Federal Contractors – Double Check the Terms of Your Contract Before Performing Ordered Changes
July 08, 2019 —
Jonathan Schirmer - Ahlers Cressman & Sleight PLLCAs federal contractors may be aware, the general rule when performing a contract for the federal government is that only the contracting officer (“CO”) can bind the government. Often, the CO delegates responsibility to a contracting officer’s representative (“COR”). While in some cases a COR may be able to bind the federal government, the contract may limit that ability exclusively to the CO.
Important for our clients, it is the responsibility of the contractor to determine whether the COR can legally bind the federal government when ordering changes to the scope of work. [1] This is true even when a COR possesses apparent authority to order changes to the work, and when the project is almost exclusively overseen by COR’s. [2]
A recent case highlights the dangers of a contractor relying on the orders of a COR when performing work outside the scope of a contract. In Baistar Mechanical Inc., a contractor was awarded a maintenance and snow removal contract with the federal government. The contract expressly stated that only the CO had contracting authority regarding additional or changed work. [3] However, Baistar, the contractor, argued it was directed by the contracting officer’s representatives to perform work outside of the contract.
Read the court decisionRead the full story...Reprinted courtesy of
Jonathan Schirmer, Ahlers Cressman & Sleight PLLCMr. Schirmer may be contacted at
jonathan.schirmer@acslawyers.com
Deleted Emails Cost Company $3M in Sanctions
January 13, 2017 —
Grace V. Hebbel - Saxe Doernberger & Vita, P.C. BlogRecently, the Federal District Court for the District of Delaware imposed $3 million in punitive sanctions in order to redress harms caused by a company’s bad faith deletion of tens of thousands of emails during the course of litigation. The sanctions were ordered pursuant to Federal Rule of Civil Procedure 37, which was amended effective December 1, 2015 to permit sanctions for the failure to preserve electronically stored information (“ESI”).
In GN Netcom, Inc. v. Plantronics, Inc.,1 the plaintiff, GN Netcom, brought an antitrust suit alleging that the defendant company, Plantronics, interfered with distributors to stop GN Netcom from marketing its product. Upon receipt of GN Netcom’s demand letter, Plantronics issued a litigation hold and began providing training sessions to its employees to ensure compliance. Upon filing of GN Netcom’s suit, Plantronics issued an updated litigation hold and continued training sessions.
Read the court decisionRead the full story...Reprinted courtesy of
Grace V. Hebbel, Saxe Doernberger & Vita, P.C.Ms. Hebbel may be contacted at
gvh@sdvlaw.com
Builder Waits too Long to Dispute Contract in Construction Defect Claim
May 10, 2012 —
CDJ STAFFThe Louisiana Court of Appeals has affirmed the lower court’s judgment in the case of Richard v. Alleman. The Richards initiated this lawsuit under Louisiana’s New Home Warranty Act, claiming that they had entered into a construction contract with Mr. Alleman and that they quickly found that his materials and methods had been substandard. They sued for the cost of repairing the home and filing the lawsuit. Mr. Alleman countersued, claiming the Richards failed to pay for labor, materials, and services. By his claim, they owed him $12,838.80.
The trial court split the issues of liability and damages. In the first trial, the court concluded that there was a contact between Alleman and the Richards and that the New Home Warranty Act applied. Mr. Alleman did not appeal this trial.
The second trial was on the issue of damages. Under the New Home Warranty Act, the Richards were found to be entitled to $36,977.11 in damages. In a second judgment, the couple was awarded $18,355.59 in attorney’s fees. Mr. Alleman appealed both judgments.
In his appeal, Alleman contended that the trial court erred in determining that the Home Warranty Act applied. This was, however, not the subject of the trial, having been determined at the earlier trial. Nor did the court accept Alleman’s claim that the Richards failed to comply with the Act. The trial record made clear that the Richards provided Alleman with a list of problems with their home by certified mail.
The court did not establish whether the Richards told Alleman to never return to their home, or if Alleman said he would never return to the home, but one thing was clear: Alleman did not complete the repairs in the list.
A further repair was added after the original list. The Richards claimed that with a loud noise, a large crack appeared in their tile flooring. Mr. Alleman stated that he was not liable for this as he was not given a chance to repair the damage, the Richards hired the flooring subcontractors, and that the trial court rejected the claim that the slab was defective. The appeals court found no problem with the award. Alleman had already “refused to make any of the repairs.”
Finally Alleman made a claim on a retainage held by the Richards. Since Alleman did not bring forth proof at trial, the appeals court upheld the trial courts refusal to award a credit to Alleman.
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
Road Project to Improve Access to Peru's Machu Picchu Site
June 04, 2024 —
C.J. Schexnayder - Engineering News-RecordReaching the Incan citadel of Machu Picchu is historically famous for its difficulty. The site’s remote location was a factor in the Spanish conquistadors overlooking it as they swept Peru for its riches. Archaeologist and politician Hiram Bingham had been seeking another “lost” Incan city when he happened across it in 1911.
Reprinted courtesy of
C.J. Schexnayder, Engineering News-Record
Mr. Schexnayder may be contacted at schexnayderc@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
School District Gets Expensive Lesson on Prompt Payment Law. But Did the Court Get it Right?
February 26, 2015 —
Garret Murai – California Construction Law BlogMy kids don’t like riding in my car.
I urge them to look outside the window (I don’t have DVD), suggest that they roll down their windows to get some fresh air (rather than have me turn on the A/C) and persist on listening to that archaic device called the radio (I don’t “stream”).
Plus, I make them play “Dad Games.” Like Synonyms.
In Synonyms, I say a word, and the next person has to come up with a synonym for that word until someone can’t think of another synonym. Sometimes, I take a walk on the wild side, and play “Antonyms.”
Things can get heated, though. Like when someone says a word and there is a disagreement over whether that word is a synonym or not.
The next case, FTR International, Inc. v. Rio School District, California Court of Appeal for the Second District, Case No. B238618 (January 27, 2015), also involved a disagreement over synonyms . . . except that the loser had to cough up nearly $10 million.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel Rosen Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com
Exploring the Future of Robotic Construction with Dr. Thomas Bock
November 06, 2023 —
Aarni Heiskanen - AEC BusinessIn
this episode of the AEC Business podcast, host Aarni Heiskanen interviews Dr. Thomas Bock, a renowned expert in construction robotics. With 45 years of experience in the field and multiple books on the topic, Thomas shares his insights and expertise.
Tune in to learn more about his professional journey and the advancements in construction robotics.
An unconventional professional journey
Thomas’s journey in construction robotics began when he built his own house as a student. The labor-intensive process led him to explore the potential of robotics in construction. He studied civil engineering and architecture simultaneously, gaining a multidisciplinary understanding of the field. His interest in robotics grew when he saw the first welding robot at a Daimler-Benz factory in Stuttgart. This encounter sparked his curiosity and led him to question why robots couldn’t be used for assembling walls and buildings.
The Illinois Institute of Technology (IIT) in Chicago was one of Thomas’s destinations during his journey. There he studied under professors who had worked on iconic architectural projects. He also learned about Japanese companies like Toyota and Sekisui, which were producing houses using innovative methods. Intrigued by these advancements, Thomas secured a scholarship to study in Japan, where he discovered that the country was ahead of what he had known in the United States.
Read the court decisionRead the full story...Reprinted courtesy of
Aarni Heiskanen, AEC BusinessMr. Heiskanen may be contacted at
aec-business@aepartners.fi
Comparing Contracts: A Review of the AIA 201 and ConsensusDocs - Part II
March 28, 2018 —
Michael Sams and Amanda Cox – Construction Executive, A publication of Associated Builders and Contractors. All Rights Reserved.Part II of this three-part series compares and analyzes important contract sections in the AIA 201 (2007 and 2017 versions) and ConsensusDocs (2014 and 2017 versions), including Schedule/Time, Consequential Damages/LDs, Claims and Disputes/ADR.
Part I covered Financial Assurances, Design Risk, Project Management and Contract Administration. Part III will cover Insurance and Indemnification and Payment.
SCHEDULE/TIME
Relevant Sections:
- 2007 & 2017 A201: Section 3.10.1
- 2014 & 2017 ConsensusDocs: Section 6.2
AIA:
- Section 3.10.1 of the 2007 A201 requires that the Contractor promptly after being awarded the Contract, prepare and submit a construction schedule providing for Work to be completed within the time limits required in the Contract Documents.
- This schedule shall be revised at appropriate intervals.
- The 2017 edition breaks down the schedule to contain date of commencement, interim milestone dates, date of substantial completion, apportionment of Work by trade or building system, and the time required for completion of each portion of the Work.
- Under section 3.10.2 of the 2007 and 2017 versions, if the Contractor fails to provide a submittal schedule, the Contractor is not entitled to any additional compensation or a time extension based on the Owner’s or the Architect’s slow processing of submittals, regardless of how long they take.
ConsensusDocs 200:
- The 2017 Contract replaces the term Contract Time and instead requires a “Schedule of the Work…formatted in detailed precedence-style critical path method that (a) provides a graphic representation of all activities and events, including float values that will affect the critical path of the Work and (b) identifies dates that are critical to ensure timely and orderly completion of the Work.”
- The Constructor must submit an initial schedule to the Owner only before, “first application for payment” and thereafter on a monthly basis. (Section 6.2.1).
- The Owner is allowed to change the sequences provided in the schedule as long as it does not “unreasonably interfere with the Work.” (Section 6.2.2).
Reprinted courtesy of
Michael Sams , Kenney & Sams and
Amanda Cox, Kenney & Sams
Read the court decisionRead the full story...Reprinted courtesy of
Assembly Bill 1701 Contemplates Broader Duty to Subcontractor’s Employees by General Contractor
August 17, 2017 —
Richard H. Glucksman, Esq. & Chelsea L. Zwart, Esq. – Chapman Glucksman Dean Roeb & BargerAB 1701 recently passed the Assembly and is pending in the Senate’s Labor and
Industrial Relations and Judiciary Committees. The Bill, if signed by the Governor, would
create a new section in the California Labor Code (Section 218.7) making “direct contractors” –
defined as a contractor “making or taking a contract in the state for the erection, construction,
alteration, or repair of a building, structure, or other private work” – liable for wages a
subcontractor or sub-subcontractor fails to pay to its employee for work included in the general
contractor’s contract with the project owner.
Under the new law, direct contractors would be liable for up to one year from the date of
completion of the work for unpaid wages, fringe benefits, health and welfare benefits, and
pension fund contributions, including interest and state tax payments owed to a subcontractor’s
employee. The employee, however, would not be able to recover penalties or liquidated
damages from the general contractor.
AB 1701 would give the employee, Labor Commissioner, or a joint labor-management
cooperation committee the right to enforce the direct contractor’s liability through a civil action.
It would also extend to third parties who are owed fringe or other benefit payments or
contributions on the employee’s behalf. Pursuant to the proposed language of the new statute, a
prevailing plaintiff in such an action would be entitled to their reasonable attorneys’ fees and
costs, including expert witness fees.
Although Labor Code § 218.7 would impose certain obligations on the subcontractor to
provide the direct contractor with relevant project and payroll records, the subcontractor’s failure
to comply with those obligations does not relieve the direct contractor from liability.
Impact
AB 1701’s apparent purpose is to protect employees, an undeniably important legislative
goal. However, if passed, the bill could greatly increase general contractors’ exposure when
subcontracting work and their cost of doing business. Especially because the new law would not
impact existing laws requiring a direct contractor to timely pay a subcontractor.
As a result, many coalitions against AB 1701 stress the halting effect this could have on
the construction industry as a whole, particularly private construction, which is not as heavily
regulated as public works.
CGDRB will continue to monitor this Bill and provide updates as developments occur.
Reprinted courtesy of
Richard H. Glucksman, Chapman Glucksman Dean Roeb & Barger and
Chelsea L. Zwart, Chapman Glucksman Dean Roeb & Barger
Mr. Glucksman may be contacted at rglucksman@cgdrblaw.com
Ms. Zwart may be contacted at czwart@cgdrblaw.com
Read the court decisionRead the full story...Reprinted courtesy of