Construction Contract Basics: No Damages for Delay
May 06, 2024 —
Christopher G. Hill - Construction Law MusingsAfter WAY too long a hiatus, I am back with another in my series of “Construction Contract Basics” posts. In past posts, I’ve covered venue provisions, attorney fee provisions, and indemnity clauses. In this post, I’ll share a few thoughts (or “musings”) on the topic of so-called “no damages for delay” clauses. These clauses essentially state that a subcontractor’s only remedy for a delay caused by any factor beyond its control (including the fault of the general contractor), after proper notice to the owner or general contractor, is an extension of time to complete the work.
These types of clauses generally make it impossible for a subcontractor (if found in a Subcontract) or Contractor (if found in a Prime Contract) that is delayed through no fault of its own to recover any damages relating to the expenses that are inevitably caused by such delays. Such expenses/damages could include additional supervisory time (including more high-dollar superintendent payments), acceleration costs, demobilization/mobilization costs, and other related expenses. These can add up to real money. Couple that with the inevitable liquidated damages or delay damages that will occur should a contractor or subcontractor cause any delay, and this becomes a very one-sided proposition.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Michigan Court Waives Goodbye to Subrogation Claims, Except as to Gross Negligence
March 13, 2023 —
Lian Skaf - The Subrogation StrategistIn Ace American Insurance Company, et. al. v. Toledo Engineering Co., Inc., et. al., No. 18-11503, 2023 U.S. Dist. LEXIS 15222 (Ace American), the United States District Court for the Eastern District of Michigan determined whether insurers could pursue their subrogation claims against the defendants despite a waiver of subrogation in each of the contracts the insured had with the respective defendants. Based on the language of the contracts and the circumstances leading up to the loss, the court held that the insurers could not pursue their subrogation claims – other than their claims for gross negligence – due to waivers of subrogation in the applicable contracts.
In Ace American, the insured, Guardian Industries, LLC (Guardian), retained Toledo Engineer Co., Inc. (TECO) and Dreicor, Inc. (Dreicor) to renovate a glass furnace in the insured’s glass manufacturing plant. Guardian and TECO entered into a contract on December 6, 2016. Guardian and Dreicor entered into a contract on September 29, 2013, that the parties later updated on June 3, 2016. Both defendants began work on the project in the spring of 2017 and were finished with the portion of the work known as the “Cold Tank Repair” prior to the loss.
On June 3, 2017, there was an explosion and fire at the plant that caused significant property damage. The plaintiff insurers (Plaintiffs) made payments in the amount of $80 million and became subrogated to its insured’s rights. Plaintiffs then initiated this action.
Read the court decisionRead the full story...Reprinted courtesy of
Lian Skaf, White and Williams LLPMr. Skaf may be contacted at
skafl@whiteandwilliams.com
The Benefits of Trash Talking: A Cautionary Tale of Demolition Gone Wrong
September 02, 2024 —
Joshua Levy, Anne O'Meara & Kimberly Gutierrez - Construction ExecutiveThat sinking feeling has crossed everyone’s mind at some point: "Did I accidentally throw out...?” It can happen to anyone, from valuable jewelry to uncashed checks or even (in the case of one contractor) to fire-pump control cabinets.
Demolishing the wrong equipment is a concern construction and demolition contractors should review before beginning any project. Recently, one general contractor and its demolition subcontractor would have benefitted from a more detailed “trash” talking session, which could have helped them avoid a dumpster-fire of a legal dispute.
In this case, the general contractor was contracted to renovate a hangar for a military base. The company subcontracted the demolition work to a local, family-owned contractor to demolish aspects of the hangar’s fire-suppression room. The two companies met many times, from planning to daily field walk-downs. They discussed that any equipment that was tagged with bright orange tags would remain in the fire-suppression room. The contractor also reviewed the demolition plans with the demolition company, detailing what should and should not be removed.
Reprinted courtesy of
Joshua Levy, Anne O'Meara & Kimberly Gutierrez, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Delay In Noticing Insurer of Loss is Not Prejudicial
April 28, 2014 —
Tred R. Eyerly – Insurance Law HawaiiThe Tenth Circuit reversed a district court's determination that untimely notice of the loss was prejudicial, eliminating the insurer's coverage obligations. B.S.C. Holding, Inc. v. Lexington Ins. Co., 2014 U.S. App. LEXIS 4492 (10th Cir. March 11, 2014).
In January 2008, the insured's employees detected an inflow of water in a salt mine and feared dissolution of the salt or structural problems. The insured tried to devise a solution. Two and a half million dollars were spent to find the cause of the water inflow and to identify a solution. In April 2010, the insured determined the inflow was caused by an improperly sealed oil well. In July 2010, the insured notified Lexington of the water inflow. The ultimate proof of loss was for $7.5 million, which included remediation measures that the insured had performed before notifying Lexington.
Lexington's all-risk policy required the insured to notify the company in writing as soon as practicable.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Sometimes a Reminder is in Order. . .
February 18, 2020 —
Christopher G. Hill - Construction Law MusingsRecently, I was talking with my friend Matt Hundley about a recent case he had in the Charlottesville, VA Circuit Court. It was a relatively straightforward (or so he and I would have thought) breach of contract matter involving a fixed price contract between his (and an associate of his Laura Hooe) client James River Stucco and the Montecello Overlook Owners’ Association. I believe that you will see the reason for the title of the post once you hear the facts and read the opinion.
In James River Stucco, Inc. v. Monticello Overlook Owners’ Ass’n, the Court considered Janes River Stucco’s Motion for Summary Judgment countering two arguments made by the Association. The first Association argument was that the word “employ” in the contract meant that James River Stucco was required to use its own forces (as opposed to subcontractors) to perform the work. The second argument was that James River overcharged for the work. This second argument was made without any allegation of fraud or that the work was not 100% performed.
Needless to say, the Court rejected both arguments. The Court rejected the first argument stating:
In its plain meaning, “employ” means to hire, use, utilize, or make arrangements for. A plain reading of the contractual provisions cited–“shall employ” and references to “employees”–and relied on by Defendant does not require that the persons performing the labor, arranged by Plaintiff, be actual employees of the company or on the company’s payroll. It did not matter how the plaintiff accomplished the work so long as it was done correctly. The purpose of those provisions was to allocate to Plaintiff responsibility for supplying a sufficient workforce to get the work done, not to impose HR duties or require the company to use only “in house” workers. So I find that use of contracted work does not constitute a breach of the contract or these contractual provisions.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Deference Given To Procuring Public Agency Regarding Material Deviation
April 10, 2019 —
David Adelstein - Florida Construction Legal UpdatesDeference will be given to a procuring public agency in a bid protest, particularly when the issue involves whether a bid is non-responsive and constitutes a material deviation from the solicitation. You do not believe me? Perhaps you will after this holding in Biscayne Marine Partners, LLC v. City of Miami, Florida, 44 Fla.L.Weekly D467a (Fla. 3d DCA 2019):
Consequently, no principle of law is clearly established…as to any obligation of the trial court (and, by analogy, an administrative hearing officer) [in a bid protest] to decide or to defer [whether a bid constitutes a material deviation from the solicitation]. If anything, the existing and clearly established principle of law inclines toward judicial deference in public agency competitive bidding disputes when the agency has exercised it discretion absent illegality, fraud, oppression or misconduct.
I do not know about you, but that last underlined sentence is pretty strong language regarding judicial deference!
In this case, Miami (the procuring public agency) issued a Request for Proposals (RFP) for the redevelopment and lease of waterfront property, for the operation of a marina, boatyard, restaurant, wet slips, and a dry storage facility on the property. Miami issued five addenda to the RFP. There were three bidders.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com
Administration Launches 'Buy Clean' Construction Materials Push
February 28, 2022 —
James Leggate - Engineering News-RecordThe Biden administration is moving to put U.S. government purchasing power behind construction materials with lower embodied carbon emissions and pollutants, with the White House launching a “Buy Clean Task Force” on Feb. 15. as part of a slate of initiatives intended to decarbonize manufacturing while boosting the economy.
Reprinted courtesy of
James Leggate, Engineering News-Record
Mr. Leggate may be contacted at leggatej@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Pile Test Likely for Settling Millennium Tower
October 04, 2021 —
Nadine M. Post - Engineering News-RecordA pilot pile program to prove the efficacy of a less-disruptive method for the paused foundation fix at the ailing Millennium Tower in San Francisco could begin the week of Oct. 4. Accelerated settling and tilt—caused by a pile upgrade intended to correct settlement of the 645-ft-tall residential condominium—ceased after Aug. 20, when the engineer-of-record halted the $100-million fix.
Reprinted courtesy of
Nadine M. Post, Engineering News-Record
Ms. Post may be contacted at postn@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of