The Relevance and Reasonableness of Destructive Testing
August 17, 2017 —
David Adelstein - Florida Construction Legal UpdatesDestructive testing is a routine investigatory procedure in construction defect disputes. The destructive testing is necessary to determine liability (causation), the extent of damage, and the repair protocol. Destructive testing is designed to answer numerous questions: Why did the building component fail? Was the building component constructed incorrectly? What is the magnitude of the damage caused by the failure? What specifically caused the damage? What is the most effective way to fix the failure and damage? There are different iterations to the same questions, but in many instances, destructive testing is necessary to answer these questions.
Claimants sometimes prohibit destructive testing. Of course, destructive testing is intrusive. In many instances, it is very intrusive. But, this testing is a necessary evil. Without this testing, how can a defendant truly analyze their potential exposure and culpability? They need to be in a position to prepare a defense and figure out their liability. This does not mean destructive testing is warranted in every single construction defect dispute. That is not the case. However, to say it is never warranted is irrational.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Florida Construction Legal UpdatesMr. Adelstein may be contacted at
Dadelstein@gmail.com
Subcontractor Exception to Your Work Exclusion Paves the Way for Coverage
April 03, 2013 —
CDJ STAFFIn a brief opinion, the Second Circuit vacated the district court's denial of coverage for construction defects. Scottsdale Ins. Co. v. R.I. Pools Inc., 2013 U.S. App. LEXIS 5680 (2nd Cir. March 21, 2013).
The insured, R.I. Pools, employed outside companies to supply concrete and to shoot the concrete into the ground. During the summer of 2006, it obtained its concrete from one subcontractor and used another to shoot the concrete. In 2009, nineteen customers of R.I. Pools from 2006 complained damage to their pools, including cracking, flaking, and deteriorating concrete.
Scottsdale sought a declaratory judgment against R.I. Pools that it had no obligations under the policy to defend or indemnify for claims related to cracks in the pools.
Read the court decisionRead the full story...Reprinted courtesy of
Tred EyerlyTred Eyerly can be contacted at
te@hawaiilawyer.com
Appreciate The Risks You Are Assuming In Your Contract
February 10, 2020 —
David Adelstein - Florida Construction Legal UpdatesAPPRECIATE THE RISKS YOU ARE ASSUMING IN YOUR CONTRACT. Otherwise, those risks will come back and bite you in the butt. This language is not capitalized for naught. Regardless of the type of contract you are entering into, there are risks you will be assuming. You need to appreciate those risks because there may be insurance you can obtain to cover that risk.
For instance, exculpatory provisions (or get-out-of-jail provisions) in contracts are enforceable if they are unambiguous. “Such provisions are deemed to be unambiguous and enforceable when the language unequivocally demonstrates a clear and understandable intention for the defendant to be relieved from liability such that an ordinary and knowledgeable person will know what he or she is contracting away.” Pillay v. Public Storage, Inc., 44 Fla.L.Weekly D2744c (Fla. 4th DCA 2019).
An example of an exculpatory provision can be found in the public storage rental contract found in Pillay that read:
(1) ALL PERSONAL PROPERTY IS STORED BY OCCUPANT AT OCCUPANT’S SOLE RISK.
(2) Owner and Owner’s agents . . . will not be responsible for, and Tenant releases Owner and Owner’s agents from any responsibility for, any loss, liability, claim, expense, damage to property . . . including without limitation any Loss arising from the active or passive acts, omission or negligence of Owner or Owner’s agents.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
COVID-19 Business Interruption Claims Four Years Later: What Have We Learned?
September 23, 2024 —
Patrick McKnight - The Dispute ResolverFour and half years ago the COVID-19 pandemic spread around the globe, bringing with it interesting, but challenging, legal problems for construction attorneys. Construction projects ground to a halt. Ever-changing guidance from authorities ranging from the U.S. Department of Labor to local health authorities resulted in a web of evolving obligations for general contractors and subs alike. One of the most closely watched legal questions was the wave of business interruption claims filed by plaintiffs, many of whom owned businesses impacted by government shutdowns. During the opening months of the pandemic, I
noted that hundreds of business interruption claims had been filed by insureds across the country. At that time, the only thing certain was that although the outcome remained unknown, virus exclusions were likely to become more likely in the future. Needless to say, much has happened since early 2020.
What does the data say about the outcome of business interruption claims?
In sum, plaintiffs have had an uphill battle. A helpful resource for analyzing the outcome of business interruption suits is the
Covid Coverage Litigation Tracker (“Tracker”), an insurance law analytics tool offered by Penn Carey Law of the University of Pennsylvania. According to its website, “[t]he Covid Coverage Litigation Tracker is a multi-sourced database and dashboard through which to view the unfolding insurance litigation arising out of the pandemic in federal and state courts. Widely cited in briefs, judicial opinions, and the press, the tracker also serves as a proof of concept for new methods to identify, track, and understand emerging case congregations in real time.”
Read the court decisionRead the full story...Reprinted courtesy of
Patrick McKnight, Fox Rothschild LLPMr. McKnight may be contacted at
pmcknight@foxrothschild.com
Texas Federal District Court Dismisses COVID-19 Claim
October 25, 2020 —
Tred R. Eyerly - Insurance Law HawaiiJudge Ezra, formerly on the bench in Hawaii, dismissed a COVID-19 claim pursued by a Texas policy holder. Diesel Barbershop, LLC v. State Farm Lloyds, 2020 U.S. Dist. LEXIS 147276 (W.D. Texas Aug. 13, 2020).
Local and state officials in Texas issued shutdown orders in March 2020 due to the spread of the cornavirus. All non-essential businesses, including the insureds' barbershop businesses, were ordered closed from April 2, 2020 until April 30, 2020. The insureds submitted a claim for business interruption and civil authority coverage to their carrier, State Farm. The claim was denied based on the policy's exclusion for loss caused by enforcement of ordinance or law, virus, and consequential losses. For Civil Authority coverage, State Farm contended the policy required that there by physical damage within one mile of the described property and that the damage be the result of a Covered Cause of Loss, which, State Farm asserted, a virus was not.
The insureds sued and State Farm moved to dismiss. The court noted cases in which courts had found physical loss even without tangible destruction to the covered property. Yet, the court found that the line of cases requiring tangible injury to property were more persuasive. Therefore, the court found that the insureds failed to plead a direct physical loss.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Hunton Insurance Practice Again Scores “Tier 1” National Ranking in US News Best Law Firm Rankings
December 05, 2022 —
Hunton Insurance Recovery BlogOn November 3, 2022, US News announced its
annual law firm rankings, where Hunton Andrews Kurth LLP garnered the highest (Tier 1) ranking among national insurance law practices. Hunton’s insurance team also received Tier 1 honors for “Insurance Law” in three regions (Washington, DC, Atlanta and San Francisco) and Tier 2 honors for “Litigation – Insurance” in Washington, DC. US News ranks law firms in tiers from 1 (highest) to 3 (lowest) based on quantitative data that speaks to general demographic and background information on the practice group, attorneys and other data that speaks to the strengths of a law firm’s practice, as well as qualitative client feedback about:
- the practice group’s expertise,
- responsiveness,
- understanding of a business and its needs,
- cost-effectiveness,
- civility, and
- whether the client would refer another client to the firm.
Read the court decisionRead the full story...Reprinted courtesy of
Hunton Andrews Kurth LLP
Florida’s Construction Defect Statute of Repose
August 24, 2017 —
David Suggs – Bert L. Howe & Associates, Inc.Butler Weihmuller of Katz Craig LLP discussed Florida’s 10-year statute of repose law: “Under § 95.11(3)(c), the action must commence within 10 years after the date of actual possession by the owner, the date of the issuance of a certificate of occupancy, the date of abandonment of construction if not completed, or the date of completion or termination of the contract between the professional engineer, registered architect, or licensed contractor and his or her employer, whichever date is latest.”
However, Weihmuller explains that parties may disagree on the specific date For instance, in Busch v. Lennar Homes, LLC, Florida’s 5th DCA recently “reversed a trial court’s dismissal of a homeowner’s construction defect claim that was filed just beyond 10 years after the closing date on the property.” The previous decision had been based on the notion that the contract had been completed upon the date of closing. The 5th DCA declared that “a contract is not completed until both sides of a contract have been performed” and “pointed to the ‘inspection and punch-list clause’ of the contract.” The clause indicated that “[a]ny remaining items that Seller has agreed to correct will be corrected by Seller at Seller’s sole cost and expense prior to closing or at Seller’s option within a reasonable time after closing.” Since not all punch-list items had been completed prior to closing, the 5th DCA held that the contract had not been completed at closing, and therefore the statute of repose did not begin until the punch-items had been accomplished.
Read the court decisionRead the full story...Reprinted courtesy of
EPA Fines Ivory Homes for Storm Water Pollution
June 26, 2014 —
Beverley BevenFlorez-CDJ STAFF“Utah’s largest home builder [Ivory Homes] has agreed to a $250,000 fine and to take several steps…to comply with Clean Water Act requirements to control pollution associated with storm-water runoff from construction sites,” reported The Salt Lake Tribune.
David Broadbent, Ivory Homes’ chief operating officer, stated in an email to The Salt Lake Tribune: “We are proud of our environmental record, particularly our storm-water compliance record. We are the first and the only home builder in Utah to implement a robust, companywide program to safeguard against sediment from entering Utah waters as a result of home-building activities.” Furthermore, Broadbent declared that the “inspections that led to the violations notices” did not yield any evidence that their “home-building practices resulted in any sediment discharge in any amount, let alone harm, to Utah waters.”