Lucky No. 7: Seventh Circuit Court of Appeals Issues Pro-Policyholder Decision Regarding Additional Insured Coverage for Upstream Parties
November 02, 2020 —
Daniela Aguila - Saxe Doernberger & VitaIn Scottsdale Ins. Co. v. Columbia Ins. Group, Inc,1 the Seventh Circuit Court of Appeals recently held that a subcontractor’s insurer was obligated to defend and indemnify the project owner’s insurer for damages associated with the subcontractor's employee's personal injury lawsuit where the underlying complaint alleged negligence by the additional insureds. The case cements the notion that under Illinois law, one can significantly benefit from the facts presented in third party complaints as a basis for additional insured coverage.
Rockwell Properties (“Rockwell”) was the project owner, along with Prairie Management & Development (“Prairie”), the general contractor, on a construction project in Chicago. Prairie subcontracted HVAC services to TDH Mechanical (“TDH”). When an employee of TDH Mechanical sustained serious injuries performing work at a construction site, a suit was lodged against Rockwell and Prairie in state court. The lawsuit did not bring any claims against TDH but instead alleged that both Rockwell and Prairie had negligently failed to supervise the subcontractors’ work on-site, thus contributing to the worker’s injuries.
Read the court decisionRead the full story...Reprinted courtesy of
Daniela Aguila, Saxe Doernberger & VitaMs. Aguila may be contacted at
dag@sdvlaw.com
Nevada Insureds Can Rely on Extrinsic Facts to Show that An Insurer Owes a Duty to Defend
November 15, 2021 —
Sarah J. Odia & Scott S. Thomas - Payne & FearsOn Oct. 28, 2021, the Nevada Supreme Court in Zurich American Insurance Company v.. Ironshore Specialty Insurance Company, 137 Nev. Adv. Op. 66, held that an insured can rely on extrinsic facts to show that an insurer has a duty to defend the insured, as long as the facts were available to the insurer at the time the insured tendered the claim. The court also held that an insured has the burden of proving that an exception to an exclusion in an insurance policy applies to create a duty to defend.
In Zurich, Ironshore refused to defend to its insured against multiple property damage claims arising out of construction defects, claiming that its policies’ continuing and progressive damage exclusions barred coverage. The underlying lawsuits made no specific allegations describing when or how the property damage occurred. Ironshore claimed that the property damage had occurred due to faulty work that predated the commencement of its policies. Two different federal trial courts came to conflicting conclusions in the underlying cases. One held that Ironshore had a duty to defend because Ironshore failed to show that an exception to the exclusion did not apply. The second granted summary judgment in favor of Ironshore holding that the insured failed to meet its burden of proving that an exception to the exclusion applied.
Reprinted courtesy of
Sarah J. Odia, Payne & Fears and
Scott S. Thomas, Payne & Fears
Ms. Odia may be contacted at sjo@paynefears.com
Mr. Thomas may be contacted at sst@paynefears.com
Read the court decisionRead the full story...Reprinted courtesy of
Baby Boomer Housing Deficit Coming?
October 29, 2014 —
Beverley BevenFlorez-CDJ STAFFAccording to Builder magazine, a new study by Epcon Franchising and Metrostudy found that “10 metro areas are expected to have a significant housing gap for baby boomers.” Furthermore, “52 percent of new-home buyers will be over 55 in the next five years.”
Builder listed the top 10 markets that are expected to have a baby boomer housing deficit. The top three are Dallas-Fort Worth, Houston, and the District of Columbia.
Read the court decisionRead the full story...Reprinted courtesy of
Craig Holden Named Top 100 Lawyer by Los Angeles Business Journal
June 27, 2022 —
Craig Holden - Lewis BrisboisLos Angeles, Calif. (May 17, 2022) - Los Angeles Partner Craig Holden has been named to the Los Angeles Business Journal’s (LABJ) “Top 100 Lawyers” list, which recognizes the most impactful attorneys in the Los Angeles region for their ongoing efforts as outstanding legal professionals. The attorneys on the list were honored on May 12 at LABJ’s inaugural Top 100 Lawyers Awards at the ASU California Center.
In the publication’s special section, LABJ Publisher Josh Schimmels noted that the attorneys on the Top 100 Lawyers list “have demonstrated exceptional legal skill and achievements across the full spectrum of responsibility, exemplary leadership and contributions to the Los Angeles community at large.” He also observed, “Considering the fact that the Los Angeles region has long been known for its status as a hub for legal [through] leaders and record-setting attorneys, being a standout in that field is particularly impressive.”
Likewise, in discussing his inclusion on the list, Mr. Holden remarked, “I am honored to be included on this list with so many exceptional attorneys from the LA legal community.”
Read the court decisionRead the full story...Reprinted courtesy of
Craig Holden, Lewis BrisboisMr. Holden may be contacted at
Craig.Holden@lewisbrisbois.com
California Appeals Court Remands Fine in Late Completion Case
November 18, 2011 —
CDJ STAFFThe California Court of Appeals in Stanislaus County has reversed the decision of the lower court in Greg Opinski Construction Inc. v. City of Oakdale. The earlier court had awarded the city of judgment of $54,000 for late completion, $3,266 for repair of construction defects and interest, and $97,775 in attorneys’ fees. The late completion of the project was due to actions by the City of Oakdale, however, the court rejected Opinski’s argument that the California Supreme Court decision in Kiewit did not allow this, as his contract with the city established a procedure for claiming extensions.
The appeals court noted that the Kiewit decision has been “criticized as an unwarranted interference in the power of contracting parties to shift the risk of delays caused by one party onto the other party by forcing the second party to give the first notice of any intention to claim an extension of time based on delays caused by first.” They cited Sweet, a professor at Boalt Hall, UC Berkeley’s law school, that Kiewit “gutted” the “provision that conditions the contractor’s right to claim an extension of time for delays beyond his control.”
Further changes in California law in response to the Kiewit decision lead to the current situation which the court characterized as “if the contractor wished to claim it needed an extension of time because of delays caused by the city, the contractor was required to obtain a written change order by mutual consent or submit a claim in writing requesting a formal decision by the engineer.”
Opinski also argued that the lower court misinterpreted the contract. The Appeals court replied that “Opinski is mistaken.” He cited parts of the contract regarding the increase of time, but the court rejected these, noting that “an inability to agree is not the same as an express rejection.”
The court also rejects Opinski’s appeal that “the evidence the project was complete earlier than September 30, 2005, is weightier than the evidence to the contrary,” which they describe as “not a winning appellate argument.” The court points out that the role of an appeals court is not to reweigh the evidence, but to determine “whether the record contains substantial evidence in support of the judgment.”
The court did side with Opinski on one question of the escrow account. They rejected most of his arguments, repeating the line “Opinski is mistaken” several times. They decided that he was mistaken on the timing of the setoff decision and on whether the city was the prevailing party. However, the appeals court did find that Opinski was not liable for interest on the judgment.
The appeals court rejected the awarding of prejudgment interest to the city as the funds from which the judgment was drawn was held in an escrow account. The court noted that the city had access to the funds and could “access the funds when it determined that Opinski had breached the contract.” The appeals court noted that the judgment exhausted the escrow balance and remanded the case to the lower court to determine the amount own to Opinski.
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
Colorado Senate Bill 13-052 Dies in Committee
May 10, 2013 —
David M. McLainOn April 17, 2013, the Colorado Senate Judiciary Committee voted, along party lines, to postpone indefinitely SB 52. Here is a link to the Denver Business Journal's story regarding the bill and its untimely demise: "Lawmakers kill lawsuit limits on condo defects."
Unfortunately, it will be at least another year before the legislature will have the ability to provide some much needed relief to the Colorado construction industry.
Read the court decisionRead the full story...Reprinted courtesy of
David M. McLainMr. McLain can be contacted at
mclain@hhmrlaw.com
Gain in Home Building Points to Sustained U.S. Growth
October 22, 2014 —
Michelle Jamrisko and Danielle Trubow – BloombergBuilders started work on more homes in September and American consumers this month were the most optimistic in seven years, signaling the U.S. economy will ride out a global slowdown.
Housing starts climbed 6.3 percent to a 1.02 million annualized rate from a 957,000 pace in August as multifamily and single-family projects advanced, the Commerce Department reported today in Washington. The Thomson Reuters/University of Michigan preliminary sentiment index for October increased to 86.4, the strongest since July 2007, another report showed.
Gains in residential construction will help underpin the economic expansion as the recent drop in mortgage rates lifts home sales and gives builders reason to take on more projects. Other figures showing factory production rebounded last month and claims for jobless benefits dropped last week to the lowest level in 14 years added to evidence the turbulence in global markets has yet to depress the world’s largest economy.
Ms. Jamrisko may be contacted at mjamrisko@bloomberg.net; Ms. Trubow may be contacted at dtrubow@bloomberg.net
Read the court decisionRead the full story...Reprinted courtesy of
Michelle Jamrisko and Danielle Trubow, Bloomberg
Force Majeure and COVID-19 in Construction Contracts – What You Need to Know
April 06, 2020 —
Brenda Radmacher & Jason Suh - Gordon & Rees Construction Law Blog“Force Majeure” – While most construction contracts contain these provisions, they are often not understood in relation to the implications they may have on construction projects. With the onset of the COVID-19 pandemic, we are all taking a closer look at many portions of our contracts. The following is a brief primer on how to understand your construction contract and its potential implications on your business in this season of change.
What is a Force Majeure?
Construction contracts usually take into consideration that the parties want to agree at the outset on who bears the risk of unforeseen incidents that may affect the project’s progression. These issues are generally handled in a “force majeure” clause. Force majeure, according to Mariam Webster’s Dictionary is a “superior or irresistible force; or an event or effect that cannot be reasonably anticipated or controlled.” To be deemed a force majeure, generally the circumstances must be outside of a party’s control which makes performance impossible, inadvisable, commercially impractical, or illegal. In addition to being unforeseeable, the circumstances must have external causation, and be unavoidable. However, the key to understanding if COVID-19 will be deemed a condition that will excuse a contractor’s performance is the specific language in the provision.
Generally force majeure events are unavoidable events such as “acts of God,” most notably weather conditions including hurricanes, tornadoes, floods, earthquakes, landslides, and wildfires, as well as certain man-made events like riots, wars, terrorism, explosions, labor strikes, and scarcity of energy supplies. However, there is not much case law or specifics on conditions similar to COVID-19.
Reprinted courtesy of
Brenda Radmacher, Gordon & Rees and
Jason Suh, Gordon & Rees
Ms. Radmacher may be contacted at bradmacher@grsm.com
Mr. Suh may be contacted at jwsuh@grsm.com
Read the court decisionRead the full story...Reprinted courtesy of