Value in Recording Lien within Effective Notice of Commencement
August 03, 2020 —
David Adelstein - Florida Construction Legal UpdatesConstruction lien priority is no joke! This is why a lienor wants to record its construction lien within an effective notice of commencement. A lien recorded within an effective notice of commencement relates back in time from a priority standpoint to the date the notice of commencement was recorded. A lienor that records a lien wants to ensure its lien is superior, and not inferior, to other encumbrances. An inferior lien or encumbrance may not provide much value if there is not sufficient equity in the property. Plus, an inferior lien or encumbrance can be foreclosed.
An example of the importance of lien priority can be found in the recent decision of Edward Taylor Corp. v. Mortgage Electronic Registration Systems, Inc., 45 Fla.L.Weekly D1447b (Fla. 2d DCA 2020). In this case, a contractor recorded a notice of commencement for an owner. While an owner is required to sign the notice of commencement that the contractor usually records, in this case, the owner did not sign the notice of commencement. Shortly after, the owner’s lender recorded a mortgage and then had the owner sign a notice of commencement and this notice of commencement was also recorded. When there is a construction lender, the lender always wants to make sure its mortgage is recorded first—before any notice of commencement—for purposes of priority and has the responsibility to ensure the notice of commencement is recorded. Here, the lender apparently did not realize the contractor had already recorded a notice of commencement at the time it recorded its mortgage.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Insurance Policy Language Really Does Matter
August 19, 2015 —
Craig Martin – Construction Contractor AdvisorThe debate continues on whether a subcontractor’s faulty work constitutes property damage and an occurrence such that the insurer must cover the claim. The most recent court to weigh in on this issue is the New Jersey appellate court (one step down from the New Jersey Supreme Court) in Cypress Point Condominium Association, Inc. v. Adria Towers, LLC.
In this case, the condominium association sued the general contractor, who also acted as the developer, and subcontractors for faulty workmanship. The condominium association also sued the insurer for the general contractor, demanding payment of consequential damages caused by a subcontractor’s faulty work. The trial court granted summary judgment to the insurer, holding that the subcontractor’s faulty work was not property damage and thus not an occurrence under the Commercial General Liability (CGL) insurance policy, so no coverage.
The appellate court reversed the trial court’s decision, finding that the claims for consequential damages caused by faulty workmanship constituted property damage and an occurrence as defined in the policy. This was a shift from earlier opinions in New Jersey.
Read the court decisionRead the full story...Reprinted courtesy of
Craig Martin, Lamson, Dugan and Murray, LLPMr. Martin may be contacted at
cmartin@ldmlaw.com
Hurry Up and Wait! Cal/OSHA Hits Pause on Emergency Temporary Standards for COVID-19 Prevention
June 14, 2021 —
Michael Studenka & Jasmine Shams - Newmeyer DillionEmployers scrambling to prepare for the June 15th Reopening announced by Governor Newsom have spent the last week pouring over the revised Emergency Temporary Standards for COVID-19 Prevention (“Revised ETS”) approved by the Cal/OSHA Standards Board on June 3, 2021. After last night’s meeting of the Standards Board, however, it’s time to hit pause.
Last night, the Cal OSHA Standards Board held a specialty meeting to reconsider its Revised ETS in light of the latest guidance on face coverings issued by the California Department of Public Health (“CDPH”) on June 7, 2021. Following a presentation by the CDPH and extensive public comment, the Cal OSHA Standards Board voted unanimously to withdraw the Revised ETS and to take up the issue again at its next scheduled meeting on June 17, 2021. The net result in the interim is that California employers who intend to reopen on June 15 must initially comply with all of the requirements of the Cal/OSHA Standards Board Emergency Temporary Standards for COVID-19 Prevention as originally issued on November 20, 2020, including but not limited to, its social distancing, physical partitioning and mask wearing requirements.
Reprinted courtesy of
Michael J. Studenka, Newmeyer Dillion and
Jasmine Shams, Newmeyer Dillion
Mr. Studenka may be contacted at michael.studenka@ndlf.com
Ms. Shams may be contacted at jasmine.shams@ndlf.com
Read the court decisionRead the full story...Reprinted courtesy of
Retaining Wall Contractor Not Responsible for Building Damage
July 20, 2011 —
CDJ STAFFThe Court of Appeals of Indiana ruled on July 8 in the case of Rollander Enterprises, Inc. v. H.C. Nutting Co. Judge Baily wrote the opinion affirming the decision of the trial court.
The case involved an unfinished condominium complex, the Slopes of Greendale, in Greendale, Indiana. Rollander is a real estate development company incorporated in Ohio. One of the issues in the case was whether the case should be settled in the Indiana courts or be tried in Ohio. The project was owned by a special purpose entity limited liability corporation incorporated in Indiana.
Rollander hired Nutting to determine the geological composition of the site. Nutting’s report described the site as “a medium plastic clay containing pieces of shale and limestone.” The court summarized this as corresponding with “slope instability and landslides.” Rollander then hired Nutting to design the retaining walls, which were constructed by Scherziner Drilling.
After cracking was discovered on State Route 1, the walls were discovered to be inadequate. More dirt was brought in and a system of tie-backs was designed to anchor the walls. Not only were the tie-backs unsightly, local officials would not approve the complex for occupancy. Further, the failure of the wall below one building lead to damage of that building.
The court concluded that since almost all events occurred in Indiana, they rejected Rollander’s contention that the case should be tried in Ohio. Further, the court notes “the last event making Nutting potentially liable on both claims was an injury that occurred in Indiana and consequently, under the lex loci delicti analysis, Indiana law applies.”
Nor did the court find that Nutting was responsible for the damage to the rest of the project, citing an Indiana Supreme Court ruling, that “there is no liability in tort to the owner of a major construction project for pure economic loss caused unintentionally by contractors, subcontractors, engineers, design professionals, or others engaged in the project with whom the project owner, whether or not technically in privity of contract, is connected through a network or chain of contracts.”
The court concluded:
Because Rollander was in contractual privity with Nutting, and Indy was connected to Nutting through a chain of contracts and no exception applies, the economic loss rule precludes their recovery in tort. Damage to Building B was not damage to "other property," and the negligent misrepresentation exception to the economic loss rule is inapplicable on these facts. The trial court therefore did not abuse its discretion by entering judgment on the evidence in favor of Nutting on the Appellants' negligence and negligent misrepresentation claims.
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
Construction Spending Highest Since April 2009
October 25, 2013 —
CDJ STAFFThe Commerce Department has announced that construction spending has increased by 0.6 percent, but that modest gain puts it at the highest it has been in four and a half years. The last time construction spending was this high was April 2009.
The rise in construction spending is due to increases in both public and private construction project. Public construction was up, despite a decrease in spending by the federal government. Private residential construction is at a five-year high.
Read the court decisionRead the full story...Reprinted courtesy of
Exculpatory Provisions in Business Contracts
May 30, 2018 —
David Adelstein - Florida Construction Legal UpdatesAn exculpatory provision in a contract is a provision that relieves one party from liability for damages. It shifts the risk of an issue entirely to the other party. Such a provision is generally drafted by the party preparing the contract that is looking to eliminate or disclaim liability associated with a particular risk, oftentimes a risk within their control. These provisions are also known as limitation of liability provisions because they do exactly that — limit liability as to a risk. For this reason, they can be useful provisions based on the context of certain risks, and are provisions that are included in business contracts (such as construction contracts).
While such clauses are disfavored, they are enforceable if they are drafted clearly, unambiguously, and unequivocally. If they are unclear, ambiguous, or equivocal, they will construed against enforcement. See Obsessions In Time, Inc. v. Jewelry Exchange Venture, LLP, 43 Fla.L.Weekly D1033a (Fla. 3d DCA 2018) (finding exculpatory clause in lease ambiguous and, therefore, unenforceable as to lessor looking to benefit from the exculpatory clause).
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Florida Construction Legal UpdatesMr. Adelstein may be contacted at
dadelstein@gmail.com
Highest Building Levels in Six Years in Southeast Michigan
December 11, 2013 —
CDJ STAFFMacomb Township in southeast Michigan has had $122 million in new development in 2013, all of which helped the region reach its highest building levels since 2007. The wider area saw 398 permits issued for single-family homes in the last twelve months, fifty-two more than in the twelve months prior.
“The improvement is economically driven,” said Michael Stoskofa, the CEO of the Home Builders Association of Southeast Michigan. As employment improves in the area, “more people are willing and able to purchase a home,” he said. Home inventory in the area is also at a record low. As a result, projects that were put on hold in 2008 are active again.
Read the court decisionRead the full story...Reprinted courtesy of
The Big Three: The 9th Circuit Joins The 6th Circuit and 7th Circuit in Holding That Sanctions For Bad-Faith Litigation Tactics Can Only Be Awarded Against Individual Lawyers and Not Law Firms
September 03, 2015 —
Christopher B. Lloyd & Stephen J. Squillario – Haight Brown & Bonesteel LLPIn Law v. Wells Fargo Bank, N.A. (2015 S.O.S. 13–56099 – filed August 27, 2015), the Ninth Circuit joined the shortlist of Circuit Courts to hold that sanctions for bad-faith litigation tactics under 28 U.S.C. section 1927 can only be sought against individual attorneys and not law firms. Section 1927 authorizes sanctions against “[a]ny attorney or other person admitted to conduct cases in any court of the United States … who so multiplies the proceedings in any case unreasonably and vexatiously….”
On behalf of the client, an attorney with Kaass Law filed a complaint against ten different defendants, including Wells Fargo Bank, which moved to dismiss under F.R.C.P. Rule 12(b)(6). Rather than responding to the motion to dismiss, plaintiff filed a motion to amend the initial complaint; Wells Fargo Bank filed a notice of non-opposition.
Reprinted courtesy of
Christopher B. Lloyd, Haight Brown & Bonesteel LLP and
Stephen J. Squillario, Haight Brown & Bonesteel LLP
Mr.Lloyd may be contacted at clloyd@hbblaw.com
Mr. Squillario may be contacted at ssquillario@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of