Fourth Circuit Holds that a Municipal Stormwater Management Assessment is a Fee and Not a Prohibited Railroad Tax
April 22, 2019 —
Anthony B. Cavender - Gravel2GavelOn February 15, the U.S. Court of Appeals for the Fourth Circuit decided Norfolk Southern Railway Co. v. City of Roanoke, et al.; the Chesapeake Bay Foundation was an Intervenor-Defendant. The Fourth Circuit held that a large stormwater management fee (stated to be $417,000.00 for the year 2017) levied by the City of Roanoke against the railroad to assist in the financing of the City’s permitted municipal stormwater management system was a permissible fee and not a discriminatory tax placed on the railroad.
The Railroad Revitalization and Regulatory Reform Act of 1976 specifically provides that states and localities may not impose any tax that discriminates against a rail carrier, 49 U.S.C. § 11501. Accordingly, the issue confronting the Fourth Circuit was whether the assessment was fee and not a tax.
Read the court decisionRead the full story...Reprinted courtesy of
Anthony B. Cavender, PillsburyMr. Cavender may be contacted at
anthony.cavender@pillsburylaw.com
Toward Increased Citizen Engagement in Urban Planning
November 14, 2018 —
Aarni Heiskanen - AEC BusinessDigitalization creates new opportunities for citizen engagement in urban planning. I gave a short presentation on the topic at the Digitalization in Urban Planning event in Helsinki.
The event was organized by CHAOS Architects, a tech company. Its AI cloud platform allows citizens to share ideas about their city and co-create it with their community. The platform contains engagement-driven applications and third-party APIs that process business intelligence for better interaction and decision-making.
Read the court decisionRead the full story...Reprinted courtesy of
Aarni Heiskanen, AEC BusinessMr. Heiskanen may be contacted at
aec-business@aepartners.fi
Whether Subcontractor's Faulty Workmanship Is an Occurrence Creates Ambiguity
March 16, 2017 —
Tred R. Eyerly – Insurance Law HawaiiThe Ohio Court of Appeals determined that the CGL policy was ambiguous as to whether a subcontractor's faulty workmanship was an "occurrence." Ohio N. Univ. v. Charles Constr. Serv., 2017 Ohio App. LEXIS 258 (Ohio Ct. App. Jan. 23, 2017).
In 2007, Ohio Northern University (ONU) entered a contract with Charles Construction Services, Inc. (CCS) to construct a hotel on the campus. In 2011, the building was completed, but ONU found water intrusion and moisture damage in the interior. When remediating the water damage, ONU found additional, serious structural defects.
ONU sued CCS, alleging breach of contract, breach of express warranty, and negligent misrepresentation. CCS filed a third-party action against many of its subcontractors. Cincinnati Insurance Company (CIC) intervened and filed a cross-claim for a declaratory judgment that it had no duty to provide coverage to CCS. CIC and ONU filed cross motions for summary judgment.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
New York Office Secures Appellate Win in Labor Law 240(1) Fall in Basement Accident Case
March 20, 2023 —
Nicholas P. Hurzeler & Gregory S. Katz - Lewis BrisboisNew York, N.Y. (March 14, 2023) – New York Appellate Partner Nicholas P. Hurzeler and Managing Partner Gregory S. Katz recently prevailed when the New York Appellate Division, Second Department affirmed the dismissal of a Labor Law 240(1) claim involving an accident that occurred in the basement of a house under construction. Balfe v. Graham, ___ AD3d ___ (2d Dept. 2023), decided March 8, 2023.
In this matter, the plaintiff was installing ductwork in the basement of a house that had been stripped down to its foundation when he stepped backwards into an open hole that had been dug out of a concrete floor to accommodate the installation of an ejector pump. The lower court dismissed the plaintiff’s claim based on Labor Law 240(1), and he appealed. The plaintiff argued that he fell into an unprotected opening that should have been covered or barricaded. He further claimed the accident qualifies as a typical “falling worker” case within the scope of Labor Law 240(1), citing the depth of the hole needed to accommodate the ejector pump, and the size of the pump. Under the case law, a worker who falls into an uncovered opening on a construction site will typically be covered by Labor Law 240(1).
Reprinted courtesy of
Nicholas P. Hurzeler, Lewis Brisbois and
Gregory S. Katz, Lewis Brisbois
Mr. Katz may be contacted at Greg.Katz@lewisbrisbois.com
Mr. Hurzeler may be contacted at Nicholas.Hurzeler@lewisbrisbois.com
Read the court decisionRead the full story...Reprinted courtesy of
Your Contract is a Hodgepodge of Conflicting Proposals
January 06, 2016 —
Craig Martin – Construction Contractor AdvisorOuch. That’s what a court called a contract to remediate petroleum contamination at a number of gas stations in New York. Sometimes, it’s hard to believe the contracts that get signed.
Environmental Risk hired Science Applications to remediate petroleum contamination at 47 gas stations. Environmental Risk had previously entered into a Professional Services Master Agreement with Science Applications, but also required Science Applications to sign three separate, but basically identical, subcontracts called the Project Specific Scopes of Work. So, right from the start, there were four contracts that could apply to Science Applications’ work.
Read the court decisionRead the full story...Reprinted courtesy of
Craig Martin, Lamson, Dugan and Murray, LLPMr. Martin may be contacted at
cmartin@ldmlaw.com
California Supreme Court Shifts Gears on “Reverse CEQA”
February 23, 2016 —
Garret Murai – California Construction Law BlogThe California Supreme Court has shifted gears on so-called “reverse CEQA” under the California Environmental Quality Act (“CEQA”).
The Supreme Court, in a much-anticipated decision, in California Building Industry Association v. Bay Area Air Quality Management District, Case No. S213478 (December 17, 2015), held that public agencies subject to CEQA are not required to analyze whether existing environmental conditions may impact a proposed project’s future users or residents – also known as “reverse CEQA” or “CEQA in reverse” – as opposed to the more traditional analysis of a proposed project’s impact on the environment, unless:
1. The proposed project risks exacerbating existing environmental hazards – in which case, it is the proposed project’s impact on the environment not the environment’s impact on the proposed project, which compels the evaluation; or
2. A reverse CEQA analysis is already required under statute, for example, on certain airport, school and housing projects.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel Rosen Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com
Consider Short-Term Lease Workouts For Commercial Tenants
August 17, 2020 —
Steven Ostrow, C. Jason Kim & Patrick Haggerty - White and WilliamsThe COVID-19 pandemic is adversely affecting commercial real estate as it continues to wreak havoc in industries throughout the economy. For many years, the primary declining CRE sector has been brick and mortar retail stores. However, the retail sector is no longer suffering alone, as the COVID-19 outbreak is hurting most other CRE sectors: office, hospitality, multifamily, restaurant, personal services, entertainment and construction.
Federal, state and local governments have ordered business shutdowns and social and travel restrictions limiting most social and commercial activities. As a result, commercial tenants throughout the country are going out of business, temporarily closing, curtailing operations, laying off employees and suffering sharply declining revenues.
Short-Term Leasing Workouts of Tenant Defaults
Thousands of tenants are partially operating or temporarily closed and lack sufficient cash flow or access to additional working capital to pay some or all of their rent. How should a landlord address a distressed tenant's default and request for rent relief, taking into account the landlord's own responsibilities to pay maintenance costs, real estate taxes and debt service on the property?
Reprinted courtesy of White and Williams attorneys
Steven Ostrow,
C. Jason Kim and
Patrick Haggerty
Mr. Ostrow may be contacted at ostrows@whiteandwilliams.com
Mr. Kim may be contacted at kimcj@whiteandwilliams.com
Mr. Haggerty may be contacted at haggertyp@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of
California Enacts New Claims Resolution Process for Public Works Projects
January 19, 2017 —
Garret Murai – California Construction Law BlogIf you’re a public entity or contractor involved in public works construction you should be aware of a new law,
AB 626, which took effect on the first of this year and establishes a new mandatory claims resolution process for disputes on public works projects. Here’s what you need to know:
What is the new law and where is it codified at?
AB 626 added new Public Contract Code Section 9204 that according to the bill’s author, Assemblymember David Chiu of San Francisco, establishes “a claim resolution process applicable to any claim by a contractor in connection with a public works project.”
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel Rosen Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com