Texas Jury Awards $5.3 Million to Company Defamed by Union: Could it work in Pennsylvania?
December 21, 2016 —
Wally Zimolong – Supplemental ConditionsIn early September a Texas jury awarded a janitorial $5.3 million against the local chapter of the SEIU. The janitorial firm claimed that the SEIU damaged its reputation and caused it damages when it spread false, defamatory, and disparaging stories about the firm. Specifically, the janitorial firm claimed that the SEIU told the janitorial firms customer and potential customers that the firm “systematically failed to pay its employees for all hours worked, instructed janitors to work off the clock and had fired, threatened or refused to hire janitors who supported joining a union.” According to Law360.com, the union did this with “fliers, handbills, letters, emails, newsletters, speeches and postings on its website accused [the firm] of violating wage-and-hour and other labor laws.”
Read the court decisionRead the full story...Reprinted courtesy of
Wally Zimolong, Zimolong LLCMr. Zimolong may be contacted at
wally@zimolonglaw.com
Court Dismisses Coverage Action In Lieu of Pending State Case
July 25, 2021 —
Tred R. Eyerly - Insurance Law HawaiiThe insurer's coverage action was dismissed by the federal court in favor of the pending case in state court. Southern-Owners Ins. Co. v Marquez, 2021 U.S. Dist. LEXIS 108125 (S.D. Fla. May 4, 2021).
The underlying lawsuit was filed because of of an incident involving a golf cart on a sidewalk owned by the AOAO. The Marquezes owned the golf cart that injured the Murphy's child.
Southern-Owners issued a CGL policy to the AOAO. The Marquezes submitted a claim to Souther-Owners for coverage in the underlying lawsuit as additional insureds under the policy. Southern-Owners defended the AOAO and the Marquezes in the underlying lawsuit pursuant to a reservation of rights. The underlying complaint alleged that the Marquezes negligently permitted their daughter to operate the golf cart on the AOAO's pedestrian walkway. Further, the AOAO negligently failed to reasonably maintain the premises.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
South Carolina Legislature Defines "Occurrence" To Include Property Damage Arising From Faulty Workmanship
May 26, 2011 —
Tred R. Eyerly - Insurance Law Hawaii On May 17, 2011, South Carolina passed legislation to combat the restrictive interpretation of what constitutes an "occurrence" under CGL policies. S.C. Code Ann. sec. 38-61-70.
The legislation reversed a decision by the state's Supreme Court issued earlier this year. See Crossman Communities of North Carolina, Inc. v. Harleysville Mut. Ins. Co., 2011 W.L. 93716 (S.C. Jan. 7, 2011). Crossman had overruled an earlier decision by the South Carolina Supreme Court that holding that defective construction was an “occurrence.” Crossman, however, reversed course, holding that damages resulting from faulty workmanship were the “natural and probable cause” of the faulty work and, as such, did not qualify as an “occurrence.”
Read the full story…
Reprinted courtesy of Tred R. Eyerly, Insurance Law Hawaii. Mr. Eyerly can be contacted at te@hawaiilawyer.com
Read the court decisionRead the full story...Reprinted courtesy of
Insurer Wrongfully Denies Coverage When Household Member Fails to Submit to EUO
May 06, 2024 —
Tred R. Eyerly - Insurance Law HawaiiThe court determined that coverage for a loss by fire could not be denied when the insured's son failed to appear for a examination under oath (EUO). Adekola v. Allstate Vehicle & Prop. Ins. Co., 2024 U.S. Dist. LEXIS 27125 (E.D. Pa. Feb. 16, 2024).
Plaintiff had a homeowners policy with Allstate. Plaintiff - Michele Adekola - was the named insured under the policy. After the fire, Allstate provided payments for temporary housing. Allstate requested examinations under oath of Plaintiff and her son, Nico. Plaintiff and her son were examined by Zoom. Allstate then sought to examine Plaintiff's other son, Lemmeco, but these efforts were unsuccessful.
Allstate then stopped paying for Plaintiff's temporary housing and informed Plaintiff that Lemmeco's failure to participate in an EUO was a material breach of duties under the policy and the breach was prejudicial to Allstate. Allstate further contended that Lemmeco had a duty to submit to an EUO.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Termination for Convenience Clauses: Maybe More Than Just Convenience
June 06, 2022 —
Robert C. Shaia - ConsensusDocsA contractor begins work on a project and everything is going well, until one day the owner informs the contractor that it is being terminated for convenience. Possibly, there is no discussion about alleged defects, reasons for the termination, or any damages the owner might seek against the contractor. In that moment, the contractor may be unaware of any perceived wrongdoing or problems with its work.
The industry has typically accepted that, in this scenario, the owner implicitly waives the right to any remedies against the contractor, except those expressly set forth in the contract. Reasonable minds might assume that, if the owner believed it needed to seek further remedies, it would terminate the contractor for cause instead of convenience. And often overlooked during contract negotiations are the benefits of including an express “waiver of remedies” in the termination for convenience section.
Read the court decisionRead the full story...Reprinted courtesy of
Robert C. Shaia, Watt, Tieder, Hoffar, & Fitzgerald, LLP (ConsensusDocs)Mr. Shaia may be contacted at
rshaia@watttieder.com
Just When You Thought General Contractors Were Necessary Parties. . .
November 30, 2020 —
Christopher G. Hill - Construction Law MusingsDid you think that a subcontractor had to name a general contractor in a mechanic’s lien suit? I did. Did you think that nothing about this changed in the case where a Virginia mechanic’s lien was “bonded off” pursuant to Va. Code Section 43-71? I did.
Well, a recent Virginia Supreme Court case, Synchronized Construction Services Inc. v. Prav Lodging LLC, seems to at least create some doubt as to whether the a general contractor is a “necessary” party to a lawsuit by a subcontractor in the case where a bond is posted for release of a mechanic’s lien.
In Prav Lodging, the facts were a bit unusual. The day after the mechanic’s lien was recorded by Synchronized Construction Services, Inc. (“Synchronized”) the construction manager, Paris Development Group, the construction manager and de facto general contractor, went out of business. Despite this fact, and after the lien was bonded off, Synchronized sued to enforce the lien and for breach of contract against Paris. The wrinkle here is that Synchronized was unable to serve several defendants, among them Paris, within one year of filing suit as required by Virginia statute. In the Circuit Court, the financing bank moved to dismiss the suit for failure to serve necessary parties. The Circuit Court dismissed the breach of contract count but refused to dismiss the mechanic’s lien count on this basis.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Chambers USA 2019 Ranks White and Williams as a Leading Law Firm
June 03, 2019 —
David Marion, Patricia Santelle & Maulin Vidwans - White and Williams LLPChambers USA once again recognized White and Williams as a leading law firm in Pennsylvania for achievements and client service in the area of insurance law. In addition, three lawyers received individual honors - one for her work in insurance, one for his work in commercial litigation and another for his work in banking and finance.
White and Williams is acknowledged for its renowned practice offering expert representation to insurers and reinsurers across an impressive range of areas including coverage, bad faith litigation and excess liability. The firm is recognized for its notable strength in transactional and regulatory matters complemented by its adroit handling of complex alternative dispute resolutions. Chambers also acknowledged the firm's broad trial capabilities, including handling data privacy, professional liability and toxic tort coverage claims, and experience in substantial claims arising from bodily injury and wrongful death suits.
White and Williams' individual lawyer honorees include Managing Partner Patti Santelle, who is named an Eminent Practitioner in the area of insurance. Patti's considerable experience advising insurers on a broad range of coverage matters, including asbestos, environmental and toxic tort cases, coupled with her proficiency in coverage actions at the state and federal level earn her a well-regarded reputation as an "excellent lawyer."
Reprinted courtesy of White and Williams LLP attorneys
David Marion,
Patricia Santelle and
Maulin Vidwans
Mr. Marion may be contacted at mariond@whiteandwilliams.com
Ms. Santelle may be contacted at santellep@whiteandwilliams.com
Mr. Vidwans may be contacted at vidwansm@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of
South Carolina Clarifies the Accrual Date for Its Statute of Repose
March 18, 2019 —
William L. Doerler - The Subrogation StrategistIn Lawrence v. General Panel Corp., 2019 S.C. LEXIS 1, No. 27856 (S.C. Jan. 1, 2019), the Supreme Court of South Carolina answered a certified question related to South Carolina’s statute of repose, S.C. Code § 15-3-640,[1] to wit, whether the date of “substantial completion of the improvement” is always measured from the date on which the certificate of occupancy is issued. The court held that a 2005 amendment to § 15-3-640 did not change South Carolina law with respect to the date of substantial completion. Thus, under the revised version of § 15-3-640, “the statute of repose begins to run at the latest on the date of the certificate of occupancy, even if there is ongoing work on any particular part of the project.” A brief review of prior case law may assist with understanding the court’s ruling in Lawrence.
In Ocean Winds Corp. of Johns Island v. Lane, 556 S.E.2d 377 (S.C. 2001), the Supreme Court of South Carolina addressed the question of whether § 15-3-640 ran from substantial completion of the installation of the windows at issue or on substantial completion of the building as a whole. Citing § 15-3-630(b),[2] the court found that the windows “were ‘a specified area or portion’ of the larger condominium project” and, upon their incorporation into the larger project they could be used for the purpose for which they were intended. Thus, the court held that “the statute of repose began running when installation of the windows was complete.”
Read the court decisionRead the full story...Reprinted courtesy of
William L. Doerler, White and WilliamsMr. Doerler may be contacted at
doerlerw@whiteandwilliams.com