What If There Is a Design Error?
October 30, 2023 —
Scott L. Baker - Los Angeles Litigation BlogMany challenges can crop up when working on a construction project. Among these challenges, errors are the last thing that contractors or project owners want to face. Yet, they are not uncommon as you navigate the process.
Design errors or mistakes are one such issue that can result in serious construction disputes and delays. It is important to determine who is liable when it comes to defects and design errors.
So, who is responsible for design errors?
Many might assume the architect – or the person who created the project design – is responsible for design errors. That is not necessarily true.
Read the court decisionRead the full story...Reprinted courtesy of
Scott L. Baker, Baker & AssociatesMr. Baker may be contacted at
slb@bakerslaw.com
Fixing the Problem – Not the Blame
November 30, 2016 —
Curtis W. Martin – Peckar & Abramson, P.C. BulletinWho is responsible for defective design under Texas law? The contractor, under Lonergan? The
owner, under Spearin? A recent Fifth Circuit decision suggests that in some cases this might be the
wrong question when design responsibility is disputed. The appellate court recently remanded a
case back to the district court to determine whether the contractor or owner breached an implied
duty to cooperate in discovering defects in design and subsequently pricing the change required
to correct the problem.
Read the court decisionRead the full story...Reprinted courtesy of
Curtis W. Martin, Peckar & Abramson, P.C.Mr. Martin may be contacted at
cmartin@pecklaw.com
Sixth Circuit Finds No Coverage for Faulty Workmanship Under Kentucky Law
December 30, 2013 —
Tred Eyerly — Insurance Law HawaiiFollowing Kentucky law, the Sixth Circuit determined there was no coverage for a construction defect claim. Liberty Mut. Fire Ins. Co. v. Kay & Kay Contracting, LLC, 2013 U.S. App. LEXIS 23587 (6th Cir. Nov. 19, 2013).
Walmart hired a contractor to build a new store. The contractor hired Kay and Kay to perform site preparation work and construct the building pad for the new store.
After Kay and Kay completed the building pad and the store was erected, cracks were noticed in the building's walls. Walmart contended there was settling in the some of the fill areas. Kay and Kay denied liability, but demanded coverage under its CGL policy with Liberty Mutual.
Read the court decisionRead the full story...Reprinted courtesy of
Tred EyerlyTred Eyerly can be contacted at
te@hawaiilawyer.com
The Utility of Arbitration Agreements in the Construction Industry
December 30, 2019 —
Brian L. Gardner & Jason R. Finkelstein - Construction ExecutiveIn today’s ever-evolving world of employment law, it is far from an easy task for construction industry employers to operate their business while successfully navigating all of the potential legal potholes that continue to abound and multiply seemingly with every passing day. This is particularly true in the face of the onslaught of claims lodged by current and former employees in recent years for alleged unpaid wages. While there may not be a “sure bet” way of avoiding such claims, one tool that employers should strongly consider in their arsenal are arbitration and class action waiver agreements.
To that end, last year, the United States Supreme Court rendered its ground-breaking decision in Epic Systems Corp. v. Lewis, 584 U.S. ___ (2018). In Epic Systems, the Supreme Court held that arbitration agreements containing class and collective action waivers of wage and hour disputes are enforceable. At the time of the decision, a split of authority existed among courts across the country as to whether such agreements were viable. On the one hand, several courts contended that class waivers unfairly violated employees’ rights to collectively bargain under the National Labor Relations Act. On the other hand, many other courts were finding that such agreements were fully enforceable and supported by the policies promoted under the Federal Arbitration Act. The Epic Systems Court sided with this latter viewpoint, concluding that the FAA’s clear policy promoting arbitration as a dispute resolution mechanism and private parties’ rights to freely negotiate contracts outweighed any potential arguments against such agreements under the NLRA.
With wage and hour lawsuits being filed against construction industry employers practically daily, the Epic Systems decision is critically important. Construction employers can now freely enter into arbitration and class waiver agreements with their laborers and thereby potentially limit the cost, expense and exposure of fighting such actions in a public forum on a collective or class-wide basis. To be clear, such agreements will not eliminate employees from bringing such wage and hour claims entirely, nor should the use of those agreements signal to employers that they need not make every good-faith effort to comply with their obligations under the Federal Labor Standards Act and/or any applicable state wage and hour laws. But the reality is that arbitration and class waiver agreements can work to avoid tens or hundreds or even thousands of employees from banding together in some of the massive wage and hour lawsuits being filed across the country. Instead, employers can require that those legal battles be conducted by a single plaintiff in a more controlled environment before an arbitrator (or panel of arbitrators).
Reprinted courtesy of
Brian L. Gardner & Jason R. Finkelstein, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Mr. Gardner may be contacted at bgardner@coleschotz.com
Mr. Finkelstein may be contacted at jfinkelstein@coleschotz.com
Read the court decisionRead the full story...Reprinted courtesy of
CAUTION: Terms of CCP Section 998 Offers to Compromise Must Be Fully Contained in the Offer Itself
May 12, 2016 —
Jesse M. Sullivan & R. Bryan Martin – Haight Brown & Bonesteel LLPIn Sanford v. Rasnick, (Ct. of Appeal, 1st App. Dist., No. A145704) the First Appellate District addressed whether a CCP § 998 Offer to Compromise requiring plaintiff to execute a release and enter into a separate settlement agreement was valid. Because the settlement agreement could potentially contain additional terms not stated in the CCP 998 Offer, the Court of Appeal held that it was not.
Plaintiff alleged he was injured when the 17-year-old Defendant ran a stop sign and struck his motorcycle. Plaintiff sued the 17-year-old and his father (the owner of the vehicle) for vehicular negligence and general negligence.
Just after discovery closed, defendants jointly served a CCP § 998 Offer to Compromise to plaintiff in the amount of $130,000. The offer contained a condition requiring that in order to accept, plaintiff must provide a “notarized execution and transmittal of a written settlement agreement and general release. Each party will bear its own fees, costs and expenses.”
Mr. Sullivan may be contacted at jsullivan@hbblaw.com
Mr. Martin may be contacted at bmartin@hbblaw.com
Reprinted courtesy of
Jesse M. Sullivan, Haight Brown & Bonesteel LLP and
R. Bryan Martin, Haight Brown & Bonesteel LLP
Read the court decisionRead the full story...Reprinted courtesy of
Late Filing Contractor Barred from Involving Subcontractors in Construction Defect Claim
March 01, 2012 —
CDJ STAFFThe Colorado Court of Appeals looked at that state’s Construction Defect Action Reform Act in determining if a general contractor could add subcontractors as third-party defendants to a construction defect lawsuit. Shaw Construction, LLC was the general contraction of the Roslyn Court condominium complex, and was sued by the homeowners’ association in a construction defect case. United Builder Services was the drywall subcontractor on the project. MB Roofing had installed roofs, gutters, and downspouts. The certificate of occupancy for the last building was issued on March 10, 2004. The project architect certified completion of all known remaining architectural items in June, 2004.
The HOA filed a claim against the developers of the property on January, 21, 2009. A week later, the HOA amended its complaint to add Shaw, the general contractor. Shaw did not file its answer and third-party complaint until March 29, 2010, sending its notice of claim under the CDARA on March 30.
The subcontractors claimed that the six-year statute of limitations had ended twenty days prior. Shaw claimed that the statute of limitations ran until six years after the architect’s certification, or that the HOA’s suit had tolled all claims.
The trial court granted summary judgment to the subcontractors, determining that “substantial completion occurs ‘when an improvement to real property achieves a degree of completion at which the owner can conveniently utilize the improvement of the purpose it was intended.’”
The appeals court noted that “Shaw correctly points out that the CDARA does not define ‘substantial completion.’” The court argued that Shaw’s interpretation went against the history and intent of the measure. “Historically, a construction professional who received a complaint responded by ‘cross-nam[ing] or add[ing] everybody and anybody who had a part to play in the construction chain.’” The court concluded that the intent of the act was to prevent unnamed subcontractors from being tolled.
The court further rejected Shaw’s reliance on the date of the architect’s certification as the time of “substantial completion,” instead agreeing with the trial court that “the architect’s letter on which Shaw relies certified total completion.”
The appeals court upheld the trial court’s determination that the statute of limitation began to run no later than March 10, 2004 and that Shaw’s complaint of March 29, 2010 was therefore barred. The summary judgment was upheld.
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
Insured's Lack of Knowledge of Tenant's Growing Marijuana Means Coverage Afforded for Fire Loss
August 17, 2020 —
Tred R. Eyerly - Insurance Law HawaiiThe California Court of Appeals reversed the trial court's grant of summary judgment to the insurer regarding a claim for fire loss. Mosley v. Pacific Sec. Ins, Co., 2020 Cal. App LEXIS (Cal. Ct. App, May 26, 2020).
The Mosleys rented their property to Pedro Lopez. Six months later, the property was damaged by fire. Lopez had tapped a main power line into the attic to power his energy-intensive marijuana growing operation. The illegal power line caused the fire.
Pacific Specialty Insurance Company (PSIC) insured the property under an HO-3 Standard Homeowners policy. Paragraph E of the policy provided,
We do not insure for loss resulting from any manufacturing, product or operation, engaged in:
- The growing of plants; or
- The manufacture, production, operation or processing of chemical, biological, animal or plant materials.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
When Can Customers Sue for Delays?
September 18, 2023 —
Scott L. Baker - Los Angeles Litigation BlogConstruction projects are subject to many internal and external factors. Due to this, delays are not an uncommon occurrence. Whether delays are the result of bad weather conditions or supply chain issues, contractors and their clients cannot control every aspect of the project.
Delay issues are very
common construction disputes. Therefore, new and experienced contractors alike need to know when their clients may have a reason for a delay claim.
2 particular types of delays that pose a risk
Common obstacles that contractors faced during the height of the COVID-19 global pandemic involved supply chain issues. The lack of materials put various projects on hold across California and the country. This widespread issue was out of contractors’ and clients’ control, meaning they were excusable delays.
Read the court decisionRead the full story...Reprinted courtesy of
Scott L. Baker, Baker & AssociatesMr. Baker may be contacted at
slb@bakerslaw.com