Boilerplate Contract Language on Permits could cause Problems for Contractors
March 19, 2014 —
Beverley BevenFlorez-CDJ STAFFCraig Martin on his blog Construction Contractor Advisor discusses the potential problems for a contractor that a “boilerplate contract” could cause: “A recent case revealed the problems a contractor had with permits when the contractor’s estimate contemplated an easy permitting process and compliance, but in actuality it was much, much more difficult.”
Martin cites the case Bell/Heery v. United States, where a contractor discovered that the permit process would be much more time-consuming and expensive than originally planned. When Bell/Heery asked for additional funds to cover the additional costs, the “contracting officer rejected the request, finding that Bell/Heery had assumed the risk of the permitting process and it was liable for any costs associated with the permitting process and construction methods required by the permitting process.”
“Bell/Heery appealed to the Court of Claims,” but lost the battle. The contractor had to absorb $7 million in costs to comply with the required permits.
Read the court decisionRead the full story...Reprinted courtesy of
If I Released My California Mechanics Lien, Can I File a New Mechanics Lien on the Same Project? Will the New Mechanics Lien be Enforceable?
December 29, 2020 —
William L. Porter - Porter Law GroupIf I Released My California Mechanics Lien, Can I File a New Mechanics Lien on the Same Project? Will the New Mechanics Lien be Enforceable?
In general, the answer to the above questions is “Yes”, but only if you meet the following requirements:
- You must only release the mechanics lien itself, but not the “right” to a mechanics lien: There is an important distinction to be made between releasing a mechanics lien and releasing the right to a mechanics lien. Whether you do one or the other will depend on the specific language used in your release. In the case of Santa Clara Land Title Co. v. Nowack and Associates, Inc. (1991) 226 Cal. App.3d, 1558 a “release of mechanics lien” document was recorded TO THE County Recorder’s office which included a statement that the mechanics lien was “fully satisfied, released and discharged”. Based on this language, the court concluded that the mechanics lien claimant had waived its “right” to a further mechanics lien on the same property for the work in question. The court concluded that since the release stated that the claim was “fully satisfied” the right to mechanics lien on the project had forever been waived. The Nowak case can be distinguished from the case of Koudmani v. Ogle Enterprises, Inc., (1996) 47 Cal.App.4th 1650, where the release of mechanics lien only stated that the mechanics lien was “otherwise released and discharged” and not that it was “satisfied”. Based on the distinction drawn from the two cases, a simple mechanics lien release that only releases the mechanics lien itself, but not the “right” to a mechanics lien should be used. At the following link you will find a proper form to achieve this purpose: https://www.porterlaw.com/wp-content/uploads/2019/06/03PRI-Mechanics-Lien-Release.pdf
Read the court decisionRead the full story...Reprinted courtesy of
William L. Porter, Porter Law GroupMr. Porter may be contacted at
bporter@porterlaw.com
An Era of Legends
May 03, 2018 —
Beverley BevenFlorez-CDJ STAFFIn 2010, West Coast Casualty’s Construction Defect Seminar added a new award: The Legend of an Era. West Coast Casualty recognizes “those in the construction defect community who inspire, contribute, advocate and influence others for the benefit and betterment of this community, making it a better place.”
They define Legend as “One that inspires or achieves legendary fame based upon ones own achievement(s) which promises to be enduring” and Era, as “A fixed point of time from which a series of years is reckoned and an order of things prevail.”
This annual award is presented at the West Coast Casualty Construction Defect Seminar.
Read the court decisionRead the full story...Reprinted courtesy of
Construction Law Client Advisory: What The Recent Beacon Decision Means For Developers And General Contractors
August 20, 2014 —
Steven M. Cvitanovic and Whitney L. Stefko - Haight Brown & Bonesteel LLPOn July 3, 2014, the California Supreme Court (the “Court”) came out with its decision in Beacon Residential Community Association v. Skidmore, Owings & Merrill, et al. The Beacon decision settled a long-standing dispute in California about whether design professionals such as architects and engineers owe a duty to non-client third parties. In finding that the plaintiffs in Beacon could state a claim against the architects of the Beacon project, the Court also sowed the seeds of change in the way contracts are structured between developers, architects, engineers, and even general contractors.
So, how will Beacon change the landscape for developers and general contractors? It is important to understand the factual background in Beacon to predict how the decision may alter the playing field. For a detailed analysis of the Amicus briefs in the Beacon matter from the AIA, the CBIA, and the Consumer Attorneys of California, please click here.
The Beacon case arose from a common development model in California: a developer conceives a multi-unit project, maps the project as a condo development but rents as apartments. Shortly after completion of the Beacon project, the developer sold the entire project and the new owner finalized the existing condominium map and placed the units on the market as condominiums. Although the architects always knew they had designed a residential structure, the project ultimately became a condominium development. The newly formed homeowners’ association filed a construction defect suit against the developers, general contractor, the subcontractors and the architects for design and construction defects.
Reprinted courtesy of
Steven M. Cvitanovic, Haight Brown & Bonesteel LLP and
Whitney L. Stefko, Haight Brown & Bonesteel LLP
Mr. Cvitanovic may be contacted at scvitanovic@hbblaw.com; Ms. Stefko may be contacted at wstefko@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
How Does Weather Impact a Foundation?
December 27, 2021 —
Brent Pearson - Construction ExecutiveWhen it comes to commercial properties, it pays to be prepared. However, there are few things as unpredictable as the weather. With there being several weeks left in hurricane season, the weather can have quite an impact on the foundations of different properties. Whether it’s a new home or a century-old commercial property, preserving the integrity and safety of the structure is paramount. For those in construction looking to learn more about how the weather can sway a foundation, below are several examples along with tips on prevention.
Rain, Rain Go Away!
Hurricanes are known for bringing strong winds and plenty of rain. This can spell disaster for buildings with weak foundations. Torrential downpours can cause wet and weak soil. Too much rain—whether generated by hurricanes or frequent storms—can negatively impact the foundations of commercial properties and homes as well. It can also cause the soil to weaken, which can lead to a foundation sinking into the ground. For those that may have crawl spaces underneath their properties, heavy rains may cause water to seep under and into it. Water will sit in the crawl space, and it could take days or even weeks to dry out, causing moisture and possible mold damage.
Reprinted courtesy of
Brent Pearson, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Is Your Design Professional Construction Contract too Friendly? (Law Note)
July 09, 2014 —
Melissa Dewey Brumback – Construction Law North CarolinaMy husband often travels the back roads between Chapel Hill and Fuquay Varina to visit friends. En route (a circuitous route that goes past Sharon Harris Nuclear Power Plant, among other places), he passes by the “Friendly Grocery.”
[Sign]
No *Loitering*Littering*Alcoholic Beverages on Premises*Bike*Skateboard*
*10 minutes Parking Limit*Towing Enforced*
I’m not sure which is the “friendly” part of that sign. In fact, the sign seems to be the antithesis of friendly.
What does this have to do with your construction contracts? Sometimes, in an effort to please the client and/or secure the project, architects and engineers have the habit of being too friendly in their contract language. That is, you make promises or proposals that may promise too much of a good thing for the client. This can cause big problems. Bigger than being towed away from a rural grocery store in the middle of nowhere. You could be putting your insurance coverage at risk.
Have you ever promised to use “best efforts” in your design or plans? Promised to design to a specific LEED standard? Guaranteed 100% satisfaction? You might be putting your errors & omission coverage at issue. By warrantying or guaranteeing something, you are assuming a level of liability well beyond the standard of care required by law. By law, you only need to conform to the standard of care, and your insurance will only provide coverage up to that standard of care. In other words, if you make guarantees or promise “best efforts,” you are contracting to something that will *not* be insured. If something goes wrong, you will be without the benefit of your professional liability coverage.
Read the court decisionRead the full story...Reprinted courtesy of
Melissa Dewey Brumback, Construction Law in North CarolinaMs. Brumback may be contacted at
mbrumback@rl-law.com
Federal Magistrate Judge Recommends Rescission of Policies
February 12, 2024 —
Craig Rokuson - Traub LiebermanIn the recent case of Union Mut. Fire Ins. Co. v. 142 Driggs LLC, 2023 U.S. Dist. LEXIS 220393, Magistrate Judge Lois Bloom of the United States District Court for the Eastern District of New York recommended granting the insurer's default judgment and holding that of three policies issued to 142 Driggs LLC ("Driggs") be rescinded ab initio.
Driggs had represented on its insurance applications that it did not provide parking to anyone other than itself, tenants, and its guests at the subject insured premises. However, Union Mutual learned that Driggs had been renting out three garages to non-tenants. Second, Driggs represented that the mercantile square footage was around 1,000 square feet, when in actuality, it was larger than allowed under the policies.
Union Mutual provided underwriting guidelines in connection with its default motion, which state that "parking provided for anyone other than the insured, tenants and their guests," presents an "unacceptable risk." The guidelines also state that answering yes to any "preliminary application questions (which presumably included those regarding mercantile square footage and parking) is an "unacceptable risk." The court held that these guidelines supported a finding that Driggs made material misrepresentation and that Union Mutual relied on these misrepresentations in issuing the policies. The court, as such, recommended that the policies at issue be rescinded from inception.
Read the court decisionRead the full story...Reprinted courtesy of
Craig Rokuson, Traub LiebermanMr. Rokuson may be contacted at
crokuson@tlsslaw.com
Incorporate Sustainability in Building Design to Meet Green Construction Goals
September 25, 2018 —
Norma Lehman - Construction ExecutiveA few miles outside the city limits of Austin, Texas, construction work is expected to soon begin on the Austin Ridge Bible Church’s tri-level, 80,000-square-foot building. The building will house a 2,500-seat sanctuary, classrooms and other spaces where congregants can gather for prayer and fellowship.
When the project is completed, scheduled for the end of 2019, it will produce a worship place that will significantly reduce the building’s energy costs in the years ahead.
Reprinted courtesy of
Norma Lehman, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of