Indiana Court Enforces Contract Provisions rather than Construction Drawing Markings
January 14, 2015 —
Beverley BevenFlorez-CDJ STAFFTimothy J. Abeska, a vice-chair of Barnes & Thornburg LLP’s Construction Law Practice Group, analyzed Goodrich Quality Theaters, Inc. v. Fostcorp Heating and Cooling, Inc., 16 N.E.3d 426 (Ind. Ct. App. 2014), which “provides an example of a court enforcing contract provisions rather than markings on construction drawings that are inconsistent with contract requirements.”
The case evolved from a dispute on a construction of an IMAX theater, when the general contractor did not understand the architect’s markings for non-standard joist girders, and ordered standard joist girders, per the contract. The error created delays and other problems, which led to payment disputes and mechanic’s liens against the project.
Abeska stated that “[t]his case shows the importance of making sure all documents which comprise a construction contract are consistent with each other, as courts will enforce contracts negotiated by the parties. The case also demonstrates that litigation is not a quick process, as the Court of Appeals Opinion was issued more than seven years after the project was completed.”
Read the court decisionRead the full story...Reprinted courtesy of
Kadeejah Kelly Named to The National Black Lawyers’ “Top 40 Under 40” List
October 17, 2022 —
Lewis BrisboisNew York, N.Y. (October 6, 2022) – New York Associate
Kadeejah J. Kelly was recently named to The National Black Lawyers (NBL) “Top 40 Under 40” list.
The NBL “Top 40 Under 40” recognizes the most talented black attorneys under the age of 40 who have an outstanding reputation among peers, the judiciary and the public. The honorees on this list are nominated from leading lawyers, current members, and Executive Committee members.
Ms. Kelly is a member of the General Liability and Professional Liability Practices. She has extensive experience defending owners, contractors, developers and corporations in high exposure construction cases including New York Labor Law matters, premises liability and construction defect claims. She also has experience defending malpractice claims against attorneys, accountants, architects, engineers, funeral home directors and other miscellaneous professionals.
Read the court decisionRead the full story...Reprinted courtesy of
Lewis Brisbois
Georgia Supreme Court Determines Damage to "Other Property" Not Necessary for Finding Occurrence
July 31, 2013 —
Tred Eyerly, Insurance Law HawaiiThe Georgia Supreme Court has determined that an "occurrence" may arise under a CGL policy even if "other property" is not damaged. Taylor Morrison Servs. v. HDI-Gerling Am. Ins. Co., 2013 Ga. LEXIS 618 (Ga. July 12, 2013).
Taylor Morrison, the insured, was a homebuilder. It was sued in a class action by more than 400 homeowners in California alleging that the concrete foundations of their homes were improperly constructed. This led to water intrusion, cracks in the floors and driveways, and warped and buckled flooring.
At first, HDI-Gerling defended under a reservation of rights. Subsequently, however, HDI-Gerling sued Taylor Morrison in federal district court in Georgia, seeking a declaratory judgment that there was no coverage. The district court granted summary judgment to HDI-Gerling after determining that there was no "occurrence" when the only "property damage" alleged was damage to work of the insured. Georgia law was applied to the dispute.
Read the court decisionRead the full story...Reprinted courtesy of
Tred EyerlyTred Eyerly can be contacted at
te@hawaiilawyer.com
Drop in Civil Trials May Cause Problems for Construction Defect Cases
August 27, 2013 —
CDJ STAFFOver the last fifty years, the number of lawsuits that have been settled by trial have dropped sharply, according to Kenneth Childs, writing in the Idaho Business Review. Childs notes that in 1962, 11.5% of federal civil cases were resolved at trial, but in 2002, only 1.8 % percent went to trial. He makes the supposition that, due to their complexity, construction defect trials are even less likely to be resolved at trial.
Instead, they are being resolved in mandatory arbitration. Views on arbitration have changed over the years and the courts have gone from what he describes as “somewhat hostile to it” to embracing, encouraging, and even mandating it.
Childs notes there are some problems to this climate of arbitration. He notes that arbitrators can “operate by their own rules and according to their own standards.” The decisions made by arbitrators “are not subject to appellate review,” which allows arbitrators “to ignore the law entirely.”
Read the court decisionRead the full story...Reprinted courtesy of
Port Authority Approves Subsidies for 2 World Trade Project
December 10, 2015 —
David M. Levitt – BloombergThe Port Authority of New York and New Jersey approved subsidies to help expedite the construction of lower Manhattan’s 2 World Trade Center, where Rupert Murdoch’s 21st Century Fox Inc. and News Corp. companies have a tentative deal to move their headquarters from midtown.
Developer Silverstein Properties Inc., which leases the sites for 2 World Trade Center and two other towers from the Port Authority, would receive a rent break that amounts to $9 million over the life of the lease, Authority Director Patrick Foye said, just before the agency board unanimously approved the proposal.
Read the court decisionRead the full story...Reprinted courtesy of
David M. Levitt, Bloomberg
Loss Caused by Subcontractor's Faulty Work Covered in Georgia
January 17, 2013 —
Tred Eyerly, Insurance Law HawaiiThe Georgia Court of Appeals found a subcontractor was covered under a CGL policy for loss caused by alleged faulty workmanship. Maxum Indem. Co. v. Jimenez, 2012 Ga. App. LEXIS 970 (Ga. Ct. App. Nov. 20, 2012).
Jimenez was hired as a subcontractor to install pipes for a dormitory construction project at Georgia Southern University. Subsequent to the construction, a pipe burst occurred at the dormitory, causing damage to several units. After a jury trial, Jimenez was found liable for $191,382 in damages that arose from his negligent pipe work.
Jimenez was insured under a CGL policy issued by Maxum. Maxum filed a suit for a declaratory judgment, seeking a declaration that the claim against Jimenez was not covered.
Read the court decisionRead the full story...Reprinted courtesy of
Tred EyerlyTred Eyerly can be contacted at
te@hawaiilawyer.com
Perez Broke Records … But Should He Have Settled Earlier?
February 19, 2024 —
Sofya Uvaydov & John F. Watkins - Kahana FeldIn 2021, Mark Perez’ Labor Law 240(1) lawsuit made legal news by breaking the record of the highest appellate-sustained pain and suffering award in New York history. While that record was short-lived, it still maintains its place as New York’s highest-ever pain and suffering award for a brain injury. This January 17th, the Appellate Division, First Department revisited the litigation but, this time, in a dispute between Perez and his then-lawyer, Ben Morelli and the Morelli Law Firm. Mr. Perez claims breach of contract over a 10% additional contingency fee charge related to the Perez v. Live Nation appeal and breach of fiduciary duty by his counsel in failing to convey settlement offers during the lifetime of the case. The Morelli firm counters, among other things, that the prior settlement offers – a $30 million offer during the 2019 trial and intermediate sums during the appellate stage – were still lower than the ultimate $55 million settlement. No harm, Mr. Morelli argues, and thus no foul in failing to convey the offers.
But is that so? Did Mark Perez ultimately receive more money in his $55 million settlement than from the $30 million settlement offer mid-trial? Despite the glaring $25 million difference, the surprising calculations show that Perez would have been financially better off taking the $30 million mid-trial settlement.
Reprinted courtesy of
Sofya Uvaydov, Kahana Feld and
John F. Watkins, Kahana Feld
Ms. Uvaydov may be contacted at suvaydov@kahanafeld.com
Mr. Watkins may be contacted at jwatkins@kahanafeld.com
Read the court decisionRead the full story...Reprinted courtesy of
Let’s Talk About a Statutory First-Party Bad Faith Claim Against an Insurer
February 19, 2024 —
David Adelstein - Florida Construction Legal UpdatesLet’s talk about a statutory first-party bad faith claim against an insurer under Florida law. A recent opinion, discussed below, does a nice job providing a synopsis of a first-party statutory bad faith claim against an insurer:
The Florida Legislature created the first-party bad faith cause of action by enacting section 624.155, Florida Statutes, which imposes a duty on insurers to settle their policyholders’ claims in good faith. The statutory obligation on the insurer is to timely evaluate and pay benefits owed under the insurance policy. The damages recoverable by the insured in a bad faith action are those amounts that are the reasonably foreseeable consequences of the insurer’s bad faith in resolving a claim, which include consequential damages.
“[A] statutory bad faith claim under section 624.155 is ripe for litigation when there has been (1) a determination of the insurer’s liability for coverage; (2) a determination of the extent of the insured’s damages; and (3) the required [civil remedy] notice is filed pursuant to section 624.155(3)(a).”
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com