New Addition To New Jersey Court Rules Impacts More Than Trial Practice
November 16, 2020 —
Thomas Regan & Karley Kamaris - Lewis Brisbois NewsroomOn September 1, 2020, New Jersey adopted a brand-new rule of procedure, Rule 4:25-8, which properly defines motions in limine. On its face, the new rule prohibits, broadly, filing motions in limine that may have a dispositive effect on the case. Most notably, the rule expressly eliminates the ability to move, on motion in limine, to bar expert testimony in matters in which such experts are required to sustain a party’s burden of proof. This effectively makes the summary judgment phase of litigation the last chance to bar experts from a jury trial or take any other dispositive action
The new rule comes at a time in which the evidentiary standard for experts is shifting in New Jersey. In October 2018, the New Jersey Supreme Court reconciled the framework for analyzing the reliability of expert testimony under N.J.R.E. 702 and 703 in In re: Accutane Litigation. Significantly, New Jersey, a traditional Frye jurisdiction, incorporated certain federal Daubert factors for expert “use by our courts” but, overall, fell short of adopting the Daubert standard as a whole. In applying the relevant Daubert factors, the trial court in Accutane held that the subject experts’ methodologies were unsound due to the failure to apply fundamentals of the scientific method of the medical-evidence hierarchy. The decision resulted in the dismissal of over 3,000 claims.
Reprinted courtesy of
Thomas Regan, Lewis Brisbois and
Karley Kamaris, Lewis Brisbois
Mr. Regan may be contacted at Thomas.Regan@lewisbrisbois.com
Ms. Kamaris may be contacted at Karley.Kamaris@lewisbrisbois.com
Read the court decisionRead the full story...Reprinted courtesy of
Hunton Insurance Practice, Partners Recognized by The Legal 500
July 16, 2023 —
Hunton Insurance Recovery BlogHunton Andrews Kurth LLP’s insurance practice was recognized among the top policyholder insurance practices nationally, receiving a Band 2 national ranking in the 2023 United States Edition of The Legal 500 for Advice to Policyholders. The Legal 500 ranks the nation’s top law firms, practices, and lawyers, highlighting those that consistently provide “the most cutting edge and innovative advice to corporate counsel … based on feedback from 300,000 clients worldwide, submissions from law firms and interviews with leading private practice lawyers, and a team of researchers who have unrivalled experience in the legal market.”
Bolstering the team’s national recognition, two of its partners received individual accolades.
Lorie Masters was named in The Legal 500 Hall of Fame and
Andi DeField was named a Next Generation Partner, while team head
Syed Ahmad and partners
Walter Andrews,
Michael Levine and
Geoffrey Fehling also were recognized.
Read the court decisionRead the full story...Reprinted courtesy of
Hunton Andrews Kurth LLP
Attorneys Fees Under California’s Prompt Payment Statutes. Contractor’s “Win” Fails the Sniff Test
October 02, 2015 —
Roger Hughes – California Construction Law BlogThis past month, the California Court of Appeals for the Third District, in James L. Harris Painting & Decorating, Inc. v. West Bay Builders, Inc., Case No. C072169 (August 27, 2015), handed down a decision in a construction contract battle that has raged since 2007. And, once again, the winner is . . . in the words of Justice Andrea Lynn Hoch who authored the opinion . . . . “no prevailing party in [the] case” and hence “no prevailing party attorney’s fees [ ] awarded.”
Background
In Harris, subcontractor James L. Harris Painting & Decorating, Inc. (“Harris”) sued general contractor West Bay Builders, Inc. (“West Bay”) for extra work performed on a school construction project in Stockton, California. Among its claims, Harris asserted that West Bay was liable under California’s prompt payment statutes for failure to timely pay Harris.
Read the court decisionRead the full story...Reprinted courtesy of
Roger Hughes, Wendel Rosen Black & Dean LLPMr. Hughes may be contacted at
rhughes@wendel.com
Court of Appeals Invalidates Lien under Dormancy Clause
January 05, 2017 —
Chadd Reynolds – Autry, Hanrahan, Hall & Cook, LLPOn October 27, 2016, the Georgia Court of Appeals determined whether the Dormancy Statute, which bars the enforcement of judgments after seven years, applied to a lienholder’s action to foreclose its lien.
A property owner (“Owner”), contracted with a contractor Contractor (“Contractor”) to build a home in January 2006. Contractor purchased building materials from a supplier (“Supplier”). In September 2006, Contractor failed to pay for the materials, and Supplier filed a lien on Owner’s property in November 2006. Supplier filed a claim of lien and instituted a lien action against Contractor. In March 2007, a default judgment was entered in favor of Supplier for the lien amount.
It was not until November 2014 that Supplier sued Owner, seeking a declaration of a special lien in the amount of $14,655.65. The trial court granted Supplier’s motion for summary judgment and awarded Supplier a special lien in the amount of $14,655.65 plus $8,305 in accrued interest. Owner appealed, arguing that the lien was rendered unenforceable by the Dormancy Statute.
Read the court decisionRead the full story...Reprinted courtesy of
Chadd Reynolds, Autry, Hanrahan, Hall & Cook, LLPMr. Reynolds may be contacted at
reynolds@ahclaw.com
Bar Against Forum Selection Clauses in Construction Contracts Extended to Design Professionals
October 28, 2015 —
Garret Murai – California Construction Law BlogIt’s a tactic as old as war itself.
You can often gain a strategic advantage by selecting the location of battle.
The same is true in litigation.
But as the next case illustrates, when it comes to disputes between contractors (and design professionals), it isn’t always the combatants who dictate where the battle will be fought.
Vita Planning and Landscape Architecture, Inc. v. HKS Architects, Inc.
In Vita Planning and Landscape Architecture, Inc. v. HKS Architects, Inc., Case No. A141010, California Court of Appeals for the First District (September 25, 2015), Texas architecture firm HKS Architects, Inc. (“HKS”) was hired to provide architectural services. HKS’ design service agreement included a Texas forum selection clause which provided:
As a condition precedent to the institution of any action [or] lawsuit all disputes shall be submitted to mediation” and “[a]ll claim , disputes, and other matters in question between the parties arising out of or related to the Agreement . . . be resolved by the . . . courts in . . . Texas.”
Read the court decision
Read the full story...
Reprinted courtesy of Garret Murai, Wendel Rosen Black & Dean LLP
Mr. Murai may be contacted at gmurai@wendel.com
Insurance Coverage Litigation Section to Present at Hawaii State Bar Convention
October 15, 2014 — Tred R. Eyerly – Insurance Law Hawaii
The Hawaii State Bar convention will be on October 24, 2014, at the Hawaiian Hilton. The Insurance Coverage Litigation Section will make a presentation from 8:30 a.m. to 11:45 a.m.
Three presentations will be made. First, Richard C. Mosher (Anderson Kill), Kathy Dang (Marsh), and Beau Monday (Hawaiian Telcom) will discuss cyber-liability claims and insurance options.
Next, David R. Harada-Stone (Tom Petrus & Miller) and I (Damon Key Leong Kupchak Hastert) will address "occurrences," i.e., deciding on and the impact of determining the number of occurrences in particular factual settings.
Read the court decision
Read the full story...
Reprinted courtesy of Tred R. Eyerly, Insurance Law Hawaii
Mr. Eyerly may be contacted at te@hawaiilawyer.com
ASCE Statement on House Passage of Infrastructure Investment and Jobs Act
November 15, 2021 — American Society of Civil Engineers
The following is a statement by Dennis D. Truax, P.E., President, American Society of Civil Engineers (ASCE):
WASHINGTON, DC. – It is a great day for the nation as the U.S. House of Representatives passed the Infrastructure Investment and Jobs Act (IIJA), fulfilling President Biden's vision with a historic piece of legislation that will have monumental impacts on the economy, public safety, global competitiveness, and each American's well-being. Passage of this five-year, $1.2 trillion bill proves once again that the country can lead with infrastructure.
With this legislation, the federal government will restore their critical partnership with cities and states to modernize our nation's roads, bridges, transit systems, drinking water pipes, school facilities, broadband, ports, airports and more. Without a strong federal partner, local projects that are community lifelines have hung in the balance, oftentimes being paused or outright cancelled due to funding uncertainties. When this happens, American households and businesses are the ones who pay the price.
The IIJA is the culmination of decades of advocacy by American Society of Civil Engineers (ASCE) members who worked tirelessly to educate Congress about the role infrastructure plays in supporting the economy and our quality of life. ASCE's Infrastructure Report Cards have sounded the alarm on our nation's infrastructure conditions since 1998, with new reports being released every four years. While all categories of infrastructure have been the cause of some concerns, the common denominator behind each category's struggles has been a backlog of projects, overdue maintenance, and a need for resilience. This bill includes investments to repair and modernize these critical assets for almost all of the 17 categories in the 2021 Report Card for America's Infrastructure, which assigned our nation's infrastructure a cumulative grade of 'C-'.
ABOUT THE AMERICAN SOCIETY OF CIVIL ENGINEERS
Founded in 1852, the American Society of Civil Engineers represents more than 150,000 civil engineers worldwide and is America's oldest national engineering society. ASCE works to raise awareness of the need to maintain and modernize the nation's infrastructure using sustainable and resilient practices, advocates for increasing and optimizing investment in infrastructure, and improve engineering knowledge and competency. For more information, visit www.asce.org or www.infrastructurereportcard.org and follow us on Twitter, @ASCETweets and @ASCEGovRel.
Read the court decision
Read the full story...
Reprinted courtesy of
Coronavirus, Force Majeure, and Delay and Time-Impact Claims
March 30, 2020 — Garret Murai - California Construction Law Blog
It’s scary, uncertain times as the world grasps with how to deal with the coronavirus pandemic that has now spread to every continent on the globe with the exception of Antarctica. Although this is a global crisis, it has, and for the immediately future will continue to have, a direct impact on us individually as well our industry.
While the impact of the coronavirus on the construction industry is uncertain, what is certain, is that it will have an impact, whether on the construction labor market, on construction supply chains, on the ability of contractors to deliver projects on time and within budget, and on decisions by owners whether to move forward with projects altogether.
According to Ken Simonson, chief economist with the Associated General Contractors of America, during an interview at the ConExpo conference this past week in Las Vegas, while the coronavirus crises “is a story evolving by the hour . . . the impacts on construction are going to happen, but it’s hard to say how extensive, how long they’ll last, [and] how soon they’ll show up.”
From a legal perspective, the coronavirus, and really any natural disaster, from the “Campfire Fire” in Northern California in 2018 to the “Big One” which can happen anytime, has the potential to adversely impact a construction project or shut it down completely. This in turn raises two different, but interrelated legal concepts: (1) force majeure; and (2) delay and time-impact claims. Read the court decision
Read the full story...
Reprinted courtesy of Garret Murai, Nomos LLP
Mr. Murai may be contacted at gmurai@nomosllp.com