s flood control district.
Autumn Cafiero Giusti, Engineering News-Record
ENR may be contacted at ENR.com@bnpmedia.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of