Mexico’s Construction Industry Posts First Expansion Since 2012
August 13, 2014 —
Brendan Case – BloombergMexico’s construction industry expanded in June for the first time in 19 months, adding to signs that the economy is rebounding after missing analyst estimates in seven of the last eight quarters.
Construction increased 2.2 percent from the year earlier, helping industrial production to expand 2 percent, according to data released today by the national statistics agency. The median estimate of 19 economists surveyed by Bloomberg was for industrial output to rise 2.1 percent.
“Industrial activity continued strengthening in June, very much in line with what the market expected,” Mario Correa, the chief Mexico economist at Bank of Nova Scotia, said in a note to clients today. “The construction industry finally showed a positive growth rate.”
Read the court decisionRead the full story...Reprinted courtesy of
Brendan Case, BloombergMr. Case may be contacted at
bcase4@bloomberg.net
No Coverage Under Property Policy With Other Insurance and Loss Payment Provisions
September 17, 2015 —
Tred R. Eyerly – Insurance Law HawaiiThe court determined that the other insurance and loss payment provisions relieved the insurer of coverage obligations. Moroney Body Works, Inc. v. Central Ins. Co., 2015 Mass. App. LEXIS 97 (Aug. 6, 2015).
A fire destroyed Moroney's custom-built bookmobile that had just been completed. Moroney had two policies: a commercial property policy issued by Central, and a garage insurance policy issued by Pilgrim Insurance Company. Central denied liability for the bookmobile. Pilgrim covered the cost of repairing the bookmobile. It paid $12,449.82 based on the appraiser's estimate of the repair costs. Moroney thought this amount was inadequate given its own estimate of the repair costs.
Moroney sued both insurers. Pilgrim settled by paying Moroney an additional amount which, when added to Pilgrim's earlier payment, resulted in Moroney receiving more than the repair cost. Moroney and Central both moved for summary judgment. The trial court granted Moroney's motion.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Statute of Limitations Upheld in Construction Defect Case
September 30, 2011 —
CDJ STAFFThe Missouri Court of Appeals has ruled in Ball v. Friese Construction Co., finding that Mr. Ball’s claims were barred by the statute of limitations.
Mr. Ball hired Friese Construction Company to build a single-family home. The sale was completed on March 29, 2001. That December, Mr. Ball complained of cracks in the basement floor. SCI Engineering, n engineering firm, hired by Friese, determined that the home’s footing had settled and recommended that Mr. Ball hire a structural engineer to determine if the footings were properly designed and sized. In September 2002, the structural engineer, Strain Engineering, determined that the cracks were due to slab movement, caused in part by water beneath the slab, recommending measures to move water away from the foundation. In 2005, Mr. Ball sent Friese correspondence “detailing issues he was having with the home, including problems with the basement slab, chimney structure, drywall tape, and doors.” All of these were attributed to the foundation problems. In 2006, Friese stated that the slab movement was due to Ball’s failure to maintain the storm water drains.
In 2009, Ball received a report from GeoTest “stating the house was resting on highly plastic clay soils.” He sued Friese in May, 2010. Friese was granted a summary judgment dismissing the suit, as the Missouri has a five-year statute of limitations. Ball appealed on the grounds that the extent of the damage could not be determined until after the third expert report. The appeals court rejected this claim, noting that a reasonable person would have concluded that after the conclusion of SCI and Strain Engineering that “injury and substantial damages may have occurred.”
The court concluded that as there were not “continuing wrongs causing new and distinct damages,” he should have filed his lawsuit after the first two expert reports, not waiting seven years for a third expert to opine.
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
A Few Green Building Notes
April 03, 2019 —
Christopher G. Hill - Construction Law MusingsThis past week, the blogosphere (if that’s even the word these days) has been abuzz about green building and the value that green can add to a project. Three items in particular (among many) got my attention.
The first of these was the fact that a new private sustainability rating system is ready for launch. The Institute for Sustainable Infrastructure (or ISI) is seeking public comment on its proposed envISIon. This new system (aptly dubbed Version 1.0) will go “live” in July for comment. Why mention this new system? First of all, ISI’s founding members are the American Society of Civil Engineers (ASCE), the American Public Works Association (APWA) and the American Council of Engineering Companies (ACEC). This trio gives the new program some fairly heavy weight backing. Second, while there are rating systems aside from the ever present LEED, none have taken hold in any real way to compete with LEED. I am curious to see if the envISIon system has any better luck. Finally, this shows that sustainable building is of interest to more than the USGBC and those of us that discuss LEED on a daily basis. I find this to be a great thing that could lead to more societal acceptance of sustainable practices as a standard practice rather than a goal.
Hopefully such efforts will offset the other two notes that caught my eye recently.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Palo Alto Proposes Time Limits on Building Permits
October 01, 2013 —
CDJ STAFFPalo Alto, California has a problem. Too many construction or renovation projects have languished without any sign of completion. The city council has a solution: time limits. Under current rules, projects only have to complete enough work so that there’s something to inspect every six months.
Under the proposed rules, builders would have a set time to finish the project, with larger projects getting more time in which to finish. Projects that ran over that time would get fines.
Read the court decisionRead the full story...Reprinted courtesy of
The American Rescue Plan Act: What Restaurants Need to Act on NOW
March 22, 2021 —
Michael Krueger - Newmeyer DillionThe American Rescue Plan Act (“Act”) was passed by the Senate over the weekend and passed by the House today. President Biden is set to sign the Act into law on Friday, March 12th. The Act has $1.9 Trillion in relief funds with $28.6 Billion set aside for the restaurant industry in the Restaurant Revitalization Fund (“Fund”). The Fund has apportioned funds into two funding groups; $5 Billion for restaurants with annual gross revenue under $500,000 and $23.6 Billion for restaurants over $500,000 in annual gross revenue.
Differences from the Paycheck Protection Program (“PPP”)
This is a grant program with no loan documents or forgiveness applications. Instead, each restaurant entity can apply for and receive up to $10M in grant funds through the Act. The amount a restaurant receives is based on the sum of the restaurant’s gross revenue in 2019 minus the gross revenue in 2020 minus PPP and EIDL money received. For example, Restaurant A made $7M gross revenue in 2019, made $3M gross revenue in 2020 and received $1M in PPP and EIDL combined. ($7M - $3M -$1M =$3M) The restaurant will receive $3M in grant funds directly from the SBA (as long as funds are available).
Read the court decisionRead the full story...Reprinted courtesy of
Michael Krueger, Newmeyer DillionMr. Krueger may be contacted at
michael.krueger@ndlf.com
Green Buildings Could Lead to Liabilities
March 28, 2012 —
CDJ STAFFAttempts to build “green,” reducing energy costs and increasing the use of sustainable building materials, may lead to more lawsuits, according to a report issued by the British Columbia Construction Association. The report warned those who were going to build green look into the implications. The report looked at the result of green building practices and requirements adopted in the United States.
The report warns that “the use of novel, less harmful building material or new construction techniques may give rise to liability due to: contractor inexperience with installation; lack of long-term evaluation of green materials; lack of understanding of how new building materials may impact existing traditional building systems; or warranties provided unintentionally about the durability or effectiveness of unproven materials or techniques.”
Manley McLachlan, president of the BCAA noted that they are aware of “legal action around the performance of the buildings,” noting that while fast-growing trees help toward LEED certification, their wood is more prone to mold. He also felt that low-VOC paints needed more testing to prove their durability as exterior finishes.
Read the full story…
Read the court decisionRead the full story...Reprinted courtesy of
New York Court of Appeals Finds a Proximate Cause Standard in Additional Insured Endorsements
June 15, 2017 —
Geoffrey Miller - Saxe Doernberger & Vita, P.C.In The Burlington Insurance Company v. NYC Transit Authority, et al., No. 2016-00096, the New York Court of Appeals issued a landmark decision with regard to the meaning of “caused, in whole or in part, by” in the additional insured context. In a split decision, the court rejected Burlington Insurance Company’s argument that the language implied a “negligence” standard, but held that coverage was provided to the additional insured only where the named insured’s acts or omissions were the proximate cause of the injury:
While we [the majority] agree with the dissent that interpreting the phrases differently does not compel the conclusion that the endorsement incorporates a negligence requirement, it does compel us to interpret ‘caused, in whole or in part’ to mean more than ‘but for’ causation. That interpretation, coupled with the endorsement’s application to acts or omissions that result in liability, supports our conclusion that proximate cause is required here.[1]
Read the court decisionRead the full story...Reprinted courtesy of
Geoffrey Miller, Saxe Doernberger & Vita, P.C.Mr. Miller may be contacted at
gjm@sdvlaw.com